Procurement of Construction Services

Agreed Scrutiny 1 paper

Environment Scrutiny Committee agreed this item on Tuesday 5 October 2010. Below is the council's own wording, with the papers it was decided on.

Item10/61/ESC

Resolved

The City Council is planning to tender a new framework agreement to provide civil engineering construction services across all of its user departments. These services are planned to be in place by summer 2011, following a procurement process. In the meantime an interim supplier of civil engineering construction services is required, to enable the City Council to continue to deliver its services. This report requests an approval to procure civil engineering construction services from Cambridgeshire Highways, through a written agreement with Cambridgeshire County Council, in accordance with the City Council’s procurement rules. Decision of Exec Cllr for Climate Change and Growth: I. Approved the procurement of interim civil engineering construction services from Cambridgeshire Highways through a written agreement with Cambridgeshire County Council in accordance with City Council procurement rules and relevant legislation. II. Noted the proposed development of a new City Council framework agreement for civil engineering construction services. Reason for the The City Council has a requirement for construction services across many departments, from housing maintenance to capital environmental improvements (EIP), of which EIP schemes form the majority. The Legal Services Team has reviewed the Cambridgeshire Highways Contract. In their opinion, the arrangements that we are proposing to put in place with the County Council, to deliver City Council schemes through this contract are acceptable. Any alternative options considered and rejected: I. Letting a new contract for construction services. This is planned, but as indicated, the timescales associated with the procurement process would not allow any construction work to be completed this financial year. Additionally a review of the long term funding of the EIP programme is due in October 2010 and until that is completed there is no clear vision of future work volumes. II. Requesting individual quotations for each item of work. This would not only be resource intensive, significantly reducing the amount of work constructed, but would also fail to meet the procurement rule associated with the aggregation of contracts and not bring economies of scale. III. An agreement with Cambridgeshire County Council to provide construction services through their contract with Cambridgeshire Highways is seen as the most appropriate option to ensure the continuation of the delivery of City Council projects planned for this financial year. Scrutiny Considerations: The committee received a report form the Environmental Projects Manager. The Scrutiny Committee considered and endorsed the recommendations in the report by 6 votes to 0. The Executive Councillor for Climate Change and Growth approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

The City Council is planning to tender a new framework agreement to provide civil engineering construction services across all of its user departments. These services are planned to be in place by summer 2011, following a procurement process. In the meantime an interim supplier of civil engineering construction services is required, to enable the City Council to continue to deliver its services. This report requests an approval to procure civil engineering construction services from Cambridgeshire Highways, through a written agreement with Cambridgeshire County Council, in accordance with the City Council’s procurement rules.

Recommendations

2.1The Executive Councillor is recommended:

• To approve the procurement of interim civil engineering construction services from Cambridgeshire Highways through a written agreement with Cambridgeshire County Council in accordance with City Council procurement rules and relevant legislation. • To note the proposed development of a new City Council framework agreement for civil engineering construction services.

Background

3.1The City Council has a requirement for construction services across many departments, from housing maintenance to capital environmental improvements (EIP), of which EIP schemes form the majority. Report Page No: 1 3.2 A new framework agreement is proposed to be advertised and be in place by summer 2011. A significant amount of construction work is planned before then, as such an interim Contractor who will work on a call off basis is required as soon as possible.

3.3The possible options that have been reviewed include:

• Letting a new contract for construction services. This is planned, but as indicated, the timescales associated with the procurement process would not allow any construction work to be completed this financial year. Additionally a review of the long term funding of the EIP programme is due in October 2010 and until that is completed there is no clear vision of future work volumes. • Requesting individual quotations for each item of work. This would not only be resource intensive, significantly reducing the amount of work constructed, but would also fail to meet the procurement rule associated with the aggregation of contracts and not bring economies of scale. • An agreement with Cambridgeshire County Council to provide construction services through their contract with Cambridgeshire Highways is seen as the most appropriate option to ensure the continuation of the delivery of City Council projects planned for this financial year.

3.4The Legal Services Team has reviewed the Cambridgeshire Highways Contract. In their opinion, the arrangements that we are proposing to put in place with the County Council, to deliver City Council schemes through this contract are acceptable.

3.5The Procurement Team has ensured that the strategy proposed is fully in line with both the Council's own Contract Procedure Rules and wider procurement legislation. These issues have been addressed with the following conclusions:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of Construction ServicesReport 71 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
TW
Councillor Tim WardChair, present
SK
Councillor Simon KightleyVice-Chair, present
LH
Councillor Lewis Herbert Labour Spokes on Climate Change and GrowthCommittee Member, present
SK
Councillor Susannah KerrCommittee Member, present
SN
Councillor Stuart Newbold Labour Spokes on Environmental and Waste ServicesCommittee Member, present
AP
Councillor Adam Pogonowski Green SpokesCommittee Member, present
PS
Councillor Paul SaundersCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present
RZ
Councillor Roman ZnajekCommittee Member, present

On this subject at Cambridge

Search all
  1. Procurement of Construction ServicesThis decision
  2. Civil Engineering Construction Framework ProcurementApproved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies