Agreed Committee 1 paper

East Area Committee agreed this item on Thursday 23 June 2011. Below is the council's own wording, with the papers it was decided on.

Item11/33/EAC

Resolved

Agreed (unanimously) to approve the scheme for implementation subject to positive consultation at an estimated cost of £14,000 . 2. No waiting & 1hr Parking Restrictions To introduce ‘no waiting at any time’ restrictions at the junction of Birdwood Road/St Thomas’ Road and Coleridge Road/Brackyn Road to prevent obstructive parking. Measures to prevent commuter parking in Corrie Road, Rustat Road and Davy Road. Agreed (unanimously) to approve the scheme for implementation subject to positive consultation at an estimated cost of £10,000 . 3. Riverside Railings Refurbishment Refurbishment of the railings along Riverside, a 100m continuation of the current refurbishment being carried out at part of the Riverside EIP scheme. Agreed (unanimously) to approve the scheme for implementation subject to positive consultation at an estimated cost of £250 per linear metre 4. Silverwood Close and Whitehill Road Estate Verge Parking The introduction of a verge parking prohibition. Agreed (unanimously) to approve the scheme for implementation subject to positive consultation at an estimated cost of £ 8,000 5. Tree Planting on Chalmers Rd & Greville Rd Planting of 7 trees on Greville Rd and 5 on Chalmers Road, as suggested by residents on Chalmers Rd and to supplement the new bollards on Greville Rd. Agreed (unanimously) to approve the scheme for implementation subject to positive consultation at an estimated cost of £5,000 . 6. Brooks Road / Perne Road Verge Parking Prohibition The prohibition of verge parking on Brooks Road and Perne Road, including renovation of verges in particularly poor condition. Agreed (unanimously) to approve the scheme for implementation subject to positive consultation at an estimated cost of £7,500 . ANY OF THE ABOVE SCHEMES THAT ARE WITHIN THE HIGHWAY WILL REQUIRE APPROVAL BY THE COUNTY COUNCIL AS THE HIGHWAY AUTHORITY. 7. Stanley Road/Garlic Row Rat-Running The issue of HGVs using Stanley Road is difficult to resolve. A weight limit could be introduced, but this would require enforcement and would be subject to Highway Authority approval. The attraction to HGV traffic is their ability to turn right from Stanley Road into Newmarket Road, which is not possible when exiting from Garlic Row. This matter should be raised with the County Council to determine whether there are any feasible options. Agreed (unanimously) to approve the scheme for implementation subject to positive consultation at an estimated cost of £4000 . Action Point: Environmental Projects Manager to circulate a suggestions sheet for cycleway schemes for prioritisation for delivery through the City/County joint cycleways.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to East Area Committee

CAMBRIDGE CITY COUNCIL Item

Report Andrew Preston, Environmental Projects Manager by: To: East Area Committee 23 June 2011

Wards: Abbey, Coleridge, Petersfield, Romsey

Environmental Improvement Programme

1.0Adoption of Proposed New Schemes for 2011/12 Programme.

Decision: To determine which of the proposed schemes should be adopted as part of the delivery programme for 2011/12 and implemented subject to positive consultation.

2.0BUDGET

Please see over. EAST AREA COMMITTEE Environmental Improvements Programme 2011-2012

Budget for 2011/2012 financial year 56200 Add funding rephased from previous financial years 302000

Total Budget Available to 31/3/12 £358,200

COMPLETE Total Spend Forecast TOTAL Previous Spend SCHEME Approved Years 2011/12 COST Budget ADOPTED PROJECTS £ £ £ £ Mill Road Hanging Baskets 2011 0 7,500 7,500 7,500 Cherry Hinton Road Shop Forecourts 5,650 64,350 70,000 70,000 Riverside Conflict Reduction Scheme 60,000 60,000 120,000 120,000 Cavendish Road 26 14,974 15,000 15,000 Staffordshire Street Verge Parking 3 20,547 64,453 85,000 85,000 Devonshire Road Cycle Bridge Planting 3 10,702 1,500 12,202 17,500 Highway Verges Scheme 3 32,000 48,000 80,000 93,500 Mill Road Cemetery 3 0 5,000 5,000 5,000 Romsey Planting 10,175 11,825 22,000 22,000 Rustat Road Footpath 3 6,624 350 6,974 10,000 total cost to implement adopted projects 277,952

Uncommitted Budget 80,248

Total Total Spend Estimated to Date Cost SCHEMES UNDER DEVELOPMENT* £ £

total estimated cost of projects in development 0 0

Uncommitted Budget 80,248

*Projects agreed by Ctte to be investigated, but no budget committed. Costs shown are estimated and will depend on detailed design and site investigation. N.B. The estimated costs shown above are merely given as a rough guide until the projects can be designed and costed.

23 June 2011 3.0 UPDATE ON PROGRESS OF EXISTING SCHEMES

3.1Riverside conflict reduction and environmental improvement scheme This scheme is currently under construction and is 70% complete. The scheme is due to be complete by mid July.

3.2Cherry Hinton Road Shop Forecourts This scheme is currently under construction and is 75% complete. The scheme is due to be complete by the end of June.

3.3Perne Road The provision of this new pedestrian crossing is now complete.

3.4Staffordshire Street This scheme is now complete, with the exception of the planting, which will take place in October at the start of the planting season.

3.5Romsey Planting The planting beds have been reconstructed, the planting will take place in October at the start of the planting season.

3.6Greville Rd Verges This scheme is now complete.

3.7Birdwood/Chalmers Verges This scheme is now complete.

3.8Rawlyn Road Verges The road widening at either end of Rawlyn Road is now complete.

3.9Galfrid Road Verges The provision of blockwork surfaced layby at the corner of Galfrid Road and Whitehill Road is now complete.

3.10Rustat Road Footpath Extension This scheme is now complete. The replacement hedge will be planted in the autumn.

3.11Burnside Toad Crossings These are now complete.

3.12Mill Road Cemetery The £5000 grant has been provided. 3.13 Mill Road/Cavendish Road This scheme to improve the landscaping at the junction of Mill Road and Cavendish Road has been delayed due to the need for a lease agreement with the shoe shop owner for the provision of a disabled parking space on City Council owned land. The shop owner is also funding the cost of the work associated with the parking bay. Until we are in receipt of a signed agreement and the necessary funding we cannot commence this scheme.

4.0NEW SCHEMES IN DEVELOPMENT FOR ADOPTION

4.1Ditton Walk/Newmarket Rd Planting – promoted by Cllr Wright Introduction of a planting area at the junction of Ditton Walk and Newmarket Road as per the drawing attached in Appendix 1. Estimated cost - £14,000

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Environmental Improvement ProgrammeReport 254 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 16 attended
LH
Councillor Lewis HerbertChair, present
MW
Councillor Margaret WrightVice-Chair, present
JB
Councillor Jeremy BensteadCommittee Member, present
KB
Councillor Kevin BlencoweCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
CH
Councillor Caroline HartCommittee Member, present
GM
Councillor Gail Marchant-DaisleyCommittee Member, present
ZM
Councillor Zoe MoghadasCommittee Member, present
GO
Councillor George OwersCommittee Member, present
AP
Councillor Adam PogonowskiCommittee Member, present
PS
Councillor Paul SaundersCommittee Member, present
CS
Councillor Catherine Smart Liberal Democrat SpokesCommittee Member, present

All 16 on the meeting page

On this subject at Cambridge

Search all
  1. Environmental Improvement ProgrammeThis decision
  2. Review of the Environmental Improvement ProgrammeAgreed
  3. Environmental Improvement ProgrammeApproved
  4. Environmental Improvement ProgrammeAgreed
  5. Environmental Improvement ProgrammeAgreed
  6. Environmental Improvement Programme 2017-18Noted

More from Cambridge East Area Committee

All decisions
MeetingDecisionOutcome
24 Jun 2021 Open ForumAgreed it was vital that residents understood the documentation and would be happy to arrange assistance when looking... Agreed Open
3 Dec 2020 Policing and Safer NeighbourhoodsRESOLVED unanimously to write to the Acting Police and Crime Commissioner highlighting the Committee’s concern regard... Decided Open
17 Sep 2020 Election of Chair and Vice Chair - EACResolved unanimously that Councillor Barnett be Chair for the ensuing year. Councillor Barnett assumed the chair from... Decided Open
17 Sep 2020 Policing and Safer NeighbourhoodsResolved unanimously to approve the following as local areas of concern: i. Anti-social driving ii. Cycle theft iii. ... Approved Open
17 Sep 2020 Outside Body Appointment: Cambridge Airport Consultative CommitteeResolved that Councillor Davey be the representative for the Cambridge Airport Consultative Committee for the ensuing... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies