Clay Farm Land Disposal Project - Budget for Up-front Costs

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 10 October 2011. Below is the council's own wording, with the papers it was decided on.

Item11/70/SR

Resolved

To consider the budget for up-front costs to support the delivery of the Clay Farm Land Disposal Project. Decision of the Executive Councillor : The Executive Councillor for Customer Services and Resources resolved to i. Approve a budget of £117,000 to cover up-front costs of the disposal of the Council’s land at Clay Farm. Reasons for the As set out in the officer’s report Any alternative options considered and rejected: N/A Scrutiny Considerations The committee received a report from the Head of Strategic Housing seeking approval for an upfront budget to support the project to dispose of land at Clay Farm. The Head of Strategic Housing agreed to respond to Councillor Brown outside of the meeting regarding the safeguards for maintaining future access arrangements for ramblers and dog walkers. The Scrutiny Committee considered and approved the recommendations by 8 votes to 0 The Executive Councillor for Customer Services and Resources approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

A budget is required to cover legal advice, site survey and external input on the procurement to dispose of the Council’s land at Clay Farm. Quantity Surveyor input is also required on the Collaboration Agreement. It is proposed that these costs are initially met from use of the Property Strategy Fund, which is then repaid from the receipt on the sale of the land.

Recommendations

The Executive Councillor is recommended:

To approve a budget of £117,000 to cover up-front costs of the disposal of the Council’s land at Clay Farm.

Background

The Strategy and Resources Committee on 4 July 2011 considered a report setting out options to dispose of the Council’s land at Clay Farm. Following the Executive Councillor’s approval for officers to pursue a preferred option for the disposal, further work has been carried out on up-front costs associated with this option. The costs are in respect of legal advice, site survey and external input on the procurement, particularly in terms of the specification for quality architecture and environmental sustainability. Quantity Surveyor input is also required on the Collaboration Agreement.

4. Implications Report Page No: 1 (a) Financial Implications

The budget of £117,000 is made up as follows;

Legal Advice – In consultation with Legal Services the officer Project Group has agreed that it would be best to commission one external practice to provide advice on the various dimensions of the project eg

- the best legal agreement to enforce the conditions on the land sale - to advise on VAT; Stamp Duty; and State Aid issues - to advise on consents from the Government to dispose of the land - to ensure we comply with procurement regulations

Work has started to seek quotes from legal partners on the Council’s Legal Services Framework list. The quotations will be available at the end of September and an estimated budget of £50,000 has been assumed at this point.

External Specialist Consultants – The July 2011 Committee Report signalled the intention to recruit external specialists in respect of design and sustainability to validate the Brief to be used in the procurement and associated documents for the disposal. The Project Group has made contact with a number of agencies and costs range up to £1000 per day. An estimated budget of £20,000 has been assumed.

Procurement Administration – To satisfy European Union procurement regulation the land disposal will need to be administered in a prescribed way. The Council has found through successive procurements that recruiting a specialist in this respect is efficient in terms of the extensive paperwork required. An estimated budget of £10,000 has been assumed.

Quantity Surveyor – Input is required to validate the Infrastructure Costs that Countryside Properties Limited will charge the Council under the Collaboration Agreement in respect of the development of Clay Farm. An estimated budget of £2,000 has been assumed.

Site Survey and Investigations – If these not provided with the tender documents to bidders will factor in a cost to cover their risk for any unforeseen site conditions and therefore will bid less for the land. An estimated budget of £30,000 has been assumed.

Contingency – To cover any unforeseen costs such as legal searches; printing costs. An estimated budget of £5,000 has been assumed.

Report Page No: 2 It is recommended that these costs are initially met from use of the Property Strategy Fund, which is then repaid from the receipt on the sale of the land.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Clay Farm Land Disposal Project: Budget for Up-front CostsReport 49 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
MB
Councillor Max BoyceChair, present
CR
Councillor Colin RosenstielVice-Chair, present
SA
Councillor Salah Al BanderCommittee Member, apologies, sent representative
MA
Councillor Mark AshtonCommittee Member, present
JB
Councillor Jeremy Benstead Labour Spokes for Customer Services and ResourcesCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
IN
Councillor Ian Nimmo-SmithCommittee Member, present
AP
Councillor Adam Pogonowski Green SpokesCommittee Member, present
PS
Councillor Paul SaundersReserve, present as substitute

On this subject at Cambridge

Search all
  1. Clay Farm Land Disposal Project - Budget for Up-front CostsThis decision
  2. Review of Shared Ownership Housing at Virido, Clay FarmApproved
  3. 17/1461/REM: Cycleway/footway - Land Adjacent to Cambridge Guided Busway and Adjacent to existing plantation within abode 1 (Parcels 10, 11 and 12), Clay Farm, Trumpington, Cambridge.Decided
  4. 16/2149/REM: Land between 125 and 129 Shelford Road and Clay Farm Parcel 12CApproved
  5. AI/JS/39/117: Clay Farm development, Public Footpath 117- running along the rear of Foster Road propertiesApproved
  6. Review of Governance Arrangements for Clay Farm Community CentreAgreed

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open