Resolved
It was agreed: That the update be noted.
Overview and Scrutiny Committee agreed this item on Thursday 22 November 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed: That the update be noted.
1.1Bury Council is mandated to produce a Clean Air plan to tackle roadside Nitrogen Dioxide (NO2)emissions and submit an outline business case to the Joint Air Quality Unit of DEFRA and DfT early in 2019
1.2TfGM are carrying out this work on behalf of all GM boroughs as road traffic is responsible for 80% of NO2 emissions
1.3Charging Clean Air Zones are considered by Government the benchmark to ensure air quality and the associated health impacts are tackled in the shortest possible time so these will be modelled alongside wider measures to determine the optimum option.
1.4A GM communication plan to address the lack of understanding about health impacts of poor air quality and the difference between clean air zones and congestion charges was rolled out on 26th October 2018 through to December 2018.
1.5There will be a consultation period after the submission of the OBC before submission of a final business case in 2019.
1.6It is important that senior officers and members are aware of the GM Clean Air plan and a full member briefing has been arranged on 28th November 2018.
2.1Exposure to air pollution is associated with health problems including cardiovascular disease, respiratory disease (including lung cancer and asthma) and stroke. Vulnerable groups are disproportionately susceptible – children, the elderly, chronically sick and those living in the, most deprived areas. In GM poor air quality contributes to the early death of 1200 people– in Bury it would equate to 61 deaths each year.
1 2.2 There are EU targets for a number of air pollutants and Client earth (an environmental pressure group) have taken the Government to court a number of times over a failure to meet these targets for a pollutant called nitrogen dioxide (NO2) – 80% of this pollutant comes from road transport
2.3In response to this the Government has identified just over 60 UK councils that will not meet the nitrogen dioxide targets in a reasonable time. This includes Bury and 7 other GM councils namely Bolton, Manchester Salford, Stockport, Tameside, Trafford and Oldham.
2.4These councils are required to carry out feasibility studies to identify actions needed to achieve EU limit values in the shortest possible time. This plan must be produced by December 31st 2018.
2.5Charging Clean Air Zones are considered by Government to be the most likely means to achieve compliance and therefore this measure must be considered in feasibility studies.
2.6The Government has allocated £255million implementation funding and £220 million for a Clean Air Fund to allow councils to develop and deliver actions. In addition GM have already been awarded £3m to promote electric vehicles and install more rapid chargers in the GM area.
2.7As nitrogen dioxide is transport related it has been agreed that TfGM should coordinate the GM feasibility study on behalf of all 10 Local Authorities. This feasibility study will result in the GM Clean Air Plan.
3.0Progress to date
3.1So far TfGM have submitted a “Strategic Outline Case” to the Government in March 2018. This document described how we will develop the GM Clean Air Plan.
3.2As part of the feasibility study we have been required to carry out more detailed local air quality modelling (Target determination) to establish more accurately where the areas in breach of targets are. Information released on 23rd October 2018 showed that there are far more nitrogen dioxide breaches in all 10 boroughs than in the Government’s original forecasts.
3.3Originally Government assessments predicted Bury Council do not meet targets for NO2 in the busy Bury Bridge area. However further local modelling has found more areas of concern in Bury around our town centre ring road and along the A58 towards the M66 and A56 in Whitefield/Prestwich.
2 4.0 Outline Business Case (OBC)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
GREATER MANCHESTER CLEAN AIR UPDATEDecisions | 482 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Bury and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Feb 2026 | Simister and bowlee development frameworkIt was agreed that Overview and Scrutiny: i. Note the content of the Simister Bowlee Development Framework Supplement... | Agreed | Open |
| 10 Feb 2026 | Elton reservoir development frameworkIt was agreed that Overview and Scrutiny: i. Note the content of the Elton Reservoir Development Framework Supplement... | Agreed | Open |
| 3 Sep 2024 | MINUTESIt was agreed that the minutes from 24 th July 2024 be approved as a correct record and signed by the Chair. Matters ... | Agreed | Open |
| 3 Sep 2024 | Health and safety reportIt was agreed: - The report be noted | Agreed | Open |
| 24 Jul 2024 | Corporate Parenting ChampionIt was agreed: 1. Councillor Green be appointed as the Corporate Parenting Champion. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies