Resolved
RESOLVED that the public footpath diversion order be made.
AI summaryBroxtowe Planning Committee approves diversion order for part of Beeston footpath 63 to allow 397-dwelling Boots Campus development to proceed.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the public footpath diversion order be made.
This item is brought to Committee to make a diversion Order under the Town and Country Planning Act 1990 following an application received by the Council for a public path diversion order to stop up part of Beeston footpath number 63 and create an alternative footpath. The site forms part of the Boots Campus in Beeston.
The Committee is asked to RESOLVE that the public path diversion order be made.
Detail
Planning permission was granted on 09 December 2022 (planning reference 21/00672/REM) for site and infrastructure works including construction of 397 dwellings.
The application to stop up part of the route of Beeston footpath number 63 and divert this footpath has been submitted in order to enable development to take place.
The current footpath runs along the western boundary of the site and via a footbridge to the southern towpath of the Nottingham and Beeston canal.
The section of the existing footpath to be diverted is approximately 534m in length and runs north to south from Lilac Grove at its junction with Humber Road South (adjacent to the Boots campus) between points SK5436 3631 and SK5442 3599.
The Agent acting for the owner has confirmed that a pre-order consultation has been carried out with letters having been sent to the Rights of Way Officer at Nottinghamshire County Council, and other interested parties. We are informed that no objections were received.
The comments from the Head of Finance Services were as follows:
There are no additional financial implications for the Council with the costs/income being within the normal course of business and contained within existing budgets. Planning Committee 14 January 2026
Any separate financial issues associated with S106s (or similar legal documents) are covered elsewhere in the report.
The comments from the Head of Legal Services were as follows:
The Legal implications are set out in the report where relevant, a Legal advisor will also be present at the meeting should legal considerations arise.
Data Protection Compliance Implications
Due consideration has been given to keeping the planning process as transparent as possible, whilst ensuring that data protection legislation is complied with.
Climate Change Implications
Climate Change implications are considered within the report
Nil. Planning Committee 14 January 2026
Appendix
Details of the application
Section 257 of the Town and Country Planning Act 1990 states that a competent Authority may by order authorise the stopping up or diversion of any footpath if they are satisfied that it is necessary to do so in order to enable development to be carried out in accordance with a planning permission. The procedure for doing so is set out in Schedule 14 of the Town and Country Planning Act 1990.
S7.15 of the Rights of Way Circular (1/09) advises that in the making of an order for the diversion of a Public Right of Way to enable approved development: -
‘The local planning authority should not question the merits of planning permission when considering whether to make or confirm an order, but nor should they make an order purely on the grounds that planning permission has been granted. That planning permission has been granted does not mean that the public right of way will therefore automatically be diverted or stopped up. Having granted planning permission for a development affecting a right of way however, an authority must have good reasons to justify a decision either not to make or not to confirm an order.
The disadvantages or loss likely to arise as a result of the stopping up or diversion of the way to members of the public generally or to persons whose properties adjoin or are near the existing highway should be weighed against the advantages of the proposed order.’
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Footpath Diversion Order 63Report | 148 KB | DownloadRead as text |
Follow Planning Committee at Broxtowe and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Oct 2026 | 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... | Refused | Open |
| 28 Oct 2026 | 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... | Approved | Open |
| 28 Oct 2026 | 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... | Approved | Open |
| 28 Oct 2026 | 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... | Agreed | Open |
| 28 Oct 2026 | 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.