Installation of solar thermal technology on City Council properties
ApprovedScrutiny1 paper
Strategy and Resources Scrutiny Committee approved this item on Monday 19 March 2012. Below is the council's own wording, with the papers it was decided on.
The supply and installation of solar thermal panels on selected Council properties to secure a guaranteed income through energy bill savings and heat tariff as part of the Government’s national Renewable Heat Incentive (RHI). Decision of the Executive Councillor: The Deputy Leader resolved to: Financial recommendations: i. Approve commencement of the Solar Thermal Project, included in the Council’s Capital Plan - C2966, Installation of solar thermal panels and/or energy efficiency measures on non-housing Council properties (General Fund). The total capital cost of the project is £140,000. The revenue savings from the project are estimated at £15,000 per annum (savings proposal S2967) and these have been included in the revenue budget from 2013/14 onwards. Procurement recommendations: ii. Approve the procurement and installation of solar thermal panels and other necessary equipment under the Planned Maintenance Framework. Subject to: The permission of the Executive Councillor and Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract value by more than 15%. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: N/A Scrutiny Considerations N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Agenda Item Page 1 of 12
Project Appraisal and Scrutiny Committee Recommendation
Installation of solar thermal technology Project Name on City Council properties Committee Strategy & Resources Portfolio Strategy Committee Date 20 March 2012 Executive Councillor The Leader, Councilor Sian Reid Lead Officer Clare Palferman and Ian Ross
Recommendation/s Financial recommendations – • The Executive Councillor is asked to approve commencement of the Solar Thermal Project, included in the Council’s Capital Plan - C2966, Installation of solar thermal panels and/or energy efficiency measures on non-housing Council properties (General Fund). The total capital cost of the project is £140,000. • The revenue savings from the project are estimated at £15,000 per annum (savings proposal S2967) and these have been included in the revenue budget from 2013/14 onwards.
Procurement recommendations: • The Executive Councillor is asked to approve the procurement and installation of solar thermal panels and other necessary equipment under the Planned Maintenance Framework. • If the quotation or tender sum exceeds the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Finance will be sought prior to proceeding. Page 2 of 12 1 Summary
1.1The project
The supply and installation of solar thermal panels on selected Council properties to secure a guaranteed income through energy bill savings and heat tariff as part of the Government’s national Renewable Heat Incentive (RHI).
Target Start date 25 May 2012 Target completion date 30 September 2012
1.2The Cost Total Capital Cost £140,000
Capital Cost Funded from:
Funding: Amount: Details:
Reserves £140,000 C2966
HRA Reserves £
Section 106 £
Other £
Revenue Cost
Year 1 £0
Ongoing £(15,000)
1.3The Procurement The supply and installation of solar thermal panels and other equipment essential for the project can be procured under the Council’s Planned Maintenance Framework. Page 3 of 12 2 Capital Project Appraisal & Procurement Report
2.1What is the project?
In March 2011, the UK Government announced details of their Renewable Heat Incentive (RHI). RHI is designed to provide financial support that encourages individuals, communities and organisations to switch from using fossil fuel for heating, to renewables such as wood fuel.
Under the RHI, several different renewable heat technologies are eligible to claim a tariff. A tariff is a set rate paid for every kW of heat generated through renewable heat technologies. An assessment of their deployment potential in City Council owned buildings was carried out and the technology with the highest deployment potential is solar thermal.
Solar thermal technologies gather heat from the sun into collectors which transfer heat energy to a working liquid. This liquid can then be used directly to provide hot water within a building, or an exchanger can transfer the heat from the working liquid to the water.
In order to provide an estimate of the potential for renewable energy generation via solar thermal, an assessment of heat demand and the availability of roof area were required. The Climate Change Officer, together with the Home Energy Officer, carried out a desk based assessment of the viability of installing 200kWth 1 solar thermal systems on 51 Council properties and identified 6 as potentially viable: 1 communal housing property and 5 non-housing properties. Discussions with relevant officers concluded that officers do not have the capacity to install on all 6 sites, so the best sites were chosen and these informed the budget bid.
A budget bid of £200,000 (£60K HRA and £140K General Fund) has been made to purchase and install solar thermal on the following properties (subject to site assessment): • Pools & Leisure - Abbey Pool 1 KWth stands for Kilowatt Thermal and 200kWth is the maximum size of system under the RHI. Page 4 of 12 • Pools & Leisure - Kings Hedges Learner • Pool Pools & Leisure - Parkside • Sheltered Housing - Ditchburn Place
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.