Development Plan Scrutiny Sub-Committee approved this item on Tuesday 15 February 2011. Below is the council's own wording, with the papers it was decided on.
The purpose of the report was to seek final approval of the Eastern Gate Visioning Document from the Executive Councillor for Climate Change and Growth. Decision of Exec Cllr for Climate Change and Growth: The Executive Councillor is recommended to approve the final version of the Eastern Gate Visioning Document dated January 2011. Reason for the Approval was given to the recommended changes to the previous draft document at the Development Plan Steering Sub-Committee at the meeting of December 14, 2010, and this recommendation simply requests final approval of those changes. Any alternative options considered and rejected: N/A Scrutiny Considerations: Members expressed support for the changes. The Scrutiny Committee considered and endorsed the recommendations in the report unanimously . The Executive Councillor for Climate Change and Growth agreed the decision. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1The purpose of this report is to seek final approval of the Eastern Gate Visioning Document from the Executive Councillor for Climate Change and Growth. Approval was given to the recommended changes to the previous draft document at the Development Plan Steering Sub-Committee at the meeting of December 14, 2010, and this recommendation simply requests final approval of those changes.
Recommendations
2.1The Executive Councillor is recommended to approve the final version of the Eastern Gate Visioning Document dated January 2011.
Background
3.1Following approval of the recommended changes to the Draft Eastern Gate Visioning Document as discussed at DPSSC on 14th December, 2010, a final version of the document was circulated to Chair, Spokes, Opposition and the Executive Councillor on January 20, 2011, by email for final agreement. Officers circulated a table of the final changes to the document, together with a final version of the document with changes made between the draft and final version shown highlighted. The above recommendation merely gives final approval to all changes proposed and agreed. The Joint Urban Design Team are now moving forward with preparing a Development Framework as an SPD and it is proposed that the draft SPD will be considered at the DPSSC meeting of March 22, 2011. For ease of reference, the final version (with changes shown highlight in yellow colour) can be found at http://www.sendspace.com/file/4xrtua and for information is a table of the changes made to the document as a Word document attached as an appendix.
Report Page No: 1 4. Implications Financial Implications: 4.1 There are no significant direct staffing or procurement issues arising from this report. Staffing resources are already committed through the budget and service plan process. Funding may be necessary for consultation purposes but this can be found in existing consultation budgets.
4.2Funding for key projects will be considered in detail when preparing the draft Eastern Gate Area Development Framework (SPD).
Staffing Implications: 4.3 Further development of the Visioning Document into a Development Framework (SPD) will take considerable officer effort and time, although it should be noted that this is already factored into the Joint Urban Design Team Service Plan for 2010-11.
Equal Opportunities Implications: 4.4 An Equality Impact Assessment will be undertaken as part of the pre-production work for the Development Framework (SPD).
Environmental Implications: 4.5 The improvement of the Eastern Gate area as set out in the Visioning Document, and as planned to be set out in the future Development Framework (SPD), has the potential to considerably improve the environmental quality of the area overall.
4.6In order to ensure the principles of sustainable development are taken into account, a Sustainability Appraisal will be undertaken for the Eastern Gate Development Framework (SPD). The appraisal will identify the likely economic, social and environmental effects of the Development Framework for the area.
Community Safety: 4.7 The improvement of the Eastern Gate area as set out in the Visioning Document has the potential to significantly improvement the quality, attractiveness and safety of the public realm.
Background papers
5.1These background papers were used in the preparation of this report: Eastern Gate Visioning Document – Draft for Consultation, July 2010.
Report Page No: 2 6. Appendices
See final version of the Eastern Gate Visioning Document at http://www.sendspace.com/file/4xrtua (hard copies of same can be printed for committee members if necessary).
A table of the final changes is also attached: “Overview of amendments made to the Visioning Document following DPSSC on 14th December 2011”.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Plan Scrutiny Sub-Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.