Planning Committee, Wednesday 14 January 2026 at 6.00pm

Footpath Diversion Order 63

Decided Planning 1 paper

AI summaryBroxtowe Planning Committee approves diversion order for part of Beeston footpath 63 to allow 397-dwelling Boots Campus development to proceed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedStop up part of Beeston footpath 63, create alternative
MoneyNone for the councilCosts and income within existing budgets
What happens nextPublic notice and deposit28 days for objections before confirmation
Who it affectsBeeston footpath 63 usersAbout 534m of path to be diverted

What was decided

The committee resolved to make the public footpath diversion order for part of Beeston footpath 63, from Thane Road to Beeston Canal, on the Boots Campus site. Report P1, P2

The diversion is needed to enable the approved development of 397 dwellings, for which planning permission was granted on 09 December 2022 under reference 21/00672/REM. Report P4, P5

Why

The section of footpath runs along the western boundary of the Boots Campus site and via a footbridge to the southern towpath of the Nottingham and Beeston Canal, blocking the approved development. Report P5, P6

The agent for the owner carried out a pre-order consultation with the County Council Rights of Way Officer and other interested parties, and no objections were received. Report P8

Section 257 of the Town and Country Planning Act 1990 lets the council make the order if it is needed to enable development in line with planning permission, and the order is required so the footpath is retained without disadvantage to the public. Report P21, P26

What happens next

After the order is made, a public notice describing it must be advertised in the press and the order placed on deposit, with notices at each end of the affected footpath section. Report P25

Owners of affected land and statutory consultees must be served with the order and notice, with 28 days allowed for objections; if none are received the order can be confirmed as unopposed. Report P25

If objections are received the order is sent to the Secretary of State for determination, and objectors may challenge any confirmation in the High Court within six weeks of the confirmation notice being published. Report P25

Options considered

  • Chosen: Make the diversion order. Needed to enable approved 397-dwelling Boots Campus development, no objections in pre-order consultation, and the footpath can be provided without disadvantage to the public. Report P5, P8, P26, 12.1

Implications

  • Financial: No additional financial implications for the council; costs and income are within existing budgets. Report P10
  • Legal: The order is made under section 257 of the Town and Country Planning Act 1990, following the procedure in Schedule 14, and must be confirmed before it takes effect. Report P21, P25
  • Legal: Objectors may challenge confirmation in the High Court within six weeks of the confirmation notice on grounds that the decision is outside the council's powers or there was a procedural defect. Report P25
  • Equalities: The order is intended to ensure the footpath is provided without disadvantage or loss to members of the public. Report P26

Who and where

  • Users of Beeston footpath 63, who will be redirected along a new route from the existing alignment along the western boundary of the Boots Campus and the canal towpath footbridge. Report P6, P7
  • The owner of the Boots Campus site in Beeston, whose development of 397 dwellings depends on the diversion. Report P4, P5
  • Owners of land crossed by the new alignment and statutory consultees, who must be served with the order and notice. Report P25

Timeline

  • 09 December 2022: Planning permission granted for site and infrastructure works including 397 dwellings (reference 21/00672/REM). Report P4
  • Before 14 January 2026: Pre-order consultation carried out by the agent acting for the owner with the County Council Rights of Way Officer and other interested parties; no objections received. Report P8
  • 14 January 2026: Planning Committee resolves to make the public path diversion order. Report P28
  • Within 28 days of the order being made: Objection period after public notice and service on owners and consultees. Report P25

Plain English for the jargon

  • Diversion order: A legal order that stops up an existing public footpath and creates an alternative route, made under section 257 of the Town and Country Planning Act 1990.
  • Boots Campus: The development site in Beeston, formerly associated with Boots, on which 397 dwellings have approved planning permission.
  • Pre-order consultation: Consultation carried out by the applicant before the order is made, with bodies such as the County Council Rights of Way Officer and other interested parties.
  • Section 257, Town and Country Planning Act 1990: The power for a local planning authority to authorise the stopping up or diversion of a footpath if needed to enable development carried out under planning permission.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item49.5

Resolved

RESOLVED that the public footpath diversion order be made.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Planning Committee

Purpose of report

This item is brought to Committee to make a diversion Order under the Town and Country Planning Act 1990 following an application received by the Council for a public path diversion order to stop up part of Beeston footpath number 63 and create an alternative footpath. The site forms part of the Boots Campus in Beeston.

Recommendation

The Committee is asked to RESOLVE that the public path diversion order be made.

Detail

Planning permission was granted on 09 December 2022 (planning reference 21/00672/REM) for site and infrastructure works including construction of 397 dwellings.

The application to stop up part of the route of Beeston footpath number 63 and divert this footpath has been submitted in order to enable development to take place.

The current footpath runs along the western boundary of the site and via a footbridge to the southern towpath of the Nottingham and Beeston canal.

The section of the existing footpath to be diverted is approximately 534m in length and runs north to south from Lilac Grove at its junction with Humber Road South (adjacent to the Boots campus) between points SK5436 3631 and SK5442 3599.

The Agent acting for the owner has confirmed that a pre-order consultation has been carried out with letters having been sent to the Rights of Way Officer at Nottinghamshire County Council, and other interested parties. We are informed that no objections were received.

Financial implications

The comments from the Head of Finance Services were as follows:

There are no additional financial implications for the Council with the costs/income being within the normal course of business and contained within existing budgets. Planning Committee 14 January 2026

Any separate financial issues associated with S106s (or similar legal documents) are covered elsewhere in the report.

The comments from the Head of Legal Services were as follows:

The Legal implications are set out in the report where relevant, a Legal advisor will also be present at the meeting should legal considerations arise.

Data Protection Compliance Implications

Due consideration has been given to keeping the planning process as transparent as possible, whilst ensuring that data protection legislation is complied with.

Climate Change Implications

Climate Change implications are considered within the report

Background papers

Nil. Planning Committee 14 January 2026

Appendix

Details of the application

Section 257 of the Town and Country Planning Act 1990 states that a competent Authority may by order authorise the stopping up or diversion of any footpath if they are satisfied that it is necessary to do so in order to enable development to be carried out in accordance with a planning permission. The procedure for doing so is set out in Schedule 14 of the Town and Country Planning Act 1990.

S7.15 of the Rights of Way Circular (1/09) advises that in the making of an order for the diversion of a Public Right of Way to enable approved development: -

‘The local planning authority should not question the merits of planning permission when considering whether to make or confirm an order, but nor should they make an order purely on the grounds that planning permission has been granted. That planning permission has been granted does not mean that the public right of way will therefore automatically be diverted or stopped up. Having granted planning permission for a development affecting a right of way however, an authority must have good reasons to justify a decision either not to make or not to confirm an order.

The disadvantages or loss likely to arise as a result of the stopping up or diversion of the way to members of the public generally or to persons whose properties adjoin or are near the existing highway should be weighed against the advantages of the proposed order.’

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Footpath Diversion Order 63Report 148 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 16 attended
RD
Ryan DawsonCouncil Staff, expected
SP
Councillor Stephen P JeremiahChair, present
PA
Councillor Pauline A SmithVice-Chair, present
DB
Councillor David BagshawCommittee Member, apologies, sent representative
PJ
Councillor Peter J BalesCommittee Member, present
LA
Councillor Lydia A Ball BEMCommittee Member, present
GB
Councillor Gabrielle BunnCommittee Member, present
SC
Councillor Sarah CamplinCommittee Member, present
SJ
Councillor Stephen J CarrCommittee Member, present
JC
Councillor Judith CouchCommittee Member, present
TJ
Councillor Tyler J MarshCommittee Member, present
GM
Councillor Greg MarshallCommittee Member, present

All 16 on the meeting page

On this subject at Broxtowe

Search all
  1. Footpath Diversion Order 63This decision
  2. Footpath Diversion Order - Footpath 27Decided
  3. Proposed diversion of beeston footpath number 55 - wilmot lane, beeston, nottinghamDecided

More from Broxtowe Planning Committee

All decisions
MeetingDecisionOutcome
28 Oct 2026 26/00581/fulRESOLVED that the Planning permission be refused due to the proposed two-storey rear extension, by reason of its scal... Refused Open
28 Oct 2026 26/00554/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant advertisement conse... Approved Open
28 Oct 2026 26/00495/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Approved Open
28 Oct 2026 26/00335/reg3RESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open
28 Oct 2026 26/00516/fulRESOLVED that the Head of Planning and Economic Development be given delegated authority to grant planning permission... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies