Fire Risk and Asbestos Management Programmes - Leaseholder Consultation and Future Charges

Decided Executive 1 paper

AI summaryBroxtowe Cabinet agreed to fund £142,100 of fire risk and asbestos remedial works from the Housing Revenue Account and to run an informal Section 20 consultation with leaseholders now, with formal charges starting from the next inspection batch in 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedHRA funding and two-stage Section 20 leaseholder consultation
Money£142,100 from HRAEstimated cost of further remedial works in current batch
What happens nextSection 20 consultationsInformal now, formal with next inspection batch in 2027
Who it affectsCouncil leaseholdersIn General Needs blocks where works are needed

What was decided

The Housing Revenue Account will meet the estimated £142,100 cost of further remedial works tied to remaining relevant asbestos and Fire Risk Assessment actions in the current inspection batch. Report P2

An informal Section 20 consultation will begin with leaseholders about the current batch of actions, with no charge to leaseholders. Report P2

A formal Section 20 consultation, with charges insisted, will begin to coincide with the next batch of asbestos and Fire Risk Assessment inspections. Report P2

Why

Officers said the works were needed to keep residents safe, meet fire safety legislation and support the Council's wider building safety duties. Report P4

The report cited exceptional pressures since the Grenfell Tower fire in 2017, a backlog of around 6,000 fire safety actions, the June 2025 fire at The Lilacs and ongoing scrutiny from the Regulator of Social Housing. Report P18, P19, P21

The pace of change in fire and asbestos safety requirements made it impractical to run formal Section 20 charges during the current catch-up phase, but the Council plans to resume normal charging with the 2027 inspection round. Report P23

What happens next

Officers will start an informal Section 20 consultation with leaseholders on the current batch of actions, with no charge insisted. Report P2

A formal Section 20 consultation will be prepared to run alongside the next batch of inspections, anticipated to begin in 2027, with charges to leaseholders insisted. Report P23, P2

Training will be given to relevant officers on leaseholder consultation requirements, communication expectations and statutory responsibilities. Report P22

The money

  • £142,100 Estimated total cost of further remedial works in the current inspection batch, to be met by the Housing Revenue Account Report P2
  • £63,000 Estimated unclaimed cost from leaseholders for around 3,000 actions already completed in the current batch Report P15
  • £132,500 Potential Section 20 charge to leaseholders for remaining Fire Risk Assessment actions Report P24
  • £9,600 Potential Section 20 charge to leaseholders for remaining asbestos actions Report P24

Options considered

  • Chosen: Approve HRA funding and two-stage Section 20 consultation as recommended. Works are essential for safety and compliance; exceptional circumstances justify delaying formal charges until 2027 Report P2, P4, P23
  • Rejected: Recover costs of works already done by applying to the First Tier Tribunal for a Section 20ZA dispensation. Not recommended; Legal Services noted consultation may still be preferable even without charges, to avoid prejudicing leaseholders Report P33, P35, P36

Implications

  • Financial: Funding the £142,100 from the Housing Revenue Account means the HRA is effectively subsidising private leaseholders in General Needs blocks. Report P31
  • Legal: Section 20 of the Landlord and Tenant Act 1985 governs consultation; Section 20ZA(1) would apply if the Council later sought to recover costs of works already done, requiring a First Tier Tribunal dispensation. Report P17, P33, P34
  • Staffing: Training will be provided to relevant officers on leaseholder consultation requirements, communication expectations and statutory responsibilities. Report P22
  • Risk: Running formal Section 20 consultations now could add three to six months of delay to remedial works; the report judged this a heightened risk to the fire safety programme. Report P24

Who and where

  • Leaseholders in General Needs housing blocks where Fire Risk Assessment or asbestos works are needed Report P15, P16
  • Council tenants and residents in blocks covered by the inspection programme Report P4
  • Council officers delivering the Fire Risk Assessment and asbestos programmes Report P22

Timeline

  • 2006: Control of Asbestos legislation introduced, requiring the Council to manage asbestos containing materials Report P16
  • June 2017: Grenfell Tower tragedy triggered fundamental changes in fire safety legislation and regulation Report P18
  • 2021: Cabinet previously approved a Section 20 exemption linked to replacement of entrance doors and windows Report P25
  • June 2025: Fire at The Lilacs reinforced the need to address fire safety risks promptly and comprehensively Report P21
  • 2027: Next batch of Fire Risk Assessment and asbestos inspections anticipated to begin, to be accompanied by formal Section 20 consultation with charges Report P23

Plain English for the jargon

  • FRA: Fire Risk Assessment
  • ACM: Asbestos Containing Material
  • HRA: Housing Revenue Account, the ringfenced account landlords use for income and spending on council housing
  • Section 20: Section 20 of the Landlord and Tenant Act 1985, which sets out consultation requirements landlords must follow before carrying out qualifying works and recovering costs from leaseholders
  • Stay Put Strategy: A fire safety approach where residents remain in their flats during a fire because the building's fire resistance is designed to contain the fire
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item42.1

Resolved

RESOLVED that: 1. The Council’s Housing Revenue Account meets the cost of further remedial works aligned to the remaining relevant asbestos and Fire Risk Assessment (FRA) actions identified within the recent batch of inspections, at an estimated total of £142,100. 2. A Section 20 consultation commences informally with leaseholders regarding the remaining relevant asbestos and FRA actions (with no charge insisted). 3. A Section 20 consultation commences formally to coincide with the next batch of asbestos and FRA inspections (with charges insisted). Reason These works were essential to ensure resident safety, maintain compliance with fire safety legislation, and support the Council’s wider building safety responsibilities.
Word for word from the decision Broxtowe published for this meeting. Source: democracy.broxtowe.gov.uk

Follow this further

Built from Broxtowe's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to RESOLVE that the following be approved:

1. The Council’s Housing Revenue Account meets the cost of further remedial works aligned to the remaining relevant asbestos and Fire Risk Assessment (FRA) actions identified within the recent batch of inspections, at an estimated total of £142,100 2. A Section 20 consultation commences informally with leaseholders regarding the remaining relevant asbestos and FRA actions (with no charge insisted). 3. A Section 20 consultation commences formally to coincide with the next batch of asbestos and FRA inspections (with charges insisted).

3. Detail

The Council is currently delivering a significant programme of Fire Risk Assessment (FRA) remedial works across its housing stock (under 2,000 fire safety actions to be completed). These works are essential to ensure resident safety, maintain compliance with fire safety legislation, and support the Council’s wider building safety responsibilities. A significant proportion of the actions from the recent batch of FRA inspections consist of the following:

• Checking (where required):

o external wall construction with results being shared with external consultants so that any impact on fire safety can be considered

o compartmentation within identified roof spaces over common areas to confirm that there is adequate separation

o that the common area fire alarm systems have been designed and installed to support the Stay Put Strategy

o electrical intake and meter cupboards to confirm that combustible items are not being kept near ignition sources Cabinet 8 September 2026

o that identified wall and ceiling linings will achieve a surface lining classification aligned to relevant building regulations

o electrics located within identified common areas are enclosed with relevant fire resisting construction.

• Installing fire resisting glazing where required.

• Updating signs and notices.

• Sealing identified gaps with suitable fire-stopping material.

FRA’s have only been completed in General Needs blocks within the current batch of completed assessments. Prior to this, Section 20 was not an issue because there are no leaseholders within Independent Living blocks. Around 3,000 actions have been completed within this current batch of assessments, totalling an estimated unclaimed cost from Leaseholders of £63,000.

With regards to asbestos, annual planned inspections take place across all of the Council’s HRA General Needs blocks, with asbestos containing materials (ACMs) being identified within building elements. The presence of ACMs is a latent historic condition of the asset, which the council have been duty bound to manage (e.g. repair, remove or encapsulate) since the introduction of the Control of Asbestos legislation in 2006.

Under normal circumstances, the Council would be entitled to recover an appropriate proportion of fire safety remedial costs from leaseholders in accordance with the provisions of Section 20 of the Landlord and Tenant Act 1985. However, the Council has faced a series of exceptional and unprecedented challenges over the last six years which have significantly impacted its approach to fire safety management and the delivery of remedial works.

Following the Grenfell Tower tragedy in June 2017, there was a fundamental shift in fire safety legislation, regulatory expectations and sector-wide best practice. These changes significantly increased the statutory responsibilities placed on social housing providers, including the scope and complexity of Fire programmes and the volume of associated remedial actions required across housing stock.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fire Risk and Asbestos Management Programmes: Leaseholder Consultation and Future ChargesReport 145 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 10 attended
MR
Councillor Milan Radulovic MBEChair, present
GM
Councillor Greg MarshallVice-Chair, present
GB
Councillor Gabrielle BunnCommittee Member, apologies
TA
Councillor Teresa A CullenCommittee Member, apologies
RD
Councillor Richard D MacRaeCommittee Member, present
TJ
Councillor Tyler J MarshCommittee Member, present
JW
Councillor John W McGrathCommittee Member, present
SP
Councillor Sue PatersonCommittee Member, apologies
VC
Councillor Vanessa C SmithCommittee Member, present
EW
Councillor Elizabeth WilliamsonCommittee Member, present

More from Broxtowe Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Reference - Overview and Scrutiny CommitteeRESOLVED that: 1. The introduction of an end date for the informal service trial currently underway with Lime as 31 D... Approved Open
3 Nov 2026 Communications And Engagement Strategy 2026-28RESOLVED that the Communications and Engagement Strategy be approved. Reason The strategy will support the Council’s ... Approved Open
3 Nov 2026 General Fund - Medium Term Financial Strategy 2026/27 to 2030/31 and Business Strategy 2027/28RESOLVED that the updated Medium Term Financial Strategy and the Business Strategy 2027/28 be approved. Reason To be ... Approved Open
3 Nov 2026 Grant Aid Requests from Parish/Town CouncilsRESOLVED that the grant aid requests from Eastwood Town Council for up to £2,458 for its Remembrance Sunday Event 202... Decided Open
3 Nov 2026 Grants to Voluntary and Community Organisations, Charitable Bodies and Individuals Involved in Sports, the Arts and Disability Matters 2026/27RESOLVED that: The Grant Aid requests be granted as follows: Broxtowe Women’s Project £13,000 Eastwood People’s Initi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies