Environment Scrutiny Committee, Tuesday 5 October 2010 at 9.30am

Bus Shelter Framework Contract

Agreed Scrutiny 1 paper

Environment Scrutiny Committee agreed this item on Tuesday 5 October 2010. Below is the council's own wording, with the papers it was decided on.

Item10/62/ESC

Resolved

The City Council has already identified a capital programme for the replacement and provision of new bus shelters across Cambridge. In order to deliver the remit of this capital programme, the award of a new Framework Agreement for bus shelters is necessary. A 4 year framework is proposed, with a first year contract value of circa £221,000. Further use of this agreement would also be available in the subsequent 3 years, subject to further approved capital funding. Decision of Exec Cllr for Climate Change and Growth: Approved the procurement and contract award of a new framework agreement for bus shelter suppliers in order to deliver the City Council Capital Programme for new and replacement bus shelters for a maximum period 2011-2015 at an estimated first year value of £221,000, with the facility for any future approved capital funding to make use of this framework during 2012 - 2015. Reason for the For passengers and prospective service users, bus shelters are a gateway to the public transport system, contributing to the perception that residents and visitors have of their public transport network. They are also important items of street furniture and their physical appearance, location and branding impacts considerably on the surrounding area. The varied ownership and maintenance of bus shelters is currently too complex and inefficient. This procurement process plans to reduce this complexity and provide a more efficient format for managing the bus shelter stock. Any alternative options considered and rejected: N/A Scrutiny Considerations: The committee received a report from the Environmental Projects Manager. In response to members questions, the officer outlined the consultation process and stated that the final decision would be brought to this committee in March. The procurement process was being undertaken with other authorities and a Project Team, including the Urban Design Team would consider issues such as, vandal prevention, sustainability, design, cost and quality. The Project Team would select three or four styles which could be used to suit the various locations. Ward Councillors would be consulted as part of this shortlisting process. However, the aim is to produce a coherent look across the City. On-going maintenance will be simpler if there are fewer styles across the City. On new developments and fringe sites, developers would be encouraged to use the same suppliers. The existing arrangement with Adshel, who have provided and maintain 84 shelters at not cost to the City, will continue to run until the end of the agreement in 2019. These shelters are also owned by Adshel. The Scrutiny Committee considered and endorsed the recommendations in the unanimously . The Executive Councillor for Climate Change and Growth approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

The City Council has already identified a capital programme for the replacement and provision of new bus shelters across Cambridge. In order to deliver the remit of this capital programme, the award of a new Framework Agreement for bus shelters is necessary. A 4 year framework is proposed, with a first year contract value of circa £221,000. Further use of this agreement would also be available in the subsequent 3 years, subject to further approved capital funding.

Recommendations

2.1The Executive Councillor is recommended:

• To approve the procurement and contract award of a new framework agreement for bus shelter suppliers in order to deliver the City Council Capital Programme for new and replacement bus shelters for a maximum period 2011-2015 at an estimated first year value of £221,000, with the facility for any future approved capital funding to make use of this framework during 2012 - 2015.

Background

3.1For passengers and prospective service users, bus shelters are a gateway to the public transport system, contributing to the perception that residents and visitors have of their public transport network. They are also important items of street furniture and their physical appearance, location and branding impacts considerably on the surrounding area.

Report Page No: 1 3.2 There are 168 bus shelters in Cambridge (excluding the Drummer St, Addenbrookes and the Grafton Centre bus stations).

3.384 of these are owned by Clear Channel (Adshel) and are subject to a written agreement between Adshel and Cambridge City Council, which was signed in 1999 with a duration of 20 years. This agreement will remain in place through to its planned completion in 2019.

3.4The Adshel agreement with the City Council includes repairs, maintenance and cleaning and provides minimum acceptable performance requirements in these areas.

3.5Cambridge City Council owns and maintains 59 bus shelters, some of which date back to the 1960s. They are of varying designs, making it increasingly difficult and in some cases impossible to stock spare parts and provide an appropriate level of maintenance.

3.6Abacus, the City Council’s long-term suppliers of City owned shelters have pulled out of the bus shelter market severely hindering the procurement of spare parts.

3.7The County Council have purchased and own 25 Adshel shelters installed as part of their work to Drummer St, Emmanuel St, St Andrews St, the Guided Bus and the Railway Station. There is currently no maintenance carried out on these shelters.

3.8The varied ownership and maintenance of bus shelters is currently too complex and inefficient.

3.9This procurement process plans to reduce this complexity and provide a more efficient format for managing the bus shelter stock.

3.10A collaborative procurement approach with the County Council is proposed (and we are exploring possible interest of other Councils) in order to simplify the number of different shelter suppliers and increase the competitiveness of the tender process. The Eastern Shires Purchasing Organisation (ESPO) will run the procurement exercise.

3.11A 4 year framework agreement containing more than one supplier is likely to be chosen to provide a defined pallet of different styles of shelter linked to different areas of the City.

3.12Optional items for maintenance, spare parts, advertising and civil installation costs may also be included as part of the contract.

Report Page No: 2 3.13 In order to inform the procurement of new shelters, a bus shelter strategy is currently being developed to propose the most appropriate sites for new or replacement shelters.

3.14A condition survey has been carried out for the City owned shelters in order to inform the strategy for replacements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Bus Shelter Framework ContractReport 49 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 9 attended
TW
Councillor Tim WardChair, present
SK
Councillor Simon KightleyVice-Chair, present
LH
Councillor Lewis Herbert Labour Spokes on Climate Change and GrowthCommittee Member, present
SK
Councillor Susannah KerrCommittee Member, present
SN
Councillor Stuart Newbold Labour Spokes on Environmental and Waste ServicesCommittee Member, present
AP
Councillor Adam Pogonowski Green SpokesCommittee Member, present
PS
Councillor Paul SaundersCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, present
RZ
Councillor Roman ZnajekCommittee Member, present

On this subject at Cambridge

Search all
  1. Bus Shelter Framework ContractThis decision
  2. New and Replacement Bus Shelter ProgrammeApproved
  3. New and Replacement Bus Shelter ProgrammeApproved
  4. New and Replacement Bus Shelter Project AppraisalApproved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies