2011/12 Revenue and Capital Outturn, Carry Forwards and Significant Variances - Overview
AgreedScrutiny1 paper
Strategy and Resources Scrutiny Committee agreed this item on Monday 9 July 2012. Below is the council's own wording, with the papers it was decided on.
The report presented a summary of the 2011/12 outturn position (actual income and expenditure) for all portfolios, compared to the final budget for the year. The position for revenue and capital was reported and variances from budgets were highlighted. Decision of the Leader: The Leader resolved to: Revenue: i. Agree the final carry forward requests, totaling £632,970, as detailed in Appendix C of the officer’s report, be recommended to Council for approval, subject to the final outturn position. Capital: ii. Seek approval from Council to carry forward (net) capital resources to fund re-phased capital spending of £8,872,000 as shown in Appendix D of the officer’s report - Overview. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: As set out in the officer’s report Scrutiny Considerations The committee received a report from the Head of Accounting Services. The Scrutiny Committee considered and approved the recommendations by 4 votes to 0. The Leader approved the recommendations.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Executive summary
1.1This report presents a summary of the 2011/12 outturn position (actual income and expenditure) for all portfolios, compared to the final budget for the year. The position for revenue and capital is reported and variances from budgets are highlighted. Explanations have been reported to individual Executive Councillors / Scrutiny Committees and are reproduced here.
1.2It should be noted that this report reflects the reporting structure in place prior to the recent changes in Executive reporting responsibilities.
1.3Requests to carry forward funding arising from certain budget underspends into 2012/13 are identified.
1.4The outturn position for Housing Revenue Account (HRA) has been reported to Housing Management Board and the Executive Councillor for Housing on 19 June 2012.
Revenue Outturn
1.5The 2011/12 final revenue budget for all portfolios is £20,728,840. The final outturn for the year is now £18,588,884 giving an overall under-spend of £2,139,956. Of this total under-spend requests for carrying forward budgets into the next financial year are being sought for £632,970, as detailed in Appendix C. Capital Outturn
1.6The latest approved capital budget for all portfolios is £27,344,000. Actual expenditure on capital schemes and programmes during 2011/12 is £18,092,000 giving an overall under-spend of £9,252,000. Of this net underspend £8,872,000 is due to net slippage and Council approval is sought to rephase the required capital resources from 2011/12 into 2012/13.
Recommendations
The Executive Councillor is recommended:
Revenue:
a) To agree which of the final carry forward requests, totalling £632,970, as detailed in Appendix C, are to be recommended to Council for approval, subject to the final outturn position.
Capital:
b) To seek approval from Council to carry forward (net) capital resources to fund re-phased capital spending of £8,872,000 as shown in Appendix D - Overview.
Background
Revenue Outturn
3.1The revenue budget for 2011/12, initially approved by Council on 17 February 2011, was considered in the January 2012 Committee cycle and revised as appropriate. The final outturn position for all portfolios, compared to final revenue budget, is presented in detail in Appendix A.
3.2Explanations for the main variances from the final budget for 2011/12 have been reported to appropriate Executive Councillors / Scrutiny Committees and are reproduced as Appendix B.
3.3Appendix C sets out the list of items, for all portfolios, for which approval is sought to carry forward unspent budget from 2011/12 to the next financial year, 2012/13. 3.4 A summary of the final revenue outturn position for all portfolios is shown below:
2011/12 General Fund £ Revenue Summary Original Budget 18,672,260 Adjustments 2,056,580
Final Budget 20,728,840 Outturn 18,588,884
Net Variation / underspend for (2,139,956) the year Carry Forward Requests: 632,970
Net Variance and reduced use of (1,506,986) General Fund Reserves
Capital Outturn
3.5All capital schemes were reviewed in detail in January 2012 and the Capital Plan amended to account for rephasing and anticipated over/underspends on individual schemes.
3.6Appendix D - Overview summarises the final outturn position against 2011/12 final capital budgets. Explanations for the main variances from final budgets for 2011/12 have been reported to appropriate Executive Councillors / Scrutiny Committees and are reproduced as Appendices D (General Fund Detail) and Appendix E (Housing). The net under-spend of £9,252,000 is mainly due to slippage.
3.7The Capital Plan will be updated as necessary to reflect changes in the phasing of capital projects.
4. Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.