Large Hall – Leaded Window Refurbishment – Phase 1
ApprovedScrutiny1 paper
Strategy and Resources Scrutiny Committee approved this item on Monday 9 July 2012. Below is the council's own wording, with the papers it was decided on.
Refurbishment of the leaded windows in the Large Hall. Decision of the Executive Councillor: Financial recommendations The Executive Councillor resolved to: i. Approve the commencement of the scheme, which was already included in the Council’s Capital & Revenue Project Plan (PR023 Admin Buildings Asset Replacement Programme). ii. Agree that the total cost of the project was £87,500 and that it would be funded from repairs and renewals fund contributions. iii. Agreed t he ongoing revenue costs of the project was £1,000 and that it be funded from existing budget provision. Procurement recommendations The Executive Councillor resolved to: i. Approve the carrying out and completion of the procurement of the refurbishment of the leaded windows to one side of the Large Hall within The Guildhall. ii. Subject to: - the permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. - the permission of the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reasons for the Decision : As set out in the officer’s report Any alternative options considered and rejected: As set out in the officer’s report Scrutiny Considerations The committee received a report from the Building Surveyor. In response to member’s questions the Building Surveyor confirmed the following: i. Over previous years attempts had been made to refurbish the windows. However they had now deteriorated and would need replacing. ii. A full survey of all Council assets would be undertaken with regular maintenance programmes established. The Scrutiny Committee considered and approved the recommendations by 4 votes to 0. The Executive Councillor approved the recommendations.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Strategy and Resources Scrutiny Committee
Page 1 of 7
Cambridge City Council Item
To: Executive Councillor for Customer Services and Resources: Councillor Julie Smith Report by: Andy Muggeridge Relevant scrutiny STRATEGY & RESOURCES SCRUTINY 9 July committee: COMMITTEE 2012 Wards affected: All
Project Appraisal and Scrutiny Committee Recommendation Project Name: Large Hall – Leaded Window Refurbishment – Phase 1
Recommendation/s Financial recommendations – • The Executive Councillor is asked to approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR023 Admin Buildings Asset Replacement Programme). • The total cost of the project is £87,500 funded from repairs and renewals fund contributions. • The ongoing revenue costs of the project are £1,000, funded from existing budget provision. Procurement recommendations: • The Executive Councillor is asked to approve the carrying out and completion of the procurement of the refurbishment of the leaded windows to one side of the Large Hall within The Guildhall. • Subject to: - The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract.
- The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Page 2 of 7
1 Summary Refurbishment of five large stained glass windows to one side of the Large Hall located within the curtilage of The Guildhall.
1.1The project
Target Dates: Start of procurement July 2012 Award of Contract August 2012 Start of project delivery August 2012 Completion of project January 2013
1.2The Cost Total Project Cost £ 87,500
Cost Funded from:
Funding: Amount: Details:
Reserves £ 27717 Admin Buildings Repairs & Renewals £87,500 Repairs and Renewals Fund Developer £ Contributions Other £
Ongoing Revenue Cost Maintenance contribution Year 1 £1,000 towards redecoration. Maintenance contribution Ongoing £1,000 pa towards redecoration.
The ongoing revenue costs of the project will be funded from existing budget provision. Page 3 of 7
1.3The Procurement The procurement of the project will be in accordance with the Council’s Procurement strategy with three Contractors invited to tender for the works.
The estimated costs are £85,000 for the refurbishment work, consisting of £75,000 for the work to the windows, £10,000 for scaffolding and £2,500 in the form of consultancy expertise to ensure the project is correctly specified.
2 Project Appraisal & Procurement Report
2.1The Project The project is required to refurbish the leaded windows to one side of the Large Hall.
It appears that very little maintenance has been carried out to the windows for a significant number of years. This has led to the deterioration of the timber window frames. Access to carry out the work to this side of the Large Hall is very restrictive and therefore also a contributing factor.
It has become apparent that work is urgently required to prevent the lead lights from actually falling out.
Work will be carried out with guidance from the Senior Conservation & Design Officer to ensure that the work is carried out within the guidelines of a Grade 2 listed building.
The 2nd phase of the refurbishment will be planned for the near future together with the long term maintenance of The Guildhall. There has been work to these windows in the past, thus the refurbishment is not as urgent as the Phase 1 works.
2.2Aims & objectives The Refurbishment of the windows to the Large Hall meets with the Council’s vision for: ‘A city which draws inspiration from its iconic historic centre and achieves a sense of place in all of its parts with generous urban open spaces and well-designed buildings.’
2.3Major issues for stakeholders & other departments The refurbishment to the windows in The Guildhall would increase the opportunity for hiring out the rooms and increasing the potential income for the City Council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Jeremy Benstead Labour Spokes for Customer Services and ResourcesCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
PT
Councillor Philip TuckerCommittee Member, present
AP
Councillor Adam PogonowskiCommittee Member, present
Hear about the next one first
Follow Strategy and Resources Scrutiny Committee at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.