Decision of the Executive Councillor for Customer Services and Resources The Executive Councillor resolved to Financial recommendations i. Approve commencement of the project, which is already included in the Council’s Capital Plan (Programme Reference PR024). Procurement recommendations : ii. Approve the carrying out and completion of the procurement of the . iii. Agree that if the quotation or tender sum exceeds the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Resources will be sought prior to proceeding. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected : N/A Scrutiny Considerations N/A The Executive Councillor for Customer Services and Resources approved the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Summary
1.1The project The project is for the upgrade to fire detection systems within various commercial properties owned by Cambridge City Council and leased out to tenants. The properties affected are Barnwell House, Orwell House, Dales Brewery and Gwydir Street.
Target Start date July 2011 Target completion date March 2012
1.2The Cost Total Capital Cost £53,000
Capital Cost Funded from:
Funding: Amount: Details:
Reserves £
Repairs & Renewals £53,000 27720 & 27725
Section 106 £
Other £
Revenue Cost
Year 1 £0
Ongoing £0
There are no additional revenue implications arising from the project. Page 3 of 7
1.3The Procurement An external contractor will undertake the works.
The works will be subject to tender in line with the Council’s Constitution. All other resources will be met from in-house staffing levels.
2 Capital Project Appraisal & Procurement Report
2.1What is the project? The project is for the upgrade to fire detection systems within various commercial properties owned by Cambridge City Council and leased out to tenants. The properties affected are Barnwell House, Orwell House, Dales Brewery and Gwydir Street. The fire detection systems need to be upgraded in order to comply with current fire regulations.
The extent of the work was identified through a Fire Risk Assessment that was carried out by Blackbird Surveys Ltd.
The buildings are typically unoccupied during anti-social hours, which means that the risk of arson is increased. Although the upgrade work will not reduce the risk of arson, the improvements should lead to early detection of a fire and thus reduce the risk of the total loss of a building. Page 4 of 7
2.2What are the aims & objectives of the project? The aims and objectives of the project are primarily to ensure that tenants have the best chance of escape in the event of a fire and to comply with current fire regulations. The project contributes to the Council’s vision for: “A city where people behave with consideration for others and where harm and nuisance are confronted wherever possible without constraining the lives of all.”
2.3Summarise the major issues for stakeholders & other departments? Tenants of the various commercial properties will be consulted when details of the work involved and the timescales are drawn up.
Disruption will be kept to a minimum.
2.4Summarise key risks associated with the project If the upgrade work to the fire detection systems is not carried out, there is a risk that the Council will be in breach of current fire regulations and could be prosecuted.
The Fire Reform Act 2006 puts the onus on the property owner to undertake a fire risk assessment and implement any findings that would reduce the risk of fire and loss of life.
Failure to carry out the improvements could result in the Council not being able to recoup any losses in the event of a fire in one of the buildings due to inadequate fire detection.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Salah Al BanderCommittee Member, present
MA
Councillor Mark AshtonCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
IN
Councillor Ian Nimmo-SmithCommittee Member, present
AP
Councillor Adam PogonowskiCommittee Member, present
PS
Councillor Paul SaundersReserve, present
Hear about the next one first
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.