Strategy and Resources Scrutiny Committee approved this item on Monday 19 March 2012. Below is the council's own wording, with the papers it was decided on.
Purchase and Installation of an additional interview room and desk in the reception area of the Customer Service Centre. Decision of the Executive Councillor: The Executive Councillor for Customer Services and Resources resolved to: Financial recommendations: i. Approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (SC537). The total cost of the project is £25,000, funded from Reserves. There are no revenue costs arising from the project. Procurement recommendations: ii. Approve the invitation and evaluation of quotations and award of contract of an additional interview room and desk in the reception area of the Customer Service Centre. Subject to: The permission of the Executive Councillor and the Director of Resources being sought prior to proceeding if the quotation sum exceeds the estimated contract value by more than 15%. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: N/A Scrutiny Considerations The committee received a report from the Head of Customer Services. In response to member’s questions the Head of Customer Services confirmed the following: i. The works would allow greater flexibility for the Customer Service Centre to provide Post Office related services. Discussions were ongoing with local authorities already provided these services and visits to Chelmsford and Reading were being planned. The Scrutiny Committee considered and approved the recommendations by 8votes to 0 (unanimously). The Executive for Customer Services and Resources approved the recommendations.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Page 1 of 11
Cambridge City Council Item
To: Executive Councillor for Customer Services and Resources Report by: Jonathan James / Chris Bolton Relevant scrutiny Strategy and Resource Scrutiny 19th committee: March 2012 Wards affected: All
Project Appraisal and Scrutiny Committee Recommendation Project Name: Customer Service Centre Accommodation works
Recommendation/s Financial recommendations –
• The Executive Councillor is asked to approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (SC537). • The total cost of the project is £25,000, funded from Reserves.
• There are no revenue costs arising from the project.
Procurement recommendations:
• The Executive Councillor is asked to approve the invitation and evaluation of quotations and award of contract of an additional interview room and desk in the reception area of the Customer Service Centre.
• If the quotation sum exceeds the estimated contract value by more than 15% the permission of the Executive Councillor and Director of Resources will be sought prior to proceeding.
N:\Committee\E-Reports\S&R\March 2012\Project Appraisal -Building Works FINAL.doc 1 Page 2 of 11
1 Summary Purchase and Installation of an additional interview room and desk in the reception area of the customer service centre. Full background details and a more detailed explanation are provided within section 2.1.
1.1The project
Target Dates: Start of procurement April 2012 Award of Contract July 2012 Start of project delivery August 2012 Completion of project December 2012
1.2The Cost Total Project Cost £ 25,000
Cost Funded from:
Funding: Amount: Details:
Reserves £ 25,000
Repairs & Renewals £ Developer £ Contributions Other £
Ongoing Revenue Cost N/A as cleaning, heating etc Year 1 already accounted for in CSC budget provision. Ongoing
N:\Committee\E-Reports\S&R\March 2012\Project Appraisal -Building Works FINAL.doc 2 Page 3 of 11
1.3The Procurement
The Council will procure an additional interview room and desk in the reception area of the Customer Service Centre allowing residents to access Cambridge City Council services and council information.
The procurement approach will be to invite three suppliers to submit quotations based on a specification/requirements document.
2 Project Appraisal & Procurement Report
2.1The Project
The procurement of an additional interview room and desk in the reception area of the Customer Service Centre has been identified as a key enabler to allowing residents to access Cambridge City Council services and council information.
This has been borne out by the successful implementation of the Customer Service Centre in 2008 and increase in visitors’ to the centre each year.
Since 2008, the volume of face-to-face visitors to the Customer Service Centre has increased as shown in table 1 below and highlights the need for investment to increase the centres’ capacity for dealing with visitors.
Table 1. Customer Service Centre Visits, 2008 -2012
Year Visitors 2008-9 33,000 2009-10 42,000 2010-11 44,000 2011-12 36,000 to Jan ‘12
The additional interview room and desk will allow a greater capacity in room and desk space, reduce queuing times and speeding up transaction times.
N:\Committee\E-Reports\S&R\March 2012\Project Appraisal -Building Works FINAL.doc 3 Page 4 of 11
2.2Aims & objectives
“The project contributes to the Council’s vision for:
• A city which is diverse and tolerant, values activities which bring people together and where everyone feels they have a stake in the community
• A city whose citizens feel they can influence public decision making and are equally keen to pursue individual and community initiatives
The additional interview room and desk space will increase the ability of Customer Service Advisors to deal with customer enquiries, reduce queuing times and speed up transaction times.
2.3What services will be available?
The additional space will be used by advisors for all of the services that are delivered at the Centre. These are:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.