CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Broxtowe Borough Council
Cabinet, Tuesday 10 March 2026 at 6.00pm

Bramcote Hill Park Development proposal

Approved Executive 2 papers

AI summaryCabinet approved £4,000 to commission concept drawings and cost estimates for new visitor facilities at Bramcote Hills Park, including a café, meeting space and accessible toilets.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConcept design funding agreed
Money£4,000From Revenue Contingencies 2025/26
What happens nextFurther Cabinet reportAfter concept work and cost estimates
Who it affectsPark visitorsBramcote Hills Park users and residents

What was decided

Cabinet approved £4,000 to commission concept drawings and initial capital cost estimates for proposed visitor facilities at Bramcote Hills Park, funded from Revenue Contingencies in 2025/26. Report P1

Why

Public consultation has repeatedly identified the lack of toilet facilities and supporting amenities as a major constraint on the visitor experience at Bramcote Hills Park and the recently adopted Bramcote Quarry site, which together form a developing destination of borough wide significance. Report P3

What happens next

Officers will commission concept drawings and firmed up cost estimates for a new sustainable visitor facility incorporating a café, meeting space and accessible toilets. Report P4

A further report will come back to Cabinet; any full proposal would be subject to planning approval and a financial business case, with external funding opportunities to be explored. Report P4

Work continues on a proposed walking route linking five Local Nature Reserves within 5km and on early exploration of Parkrun opportunities. Report P5

The money

  • £4,000 Commissioning concept drawings and initial capital cost estimates for proposed visitor facilities at Bramcote Hills Park Report P1, P4, P11
  • £38,000 Remainder of General Fund revenue contingency budget in 2025/26 after this allocation Report P11
  • £250,000 Threshold above which a decision would be a key decision under the 2012 Executive Arrangements Regulations Report P7

Implications

  • Financial: There is no existing budget for a feasibility study at Bramcote Hills Park, so the £4,000 is drawn from the General Fund revenue contingency, of which £38,000 remains available in 2025/26. Any capital investment would require a further report to and approval by Cabinet. Report P11
  • Legal: There are no direct legal implications from this report, although further legal implications will need to be considered as the project progresses. Report P13
  • Climate: Climate change implications are contained within the report. Report P19
  • Other: The report is not a key decision under Regulation 8 of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012, as expenditure is below £250,000. Report P7

Who and where

  • Visitors and residents using Bramcote Hills Park and the recently adopted Bramcote Quarry site Report P3
  • Users of the proposed walking route linking five Local Nature Reserves within 5km and potential Parkrun participants Report P5

Timeline

  • 10 March 2026: Cabinet decision to approve £4,000 from Revenue Contingencies in 2025/26 Report P1, P7
  • 2025/26: Financial year from which the £4,000 allocation is funded Report P11

Plain English for the jargon

  • Section 106 contributions: Planning obligation payments from developers towards local infrastructure, confirmed as not available for this phase
  • Local Nature Reserves: Locally designated sites managed for nature conservation and enjoyed by the public
  • Revenue Contingencies: Money held in the General Fund revenue budget to cover unplanned or one off costs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item114.1

Resolved

RESOLVED that a budget of £4,000 for the commissioning of concept drawings and initial capital cost estimates for the proposed visitor facilities at Bramcote Hills Park be approved and funded from Revenue Contingencies in 2025/26. Reason Public consultation has repeatedly identified the lack of toilet facilities and supporting amenities as a major constraint on the visitor experience.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to RESOLVE that a budget of £4,000 for the commissioning of concept drawings and initial capital cost estimates for the proposed visitor facilities at Bramcote Hills Park be approved and funded from Revenue Contingencies in 2025/26.

3. Detail

Bramcote Hills Park, together with the recently adopted Bramcote Quarry site, now forms a developing destination of Borough‑wide significance. The combined area consists of extensive woodland, parkland and key heritage features, attracting high levels of use from both residents and visitors. Public consultation has repeatedly identified the lack of toilet facilities and supporting amenities as a major constraint on the visitor experience.

In response, the Council is proposing to advance initial design and costing work for a new sustainable visitor facility, incorporating a café, meeting space and accessible toilets. A sum of £4,000 is required to commission concept drawings and firmed‑up cost estimates, which will inform a further report to Cabinet. Any full proposal would be subject to planning approval and financial business case, and external funding opportunities will continue to be explored following confirmation that Section 106 contributions and FCC funding are not available for this phase.

Work is also progressing on wider site connectivity, including refinement of a proposed walking route linking five Local Nature Reserves within 5km, and early exploration of Parkrun opportunities. Further detail on the park’s existing features, consultation findings, sustainability requirements, funding considerations and associated project work is provided in the Appendix.

4. Key Decision

This report is not a key decision as defined under Regulation 8 of the Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012. At this stage the report does not result in in the Council incurring revenue or capital expenditure or savings of £250,000 or more. Cabinet 10 March 2026

5. Updates from Scrutiny

Not appliable.

Financial implications

The comments from the Interim Deputy Chief Executive and Section 151 Officer were as follows:

There is no budgetary provision in place for the cost of commissioning a feasibility study into a potential development opportunity for Bramcote Hills Park. An allocation of £4,000 has therefore been requested from the General Fund revenue contingency budget in 2025/26, of which £38,000 currently remains available. Any commitment in terms of funding a capital investment scheme for Bramcote Hills Park would require a further report to and approval by Cabinet.

The comments from the Head of Legal Services were as follows:

There are no direct legal implications arising from this report, however, further legal implications will need to be considered as the project progresses.

8. Human Resources Implications

Not applicable.

9. Union Comments

Not applicable.

10. Climate Change Implications

The climate change implications are contained within the report.

11. Data Protection Compliance Implications

Not applicable.

12. Equality Impact Assessment

Not applicable.

Background papers

Nil.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bramcote Hill Park Development proposalReport 92 KB DownloadRead as text
PDF
Enc. 1 for Bramcote Hill Park Development proposalReport 427 KB Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
MR
Councillor Milan Radulovic MBEChair, present
GM
Councillor Greg MarshallVice-Chair, present
GB
Councillor Gabrielle BunnCommittee Member, present
CC
Councillor Chris CarrCommittee Member, present
TA
Councillor Teresa A CullenCommittee Member, present
RD
Councillor Richard D MacRaeCommittee Member, present
JW
Councillor John W McGrathCommittee Member, present
HE
Councillor Helen E SkinnerCommittee Member, present
VC
Councillor Vanessa C SmithCommittee Member, present
EW
Councillor Elizabeth WilliamsonCommittee Member, apologies

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open
3 Nov 2026 Grants to Voluntary and Community Organisations, Charitable Bodies and Individuals Involved in Sports, the Arts and Disability Matters 2026/27RESOLVED that: The Grant Aid requests be granted as follows: Broxtowe Women’s Project £13,000 Eastwood People’s Initi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies