Resolved
RESOLVED (Unanimously) I. To approve the list of schemes in section 5.0 of the Officer’s report for further investigation into their feasibility and estimated cost.
West Central Area Committee approved this item on Thursday 1 March 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED (Unanimously) I. To approve the list of schemes in section 5.0 of the Officer’s report for further investigation into their feasibility and estimated cost.
Cambridge City Council Item
Report by: Head of Streets and Open Spaces
To: West/Central Area Committee 1 March 2012
Wards: Castle, Newnham and Market
Environmental Improvements Programme
1. DECISIONS TO BE MADE: -
NEW SUGGESTED SCHEMES FOR THE 2012/13 PROGRAMME
Recommendation: To approve the list of schemes in section 5.0 for further investigation into their feasibility and estimated cost.
2. BUDGET (See Appendix 1) 3.0 APPROVED SCHEMES – PROGRESS
3.1Manor St/King St Cycle Parking – promoted by Cllr Rosenstiel The legal agreement has been signed, the cycle bars have been erected and improvements to the surrounding surfacing will be completed shortly.
3.2Fitzroy/Burleigh Street Refurbishment – promoted by Cllr Bick The construction work to complete this scheme is due to start shortly. This involves the planting of two new trees on Burleigh Street, the replacement of two existing trees on Fitzroy Street and maintenance resurfacing works carried out by the County Council.
3.3Prospect Row – promoted by Cllr Rosenstiel The Contractor has applied for a road closure in order to construct the speed cushions proposed for this scheme. Under the traffic management act this requires a 3 month advanced notice. The work is programmed to commence in April.
3.4Grantchester Road Traffic Calming – promoted by Cllr Reid A consultation with local residents is planned for this scheme, including a public meeting to discuss the proposals and issues on Grantchester Road.
3.5Central Area Mobility Crossings - promoted by Cllr Bick The process of identifying the priority crossings in the city centre is now complete. The chosen crossings will be finalised shortly and constructed by the end of April.
3.6North Terrace Gates - requested by Friends of Midsummer Common. This work to provide wider pedestrian gates in order to improve accessibility is now complete.
3.7Gough Way Path Bridge – promoted by Cllr Reid Consultation on the proposed footbridge replacement will be carried out shortly. The new bridge is planned to be installed in the spring. 3.8 Canterbury Street - promoted by Cllr Kightley A consultation on the traffic calming options for this area is currently under way. The results will then be presented to the next West/Central Area Committee in April.
3.9Huntingdon Road 30mph extension - promoted by Cllr Kightley This scheme is currently being developed with the County Council. A request has also been made for the limit to be extended to include the access to Girton College. This is currently being discussed with key stakeholders before any formal statutory process to introduce the traffic regulation order is carried out. 5.0 NEW SUGGESTED SCHEMES FOR 2012/13
The table below lists the new schemes that have been submitted by Ward Councillors and residents for consideration as part of the 2012/13 Environmental Improvement Programme.
No Proposed Scheme Ward Promoter Estimated Considerations Cost 1. Lammas Land Access Road Newnham Cllr Cantrill £1,000 Funding from County Minor Works Budget applied – review of exit at junction for. Minimum 10% required from EIP Budget. with Barton Road. Potential to relocate stop line further into access road, cut back overhanging vegetation and review signal operation.
2. ‘No Right Turn’ Signage for Newnham Ward Councillors £1,000 Funding from County Minor Works Budget applied Newnham Croft for. Minimum 10% required from EIP Budget.
3. Resurfacing of the footpath Newnham Cllr Reid TBC Funding from County Minor Works Budget applied from South Green Road as for. Minimum 10% required from EIP Budget. far as the Grantchester This is a County Council responsibility and will be Meadows footpath starting raised with their maintenance division in the first at the Pembroke Playing instance. Field.
4. Path improvements to Newnham Cllr Reid - This is already proposed as part of the Upper Cam Paradise Nature Reserve Biodiversity Project.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Environmental Improvement ProgrammeReport | 286 KB | DownloadRead as text |
Follow West Central Area Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Sep 2023 | Environmental Report - WCACAgreed that the needle pick up across the wards seemed high but compared to the data over 24 months the number of nee... | Agreed | Open |
| 15 Jun 2023 | Policing and Safer Neighbourhoods WCACAgreed to speak with Inspector McNeill on how to improve the message of successes and if a briefing note could be cir... | Agreed | Open |
| 16 Mar 2023 | Open ForumAgreed with the points raised as experienced the same issues. ii. Had recently spoken with the traffic warden who wer... | Agreed | Open |
| 5 Mar 2020 | WCAC Area Committee Grants 2020-21Resolved- To approve the recommendations in paragraph 2 of the officer report. | Approved | Open |
| 5 Mar 2020 | Environmental Improvement ProgrammeResolved- To approve the recommendations in paragraph 2 of the officer report. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.