Broxtowe Borough Council
Cabinet, Tuesday 10 March 2026 at 6.00pm

Old Brewery Site Kimberley

Approved Executive 1 paper

AI summaryBroxtowe Cabinet approved £18,000 for initial surveys at the Old Brewery Site in Kimberley, and agreed in principle to negotiate buying the site for social housing if the surveys show it is viable.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet decision on Old Brewery site Kimberley
Money£18,000From Revenue Contingencies 2025/26 for initial surveys
What happens nextSurveys to proceedPossible purchase bid if surveys merit it
Who it affectsKimberley Old Brewery siteListed building, potential social housing use

What was decided

Cabinet approved the appointment of suitably qualified companies to undertake groundwork and building investigations at the Kimberley Brewery site. Report P2

Cabinet approved an £18,000 budget for the initial survey works, funded from Revenue Contingencies in 2025/26. Report P3

If the survey warrants further work, Cabinet approved in principle the preparation of a bid to purchase the site, subject to budget approval, contract and independent valuation, for presentation to the Administrator or Receiver. Report P4

Why

The decision supports the Council's Corporate Priority of Housing: a good quality home for everyone.

The surveys are needed to test whether the site could produce a viable social housing scheme.

Remedial works to the listed malt kilns (Building 5) must be completed before the Planning Condition can be discharged. Report P7

What happens next

The appointed companies will carry out the surveys, with on-site work estimated at about five days and an overall timescale of roughly three weeks. Report P8, P9

If survey findings support it, officers will prepare a bid to buy the site, subject to further Cabinet approval of budget, contract and an independent valuation. Report P4, P24

Any wider capital investment in the site will require a further report to and approval by Cabinet. Report P24

The money

  • £18,000 Budget for initial survey works, from General Fund revenue contingencies 2025/26 Report P3, P23
  • approximately £3,000 plus VAT Fees for cost estimate work on remedial works to the listed malt kilns Report P8
  • approximately £2,00 plus VAT Work to determine status of any Section agreements for services crossing Phase 3 Report P15
  • approximately £3,500 plus VAT Desktop study on ground conditions and utility search in Phase 3 Report P16
  • an interim estimate of £4,000 Interim estimate included in the budget request for the GPR PAS 128 survey and geo-environmental investigation Report P17
  • estimated £10,000 Additional GPR PAS 128 survey cost included in the approved budget Report P3
  • £38,000 Currently remaining in General Fund revenue contingencies 2025/26, subject to other Cabinet requests on the same agenda Report P23

Implications

  • Financial: £18,000 is being drawn from General Fund revenue contingencies 2025/26, of which £38,000 currently remains available, subject to other Cabinet requests on the same agenda. Report P23
  • Financial: Any wider capital investment in the Kimberley Brewery site would require a further report to and approval by Cabinet. Report P24
  • Legal: Comments from the Monitoring Officer and Head of Legal Services will be distributed at the meeting if necessary. Report P25
  • Other: The report is not a key decision and does not require an Equality Impact Assessment; no climate change, HR or data protection implications were identified. Report P19, P26, P30, P33, P35

Who and where

  • The Administrator or Receiver handling the Old Brewery Site at Kimberley Report P4
  • Future residents of any social housing developed on the site
  • Broxtowe residents in need of social housing Report P5
  • The listed malt kilns building (Building 5) on the site Report P7

Timeline

  • 10 March 2026: Cabinet meeting at which the decision was made Report P8, P23
  • approximately five days: Estimated duration of the on-site cost estimate work Report P8
  • around three weeks: Overall timescale for the first operator's cost estimate work Report P9
  • 2025/26: Financial year from which the £18,000 budget is drawn Report P3, P23

Plain English for the jargon

  • GPR PAS 128 survey: Ground Penetrating Radar survey to PAS 128, the British Standard for detecting and verifying underground utilities
  • Section agreements: Legal agreements relating to services (such as pipes or cables) crossing between different phases of a development
  • Malt kilns: Traditional brewery buildings used for drying malt; Building 5 on the site is a listed building
  • Administrator or Receiver: Insolvency practitioner appointed to manage or realise the assets of a company in financial difficulty
  • Revenue Contingencies: Budget held back within the General Fund to meet unforeseen or one-off revenue items
  • Section 151 Officer: The local authority officer with statutory responsibility for the proper administration of its financial affairs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item112.2

Resolved

RESOLVED that: 1. The appointment of suitably qualified and experienced companies to undertake groundwork and building investigations at Kimberley Brewery site be approved. 2. A budget of £18,000 for the initial survey works, which includes the two quoted sums plus an estimated £10,000 for the additional GPR PAS 128 survey be approved and funded from Revenue Contingencies in 2025/26. 3. If the survey merited further work, the preparation of a bid to purchase the site, subject to budget approval, contract and independent valuation, for presentation to the Administrator/Receiver be approved. Reason This is in accordance with the Council's Corporate Priority of Housing – a good quality home for everyone.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to RESOLVE that:

1. The appointment of suitably qualified and experienced companies to undertake groundwork and building investigations at Kimberley Brewery site be approved.

2. A budget of £18,000 for the initial survey works, which includes the two quoted sums plus an estimated £10,000 for the additional GPR PAS 128 survey be approved and funded from Revenue Contingencies in 2025/26.

3. If the survey merited further work, the preparation of a bid to purchase the site, subject to budget approval, contract and independent valuation, for presentation to the Administrator/Receiver be approved.

Detail

Two companies were invited to submit quotations for undertaking investigative surveys at the Old Brewery Site at Kimberley.

The first was requested to provide a quote for estimating the cost of works listed in the Planning Condition for the site, with specific attention to the remedial works for repair of the malt kilns (Building 5), which is a listed building. These remedial works must be completed prior to the Planning Condition being discharged

The operator estimated the work will take approximately five days to complete a detailed cost estimate. The work includes a site visit, measurement and costing, presentation of cost estimate and final adjustment prior to issue. Fees have been identified as approximately £3,000 plus VAT. Cabinet 10 March 2026

Timescales for the work have been estimated at around three weeks.

A further operator was requested to provide an estimate based on the following brief:

• A detailed report to cover ground conditions, access rights, and the locations of any underground services within Phase 3 of the site, especially those that link to either or both of the earlier phases of the scheme.

• Status of any section agreements required by the Planning Consent relating to all phases of the scheme; especially those for services which cross Phase 3.

• Any other information available from desktop work regarding ground conditions or services in Phase 3.

The operator’s quote outlined budget costs for the following works:

• Determine the status of any Section agreements relating to all phases of the scheme, especially those for services which cross Phase 3 at approximately £2,00 plus VAT.

• Desktop study regarding ground conditions and a utility search of services in Phase 3 at approximately £3,500 plus VAT.

The operator also recommended a GPR PAS 128 survey when site access is available to identify and verify the presence of any below ground services as well as a geo-environmental investigation to identify if any contamination is present. As fees were not provided for this work, an interim estimate of £4,000 has been included in the budget recommendation request.

Key Decision

This is not a key decision

Updates from Scrutiny

Not applicable.

Financial implications

The comments from the Interim Deputy Chief Executive and Section 151 Officer were as follows:

There is no budgetary provision in place for the cost of undertaking groundwork and building investigations at Kimberley Brewery site. An allocation of £18,000 has therefore been requested from the General Fund revenue contingencies budget in 2025/26, of which £38,000 currently remains available (subject toother Cabinet 10 March 2026

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Old Brewery Site KimberleyReport 78 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
MR
Councillor Milan Radulovic MBEChair, present
GM
Councillor Greg MarshallVice-Chair, present
GB
Councillor Gabrielle BunnCommittee Member, present
CC
Councillor Chris CarrCommittee Member, present
TA
Councillor Teresa A CullenCommittee Member, present
RD
Councillor Richard D MacRaeCommittee Member, present
JW
Councillor John W McGrathCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
VC
Councillor Vanessa C SmithCommittee Member, present
EW
Councillor Elizabeth WilliamsonCommittee Member, apologies

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open