Capital Programme 2025/26 – Capital Budget Variations

Approved Executive 1 paper

AI summaryCabinet approved 2025/26 capital budget changes covering housing delivery, UK Shared Prosperity Fund, Bramcote Leisure Centre design work and CCTV upgrades, with no adverse impact on overall capital financing.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFor 2025/26 schemes, as set out in the report
MoneyOriginal 2025/26 programme £34.966mVariations detailed across four scheme areas
What happens nextNot stated
Who it affectsNot stated

What was decided

Cabinet approved the capital budget variations for 2025/26 as set out in the report, with capital financing arrangements adjusted to match actual spend. Report P1, P4

No net impact on the Council's overall capital financing, as variations are covered by capital grants or previously agreed prudential borrowing. Report P4, P5

Why

Several capital schemes need budget amendments to more accurately reflect expectations in the current financial year, and the delivery of some schemes has slipped or accelerated beyond the Council's control. Report P4, P28

Bringing budgets into line with actual delivery, correcting a misclassified brought-forward UKSPF grant, and retaining specialist design management for the new Bramcote Leisure Centre. Report P37, P42

What happens next

Any further changes to the Capital Programme will be reported to Cabinet as necessary for approval. Report P6

A further Cabinet report will identify the capital funding arrangements for the construction stage of the replacement Bramcote Leisure Centre once design and planning are complete. Report P43

The money

  • £34.966m Total original Capital Programme for 2025/26 Report P3
  • £32.484m Original Capital Programme for 2025/26 excluding reserve items Report P3
  • £9.638m Overall cost of Land at Bramcote Crematorium new build scheme Report P30
  • 1,072,700 Budget brought forward for Land at Bramcote Crematorium new build Report P33
  • 2,02,700 Revised 2025/26 budget for Land at Bramcote Crematorium new build (as printed) Report P33
  • £350,000 New Build Housing Feasibility Costs budget after accumulated underspends brought forward Report P31, P34
  • £250,000 Proposed reduction back to original New Build Housing Feasibility Costs budget Report P31, P34
  • £1.057m UKSPF funding allocation for the Council in 2025/26 Report P36
  • £462,950 UKSPF capital budget recognised in the Capital Programme Report P36, P39
  • £300,750 Assumed UKSPF capital underspend brought forward, now to be removed Report P37, P39
  • £763,700 Total revised UKSPF capital budget before correction (as printed) Report P39
  • £135,000 Previous supplementary capital estimate for Bramcote Leisure Centre variation Report P41, P45
  • £935,000 Total uplifted RIBA Stage 4 budget for Bramcote Leisure Centre Report P41
  • £7,500 Monthly cost of retaining ReCreation for development management Report P42
  • £45,000 Additional budget proposed for Bramcote Leisure Centre development management fees, funded from General Fund capital receipts Report P42
  • £310,900 Revised total Bramcote Leisure Centre RIBA Stage 4 budget Report P45
  • £95,750 Safer Streets Fund award supporting the surveillance camera scheme Report P48
  • £19,500 Additional 2025/26 spend on surveillance camera upgrade, funded from external grant Report P48, P49

Options considered

  • Chosen: Approve the capital budget variations for 2025/26 as set out. To accurately reflect current-year expectations and keep capital financing arrangements in line with actual spend Report P1, P4

Implications

  • Financial: No adverse impact on overall capital financing; variations are met by capital grants or previously agreed prudential borrowing adjusted to match spend. Report P4
  • Financial: The UKSPF capital correction has no net impact on the Council's budget as the grant had already been used under revenue flexibilities. Report P37
  • Financial: New Build Housing Feasibility Costs budget is proposed to be reduced back to the original £250,000 level, funded from prudential borrowing. Report P31
  • Legal: No direct legal implications arising from the report. Report P14
  • Equalities: No equality impact assessment required as there is no change to policy. Report P24
  • Climate: Climate change response is a key consideration within the budget setting process generally. Report P20

Who and where

  • Housing Delivery Programme, including the new build scheme at Coventry Lane West (Land at Bramcote Crematorium) and Housing Feasibility Costs Report P27, P29, P31
  • Economic regeneration projects funded by the UK Shared Prosperity Fund, now administered via the East Midlands Combined County Authority Report P35, P36
  • Replacement Bramcote Leisure Centre project (RIBA Stage 4 design and planning approval) Report P40, P42
  • Community safety surveillance camera and wireless network upgrade scheme Report P46, P48

Timeline

  • 10 February 2022: Original CCTV surveillance camera upgrade and wireless network scheme approved by Finance and Resources Committee Report P47
  • 2023/24: Council awarded £95,750 from the Safer Streets Fund Report P48
  • 4 February 2025: Cabinet recommended the Capital Programme 2025/26 to 2027/28 Report P3
  • 5 March 2025: Council approved the Capital Programme 2025/26 to 2027/28 Report P3
  • 11 March 2025: Cabinet reported on UKSPF funding allocation for 2025/26 Report P36
  • 29 July 2025: Cabinet approved a £135,000 supplementary capital estimate for the Bramcote Leisure Centre scheme variation Report P41
  • November 2025 to January 2026: ReCreation development management work covering the Bramcote Leisure Centre planning application stage Report P42
  • 3 February 2026: Cabinet considered this report on capital budget variations Report P10, P25
  • 2027/28: Anticipated final completion of the Land at Bramcote Crematorium new build scheme Report P30

Plain English for the jargon

  • RIBA Stage 4: Royal Institute of British Architects design stage covering detailed technical design before construction
  • Section 106: Planning obligation contributions from developers used to fund infrastructure or affordable housing
  • UKSPF: UK Shared Prosperity Fund, a central government grant programme; from 2025/26 devolved to Mayoral Combined Authorities such as EMCCA
  • EMCCA: East Midlands Combined County Authority, the Mayoral Combined Authority covering the Council's area
  • Prudential borrowing: Borrowing by a local authority within its statutory borrowing limits, with repayment from its own resources
  • Capital receipts: Income from the sale of assets, here General Fund capital receipts, used to fund capital expenditure
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item104.2

Resolved

RESOLVED that the capital budget variations for 2025/26, as set out in the report, be approved. Reason To be accountable for all activities and actions and to ensure that the Council conforms to all financial regulations.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to RESOLVE that the capital budget variations for 2025/26, as set out, be approved.

3. Detail

The Capital Programme for 2025/26 to 2027/28 was approved by Council on 5 March 2025 following recommended by Cabinet on 4 February 2025. The total value of the original Capital Programme for 2025/26 was £34.966m (£32.484m excluding ‘reserve items’).

Several capital schemes require amendments to the budgets to more accurately reflect expectations in the current financial year. In all cases the capital financing will not be adversely affected with schemes either being funded by capital grants or through previously agreed prudential borrowing which will be adjusted accordingly to match spends.

These schemes include elements of the Housing Delivery Programme, an element of Economic Regeneration Projects relating to the UK Shared Prosperity Fund and other General Fund capital schemes. These are set out in the Appendix which includes the proposed amendments to the current Capital Programme together with likely financing that will be confirmed at the end of the financial year.

Any further changes to the Capital Programme will be reported to Cabinet as necessary for approval.

4. Key Decision

This report is not considered a key decision as defined under Regulation 8 of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012.

5. Updates from Scrutiny

Not applicable. Cabinet 3 February 2026

Financial implications

The comments from the Interim Deputy Chief Executive and Section 151 Officer were as follows:

The financial implications are included in the report narrative and appendices.

The comments from the Monitoring Officer / Head of Legal Services were as follows:

There are no direct legal implications that arise from this report.

8. Human Resources Implications

There were no comments from the Human Resources Manager.

9. Union Comments

Not applicable.

10. Climate Change Implications

The Council’s response to Climate Change is a key consideration as part of the budget setting process.

11. Data Protection Compliance Implications

This report does not contain any OFFICIAL(SENSITIVE) information and there are no Data Protection issues in relation to this report.

12. Equality Impact Assessment

As there is no change to policy an equality impact assessment is not required.

Background papers

Nil. Cabinet 3 February 2026

Appendix Capital Programme 2025/26 – Proposed Capital Budget Changes

1. Housing Delivery Programme

The nature of the housing delivery programme means that the delivery of some new build schemes can slip or accelerate, often beyond the control of the Council and its contracted partners.

The rate of progress for the new build scheme at Coventry Lane West (‘Land at Bramcote Crematorium’) has been far quicker than anticipated, such that some social housing units are now expected to be passed to the Council in January with new tenants moving in shortly afterwards.

Whilst the overall cost of the scheme remains as approved at £9.638m, it will be necessary to bring forward some of the budget profiled in future years to cover the accelerated rate of payments being made in 2025/26. The final completion of the scheme is now anticipated for 2027/28. This scheme is being financed by a mix of Section 106 contributions and prudential borrowing.

Also, the capital budget for ‘New Build Housing Feasibility Costs’ has risen due to accumulated budget underspends being brought forward from earlier years. This has seen the budget increase from £250,000 to £350,000 in 2025/26. It is proposed to reduce this back to the original budget. This cost is met from prudential borrowing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme 2025/26: Capital Budget VariationsReport 125 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
MR
Councillor Milan Radulovic MBEChair, present
GM
Councillor Greg MarshallVice-Chair, present
GB
Councillor Gabrielle BunnCommittee Member, present
CC
Councillor Chris CarrCommittee Member, present
TA
Councillor Teresa A CullenCommittee Member, present
RD
Councillor Richard D MacRaeCommittee Member, present
JW
Councillor John W McGrathCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
VC
Councillor Vanessa C SmithCommittee Member, present
EW
Councillor Elizabeth WilliamsonCommittee Member, present

On this subject at Broxtowe

Search all
  1. Capital Programme 2025/26 – Capital Budget VariationsThis decision
  2. Capital Programme 2025/26 – Capital Budget VariationsApproved
  3. Vehicle Fleet Replacement Programme Reallocation of the Capital BudgetsApproved
  4. Capital Programme 2025/26 – Capital Budget VariationsApproved
  5. Capital Programme 2024/25 – Capital Budget VariationsApproved
  6. Capital Programme – Budget Variations 2024/25Approved

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open
3 Nov 2026 Grants to Voluntary and Community Organisations, Charitable Bodies and Individuals Involved in Sports, the Arts and Disability Matters 2026/27RESOLVED that: The Grant Aid requests be granted as follows: Broxtowe Women’s Project £13,000 Eastwood People’s Initi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies