Decision of the Executive Councillor for Customer Services and Resources The Executive Councillor for Customer Services and Resources resolved to recommend to Council for approval i. Carry forward requests, totalling £160, 860 ii. Carry forward capital resources of £1,011,000 to fund re-phased net capital spending from 2010/11 into 2011/12 (and future years) Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected : N/A Scrutiny Considerations: The committee received a report from the Director of Resources regarding the 2010/11 Outturn – Customer Services and Resources Change Portfolio. The Scrutiny Committee considered and approved the recommendations by 5 votes to 0. The Executive Councillor for Customer Services and Resources approved the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
1.1This report presents a summary of the 2010/11 outturn position (actual income and expenditure) for services within the Customer Services & Resources portfolio, compared to the final budget for the year. The position for revenue and capital is reported and variances from budgets are highlighted, together with explanations. Requests to carry forward funding arising from certain budget underspends into 2011/12 and future years are identified.
Recommendations
The Executive Councillor is recommended:
a) To agree which of the carry forward requests, totalling £160,860 as detailed in Appendix C, are to be recommended to Council for approval.
b) To seek approval from Council to carry forward capital resources to fund re-phased net capital spending of £1,011,000 from 2010/11 into 2011/12 and future years, as detailed in Appendix D.
Report Page No: 1 3. Background
Revenue Outturn
3.1The outturn position for the Customer Services & Resources portfolio, compared to the final revenue budget, is presented in detail in Appendix A.
3.2Appendix B to this report provides explanations of the main variances.
3.3Appendix C sets out the final list of items, for this portfolio, for which approval is sought to carry forward unspent budget from 2010/11 to the next financial year, 2011/12.
3.4The overall revenue budget outturn position for the Customer Services & Resources portfolio is set out in the table below:
Variation – (Under)/Overspend for the year (822,046) Carry Forward Requests: Customer Access Strategy 133,860 Customer Service Centre 27,000
Total Carry Forward Requests 160,860
Net Variance (661,186)
The variance represents 23.5% of the overall portfolio budget for the 2010/11 financial year.
Capital Outturn
3.5Appendix D shows the outturn position for schemes and programmes within the Customer Services & Resources portfolio, with explanations of variances.
Report Page No: 2 3.6 An overall underspend of £1,173,000 has arisen. £1,011,000 is due to slippage and re-phasing of the capital programme is required to transfer the budget into 2011/12 and future years. The remaining variance of £162,000 is a result of net underspends on individual capital schemes and programmes.
4. Implications
4.1The net variance from the final budget, after approvals to carry forward budget of £160,860 from 2010/11 to the next financial year, 2011/12, would result in a reduced use of General Fund reserves of £661,186.
4.2In relation to anticipated requests to carry forward revenue budgets into 2011/12, the decisions made may have a number of implications. A decision not to approve a carry forward request will impact on officers’ ability to deliver the service or scheme in question and this could have staffing, equal opportunities, environmental and/or community safety implications.
Background papers
These background papers were used in the preparation of this report:
• Closedown Working Files 2010/11 • Directors’ Variance Explanations – March 2011 • Capital Monitoring Reports – March 2011 • Budgetary Control Reports to 31 March 2011
Appendices
• Appendix A - Revenue Budget 2010/11 - Outturn • Appendix B - Revenue Budget 2010/11 - Major Variances from Final Revenue Budgets • Appendix C - Revenue Budget 2010/11 - Carry Forward Requests • Appendix D - Capital Budget 2010/11 - Outturn
Report Page No: 3 7. Inspection of papers
To inspect the background papers or if you have a query on the report please contact:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.