Resolved
It was agreed: That the report be noted.
Overview and Scrutiny Committee agreed this item on Tuesday 9 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed: That the report be noted.
The consultation for a new delivery model for Childrens Centres commenced in September 2014 and ran for 3 months until December 2014 and a variety of methods were used to try to shape and inform a new model of delivery. The consultation involved a variety of stakeholders, parent, carers and advisory boards and a number of themes emerged.
Throughout the consultation period and following it, there were strong views, mainly from current service users about the value of health services delivered through Children Centres.
As a key delivery partner additional time was spent in trying to engage with health partners on the proposed new model, in particular how a small financial contribution could be made by them to support services continuing to cover some overheads.
A further report outlining these themes went to Cabinet in January 2015 and approval was given to start to implement the recommendations in the proposals
Recommendations following Consultation
The essential work of Children’s Centres from April 2015 should focus on providing early help to targeted families in four key areas:
Improving the health of U5’s Improving U’5’s school readiness Reducing the risk of poor parenting and mistreatment Promoting the economic prospects of families
Targeted support will always be offered following good, effective assessment to ensure the appropriate approach or intervention is offered.
Provision of a universal offer in order to support early help for families and prevent problems escalating, though in many cases this will be delivered through other partners.
The use of the Multiple Deprivation Index rankings as a means of allocating resources is a valid decision as deprivation is closely linked to poor health outcomes, a lack of school readiness and a high level of safeguarding concerns.
The original report proposed 5 Children Centre Hubs and 1 spoke in Bury East. In response to concerns raised during the consultation, Cabinet approved the hub and spoke model be extended to two further townships which have the next highest number of most deprived U’5’s. These are Radcliffe and Prestwich. The proposed hubs and spokes are shown in the table below:
1 Township Children’s Centre hub Spoke Bury East Little Oaks Redvales Radcliffe Coronation Road Stepping Stones Prestwich Sedgley Butterstile Whitefield Besses Bury West Woodbank Bury North Woodbank
As in the initial report, it is recommended that all the hub and spoke sites should come under the direct control of the Local Authority and the staff at these sites be employed the Authority.
In order to support the proposed increase of Outreach staff, 3 senior outreach Workers will be appointed to provide supervision support in the hub areas of Bury East and Radcliffe which have a substantial number of Outreach Workers. This will assist the Hub Manager in their supervision of these staff.
The initial report suggested that the Authority should seek to convert 7 of the current Children’s Centres to provide a setting for the 2 year old offer. The consultation and recommendations above have now proposed that Butterstile and Stepping Stones children’s centres should remain as spokes in Prestwich and Radcliffe.
It is now proposed that the following centres should convert:
-Daisyfield located at St Stephens CE Primary School- 20 places
-High Meadow located at St John’s Radcliffe Primary school- 12 places
-Moorside located at St John with St Mark CE Primary School – 10 places
-Ramsbottom- a standalone site – 10 places
-Toodle Hill located at Heaton Park Primary school – 32 places
Issues concerning implementation
An Implementation plan was drafted in order to scope the areas of work and identify key partners to develop elements of the plans.
The Implementation Plan covered the following sections:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CHILDREN'S CENTRES: IMPLEMENTATION UPDATEDecisions | 59 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2026 | Simister and bowlee development frameworkIt was agreed that Overview and Scrutiny: i. Note the content of the Simister Bowlee Development Framework Supplement... | Agreed | Open |
| 10 Feb 2026 | Elton reservoir development frameworkIt was agreed that Overview and Scrutiny: i. Note the content of the Elton Reservoir Development Framework Supplement... | Agreed | Open |
| 3 Sep 2024 | MINUTESIt was agreed that the minutes from 24 th July 2024 be approved as a correct record and signed by the Chair. Matters ... | Agreed | Open |
| 3 Sep 2024 | Health and safety reportIt was agreed: - The report be noted | Agreed | Open |
| 24 Jul 2024 | Corporate Parenting ChampionIt was agreed: 1. Councillor Green be appointed as the Corporate Parenting Champion. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.