CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Strategy and Resources Scrutiny Committee, Monday 10 October 2011 at 5.30pm

Office System Upgrade project

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 10 October 2011. Below is the council's own wording, with the papers it was decided on.

Item11/72/SR

Resolved

To consider the project appraisal for the Office System Upgrade project. Decision of the Executive Councillor : The Executive Councillor for Customer Services and Resources resolved to i. Approve the commencement of the project, which is already included in the Council’s Capital Plan (Programme Reference PR020), with a total capital cost of £290,000 to be funded from the IT Software Replacement Repairs and Renewal fund. ii. Approve the procurement of licences and ordering of project work to carry out the upgrade unless the quotation or tender sum exceeds the estimated contract value by more than 15%. If the contract value is exceeded by more than 15% permission of the Executive Councillor and Director of Resources will be sought prior to proceeding. Reasons for the As set out in the officer’s report Any alternative options considered and rejected: N/A Scrutiny Considerations The committee received a report from the Head of ICT Client and the ICT Client Manager seeking approval to proceed with the “Office Upgrade Project”. The committee made the following comments regarding the report i. Disappointment was expressed that it was not possible to find an appropriate open source solution, but it was acknowledged that at the moment Microsoft was the only practical solution. ii. Due to the nature of the changes from pre 2007 version, the importance of robust and effective training was emphasised to ensure that the efficiency of the council was not undermined during the transition. Members were assured that a robust and extensive training programme was planned. The Scrutiny Committee considered and approved the recommendations by 8 votes to 0 The Executive Councillor for Customer Services and Resources approved the recommendation.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Page 1 of 8

Project Appraisal and Scrutiny Committee Recommendation

Project Name Office Systems Upgrade Strategy and Resources Scrutiny Committee Committee Customer Services and Resources Portfolio Portfolio Committee Date 10th October 2011 Executive Councillor Cllr Neil McGovern Lead Officer James Nightingale

Recommendation/s Financial recommendations –

• The Executive Councillor is asked to approve commencement of the project, which is already included in the Council’s Capital Plan (Programme Reference PR020). The total capital cost of the project is £290,000, to be funded from the IT Software Replacement Repairs and Renewal fund. • There are no additional revenue implications arising from the project.

Procurement recommendations: • The Executive Councillor is asked to approve procurement of licences and ordering of project work to carry out the upgrade. • If the quotation or tender sum exceeds the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Resources will be sought prior to proceeding. Page 2 of 8 1 Summary 1.1 The project To upgrade the Council’s office system to Microsoft Office 2010

Target Start date October 2011 Target completion date March 2012

1.2The Cost £290,000 Total Capital Cost (£200,000 licences + £90,000 implementation)

Capital Cost Funded from:

Funding: Amount: Details:

Reserves £0 Repairs & IT Software Replacement £290,000 Renewals R&R fund 27749 Section 106 £0

Other £0

Revenue Cost

Year 1 £0

Ongoing £0

There are no additional revenue implications arising from the project. Page 3 of 8

1.3The Procurement

The Microsoft Office Licences are to be procured under a government framework contract. For 1,000 licences, with a split of 70% MS Office Standard and 30% MS Office Professional (including MS Access), the estimated cost will not exceed £200,000. The estimated Serco capital costs are £90,000 and will be purchased via existing contract arrangements.

2 Capital Project Appraisal & Procurement Report

2.1What is the project? The Council uses MS Office 2000 (Word, Excel, PowerPoint, and Access) as its standard office product on 1,000 desktops and laptops. Many of the Office licences currently in use were brought in 1999/2000.

An upgrade to MS Office 2000 is now due as:

• The product is out of Microsoft extended support. • There are issues when reading documents received from outside of the Council using later versions, despite deployment of a reader. • A number of users are starting to struggle with limitations in Excel 2000. This includes restrictions on the number of rows and more complex functions for data analysis not being available. Government departments that we correspond with use some of these features. • Some business system vendors no longer support Office 2000 with their products, and this raises risk of compatibility issues for production systems.

Results of Alternative Options Project

The Council’s strategy is to consider open source alternatives wherever practicable. The Council already uses an Open Source Content Management System (CMS) and operating systems and is migrating from Novell Netware to OES, which is based on SUSE Linux. With this in mind a project was launched to ascertain vendor support for open source office systems and to test office systems against all the Council’s main business Page 4 of 8 systems. To gain a direct comparison, the latest versions of Open Office and Microsoft Office were compared.

The results of this investigation and testing were that:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Office System Upgrade projectReport 146 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 10 attended
MB
Councillor Max BoyceChair, present
CR
Councillor Colin RosenstielVice-Chair, present
SA
Councillor Salah Al BanderCommittee Member, apologies, sent representative
MA
Councillor Mark AshtonCommittee Member, present
JB
Councillor Jeremy Benstead Labour Spokes for Customer Services and ResourcesCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
IN
Councillor Ian Nimmo-SmithCommittee Member, present
AP
Councillor Adam Pogonowski Green SpokesCommittee Member, present
PS
Councillor Paul SaundersReserve, present as substitute

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies