Core Switch Upgrade - Project Appraisal

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 15 October 2012. Below is the council's own wording, with the papers it was decided on.

Item12/77/SR

Resolved

The project was part of ICT’s planned replacement strategy and was to be funded from Repairs and Renewals. The core network switch within the Mandela House computer room provides connectivity for all ICT services (e.g. access to business systems, network and internet) and end users. This switch had now past it’s end of service date and required replacing. Decision of Executive Councillor for Customer Services and Resources : Financial recommendations: The Executive Councillor approved the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR020). i. The total cost of the project is £84,000, funded from IT Infrastructure Replacement Repairs &Renewals fund. ii. There were no ongoing revenue implications arising from the project. Procurement recommendations: The Executive Councillor approved the carrying out and completion of the procurement and implementation of a core network switch to the value of £84,000 Subject to: iii. The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. iv. The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: Not applicable. Scrutiny Considerations: The Committee received a report from the ICT Client Manager regarding the Core Switch Upgrade Project Appraisal. Members asked for clarification of an undefined spend of £8,000 noted in the report. The information would be supplied outside the meeting. The Committee resolved by 4 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Page 3 of 9

Cambridge City Council

To: Executive Councillor for Strategy and Resources Report by: Tony Allen Scrutiny committee: STRATEGY & RESOURCES 15/10/2012 Wards affected: All

Project Appraisal and Scrutiny Committee Recommendation

Project Name: Core Switch Upgrade

Recommendation/s Financial recommendations –

• The Executive Councillor is asked to approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR020). • The total cost of the project is £84,000, funded from IT Infrastructure Replacement Repairs &Renewals fund. • There are no ongoing revenue implications arising from the project. Procurement recommendations: • The Executive Councillor is asked to approve the carrying out and completion of the procurement and implementation of a core network switch to the value of £84,000 • Subject to: - The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. - The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Page 4 of 9

1 Summary 1.1 The project

Replacement of the core network switch within Mandela House computer room

Target Dates: October 2012 Start of procurement N/a Award of Contract N/a Start of project delivery October 2012 Completion of project March 2013

1.2Anticipated Cost Total Project Cost £ 84,000

Cost Funded from:

Funding: Amount: Details:

Reserves £ IT Infrastructure Repairs & Renewals £84,000 Replacement Repairs &Renewals fund. Developer £ Contributions Other £

Ongoing Revenue Cost

Year 1 £0

Ongoing £0 Page 5 of 9

1.3Procurement process Switches to be procured by Serco under the Council’s ICT FM contract. Serco will obtain at least 3 competitive quotes.

2 Project Appraisal & Procurement Report

2.1Project Background This project is part of ICT’s planned replacement strategy and is funded from Repairs and Renewals. The core network switch within the Mandela House computer room provides connectivity for all ICT services (e.g. access to business systems, network and internet) and end users. These switches now require replacement as: • They have now passed end of service date, so Cisco no longer provide support or bug fixes • Extra connectivity and switch features are required to support the Council’s current and future ICT projects • Additional resilience can be provided, for example by removing some single points of failure • Will provide additional switching resources for the Council’s desktop replacement project and flexible working projects.

2.2Aims & objectives

• Procure new core networking switches • Deploy new networking switch within the Computer Room • Retire obsolete network switches. • Verify that new connectivity and speeds are available • Reuse existing equipment where applicable The project will meet the Council’s Vision for: “A city whose citizens feel they can influence public decision making and are equally keen to pursue individual and community initiatives” by providing continuation of the Council’s ICT service in a cost effective and resilient manner. Page 6 of 9

2.3Major issues for stakeholders & other departments • There are no major issues associated with this project • During deployment there will be network outages, however these will be planned around confined to outside of core hours and programmed to limit impact on the Corn Exchange and TIC. Consultation undertaken:

• Public – Not required • Members – Portfolio Holder

2.4Summarise key risks associated with the project • If we do not undertake project we are working with network switching that is now out of date, creating potential network vulnerabilities. • If we do not undertake project we are working with network switching that will not adequately support both planned and future projects. 2.5 Financial implications a. Appraisal prepared on the following price base: 2012/13 b. Specific grant funding conditions are: • c. Other comments

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Core Switch Upgrade: Project AppraisalReport 104 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SB
Councillor Sarah BrownChair, present
CR
Councillor Colin RosenstielVice-Chair, present
SB
Councillor Sue BirtlesCommittee Member, present
MB
Councillor Max BoyceCommittee Member, present
MA
Councillor Mark AshtonCommittee Member, present
JB
Councillor Jeremy Benstead Labour Spokes for Customer Services and ResourcesCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
PT
Councillor Philip TuckerCommittee Member, apologies, sent representative
AP
Councillor Adam PogonowskiReserve
AB
Councillor Andy BlackhurstCommittee Member, present

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies