Resolved (Unanimously) to i. Allocate funding of £40,800 to the following projects. · Trumpington War Memorial - £8500 · Hobson Brook Railings - £9000 · South Area Mobility Crossings - £6000 · Cherry Hinton War Memorial - £5000 · Cherry Hanging Baskets - £4300 · Noticeboard on Cherry Hinton Recreation Field - £4500 · Bollards on forecourt at junction of Mill End Road and Cherry Hinton High Street - £3500 ii. Approve the schemes listed in i. for implementation, subject to positive consultation and final approval by local Ward Councillors. iii. Note the progress of existing schemes listed in appendix C of the committee report.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
• This report requests that the Committee determine which of the proposed EIP schemes are allocated funding as part of the 2012/13 Environmental Improvement Programme, from those listed in Appendix A of this report.
Recommendations
The South Area Committee is recommended:
2.1To allocate funding of up to £41,800 to the list of proposed projects in Appendix A of this report. 2.2 To approve those projects for implementation, subject to positive consultation and final approval by local Ward Councillors. 2.3 To note the progress of existing schemes listed in Appendix C of this report.
Background
3.1Initial feasibility work has been carried out on all of the schemes that have been suggested for the 2012/13 Environmental Improvement Programme (EIP).
3.2The table in Appendix A lists all of the schemes that could be feasibly delivered as part of this year’s EIP Programme, should they be allocated funding by South Area Committee.
3.3Any scheme that involved the public highway was submitted to Cambridgeshire County Council, as Highway Authority, to apply for funding from the County Council’s Minor Highway Works Budget.
Report Page No: 1 3.4 The South Area Committee has an annual budget of £41,800 to allocate to schemes from its Environmental Improvement Programme Budget.
3.5Further details of some of the proposed schemes can be found in Appendix B of this report.
3.6Some of the schemes that have been suggested for this year’s programme have not been included in Appendix A, as they either require further assessment of their feasibility, are not deliverable or will be implemented by others. Table 1.0 below provides a summary of these schemes.
Scheme Position
Cherry Hinton The estimated cost of adding filters to this signalised Rd/Fulbrooke Rd crossing is in the region of £50,000. The County Council signalised junction have indicated that this issue should be looked at as part of a wider assessment of the impact of development on this area, with a view to potential funding being sourced from the South Area Wide Corridor Transport Plan. Zebra Crossing on Development in the area and strategic nature of this route Fendon Rd close to suggest potential for South Area Transport corridor funding. Queen Edith’s Way roundabout
Pedestrian Guardrail at Due to the narrowness of the footway at this point, junction of Fen pedestrian guardrail is not feasible. Causeway and Trumpington Rd
Table 1.0; Schemes in development, to be delivered by others, or not feasible.
Background papers
None
Report Page No: 2 5.0 Appendices
APPENDIX A Summary of Feasible EIP Schemes for 2012/13.
APPENDIX B Details of Proposed Schemes
APPENDIX C Progress of Existing Schemes APPENDIX D EIP Eligibility Criteria
7. Inspection of papers
To inspect the background papers or if you have a query on the report please contact:
Election of Chair and Vice Chair - SACResolved (by 4 votes to 4 and flip of a coin by Committee Manager) that Councillor McPherson be Chair for the ensuing...
Election of Chair and Vice Chair - SACResolved (by 6 votes to 5) that Councillor McGerty be Chair for the ensuing year. Councillor McGerty proposed, and Co...
Election of Chair and Vice Chair - SACResolved (by 4 votes to 4 and toss of a coin) that Councillor McPherson be Chair for the ensuing year. County Council...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.