Community Services Scrutiny Committee approved this item on Thursday 11 October 2012. Below is the council's own wording, with the papers it was decided on.
To consider a project appraisal regarding the Corn Exchange PA system. Decision of Executive Councillor for Arts, Sport and Public Places The Executive Councillor resolved to; Financial recommendations i. Approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (SC522). ii. Note that the total cost of the project is £160,000 funded from Corn Exchange Equipment R&R budget and Capital Reserves. iii. Note that there are no ongoing revenue implications arising from the project. Procurement recommendations iv. Approve the carrying out and completion of the procurement of sound equipment to the value of £160,000. Reason for the As per the officer report Any alternative options considered and rejected: Not Applicable Scrutiny Considerations: The committee received a report from the Head of Arts and Recreation regarding the PA system for the Corn Exchange. The decision had not been selected for pre-scrutiny, but the clarification was requested on the reason for the proposed decision. The Head of Arts and Recreation and the Director of Customer and Community Services outlined for the reasons for the proposed decision. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Executive Councillor for Arts, Sport and Public To: Places Report by: Steve Bagnall – Cultural Facilities Manager Scrutiny committee: COMMUNITY SERVICES Wards affected: None
Project Appraisal and Scrutiny Committee Recommendation
Project Name: Corn Exchange PA system
Recommendation/s Financial recommendations – • The Executive Councillor is asked to approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (SC522).
• The total cost of the project is £160,000 funded from Corn Exchange Equipment R&R budget and Capital Reserves. • There are no ongoing revenue implications arising from the project.
Procurement recommendations: • The Executive Councillor is asked to approve the carrying out and completion of the procurement of sound equipment to the value of £160,000. Page 2 of 8
• Subject to: - The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%.
1 Summary 1.1 The project
Purchase and Install a replacement sound system for the Corn Exchange at an estimated cost of £160,000 Target Dates: Start of procurement October 2012 Award of Contract December 2012 Start of project delivery January 2013 Completion of project February 2013
The procurement process will be run using the expertise of the Corn Exchange technical team. The purchase will be made following a competitive tender exercise.
2 Project Appraisal & Procurement Report
2.1Project Background The Corn Exchange sound system is based on an installation completed 25 years ago when the building was refurbished. It has undergone piecemeal adaptations and enhancements since then most recently in 2003. The system and infrastructure is now out of date and at the end of it’s useful life, and as a consequence the Corn Exchange has been receiving complaints about sound quality at events and has to supplement the existing equipment with hired in kit on all spoken word and music events where the in house system is required. In order to continue to attract quality artists and performers to the Corn Exchange and to ensure continued excellent ticket sales it is essential to keep pace with industry standards. A new Sound System will ensure the venue meets the needs of promoters and enhances the experience and quality of service to customers and artists. The estimated cost of this project has been revised down from the original capital application. This is a result of prioritising business critical elements.
2.2Aims & objectives The aims of this project are - 1. To provide visitors and performers with a quality sound experience that is appropriate to the status of the venue. Page 4 of 8
2. To provide promoters with increased flexibility which will encourage use of the Corn Exchange for events that would otherwise bypass the venue such as pre tour and pre festival gigs. 3. To eliminate the cost of hiring in additional equipment for events. 4. To provide the ability to attract one off and bespoke events that aren’t touring with their own sound system and gives us the flexibility to more readily accommodate a broader range of musical events for example world music, jazz and folk.
2.3Major issues for stakeholders & other departments None
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.