AGREED by 8 votes to 0 (unanimous) to adopt the proposal and agree to the installation of a seat at an estimated cost of £2,500 following a supportive consultation. Fitzroy/Burleigh Street Refurbishment AGREED by 8 votes to 0 (unanimous) to allow City officers to work with Cambridgeshire Highways to work up details of the project and return with costs.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
• Environmental Improvement Schemes for 2010/2011 Decision: To agree to officers investigating the potential projects and return to committee with further information for formal adoption.
• Gough Way – Seat Decision: Adopt the proposal and agree to the installation of a seat at an estimated cost of £2,500 following a supportive consultation.
• Fitzroy/Burleigh Street Refurbishment Decision: Agree to allow City officers to work with Cambridgeshire Highways to work up details of the project and return with costs.
2. BUDGET and DELIVERY PROGRAMME (See over)
1 2 3 4 3.0 APPROVED SCHEMES – PROGRESS
3.1Manor Street / King Street Cycle Parking Following initial consultation with property owners, the draft proposals and draft tripartite agreement has been sent to the landowner Jesus College and building owner King Street Housing for consideration.
3.2Lammas Land pavilion This scheme is being led by Active Community Officers who are currently offering the project for an additional funding contribution from Section 106 monies. Officers propose to return to West/Central Area Committee once further funding has been secured.
3.3Tree Planting on Midsummer Common, Jesus Green and New Square Work is being undertaken to develop a consultation/workshop strategy to be organised by Active Communities in order to discuss the current approaches to tree management and planting with residents and other interested parties. A solution to the progression of this work is currently being discussed with Active Communities.
3.4Mud Lane Lighting Work is continuing in a bid to secure funding for the maintenance of this lighting.
3.5Grantchester Road traffic calming features The Highway Authority have rejected the current proposals on safety grounds. We are looking at alternative proposals to resolve the issues.
3.6Gough Way – Cranmer Road Footpath : Fencing Renewal The works of renewing the fencing between the path and the grazing land from the footbridge to Cranmer Road has been completed.
4.0EXISTING SCHEMES REQUIRING DECISIONS
4.1Environmental Improvement Schemes for 2010/2011 West/Central Area Committee are asked to review the list of potential projects for 2010/2011 appended (4) to this report and agree that they should be investigated by officers and brought back to Committee with further information for formal adoption.
Recommendation : West/Central Area Committee to agree to officers investigating the potential projects and return to committee with further information.
5 Decision: To agree to officers investigating the potential projects and return to committee with further information for formal adoption.
4.2Gough Way – Seat A local resident has requested that a seat be installed on Gough Way for bus passengers to wait. The location of the seat would be on Highways land. Highways have been consulted and have agreed to the location. Officers would intend to carry out a small local consultation and if supportive would install a seat in the location shown on the attached appended drawing.
Recommendation : Officers recommend that the West/Central Area Committee formally adopt the proposal and agree to the installation of a seat at an estimated cost of £2,500. Installation would be carried out only following a supportive consultation.
Decision: Adopt the proposal and agree to the installation of a seat at an estimated cost of £2,500 following a supportive consultation.
4.3Fitzroy/Burleigh Street Refurbishment The draft proposals for the refurbishment of Fitzroy/Burleigh Street have been put to public consultation between 10 and 24 March 2010. The consultation summary/analysis is appended to this report. The analysis shows overwhelming support for the works to be implemented.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Policing and Safer Neighbourhoods WCACAgreed to speak with Inspector McNeill on how to improve the message of successes and if a briefing note could be cir...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.