Options for Site K1, Orchard Park

Approved Scrutiny 2 papers

Strategy and Resources Scrutiny Committee approved this item on Monday 15 October 2012. Below is the council's own wording, with the papers it was decided on.

Item12/79/SR

Resolved

Site K1 was approved for disposal in November 2004. The Strategy & Resources Scrutiny Committee on 29 th March 2010 approved investigation for a community co-housing scheme. This is the provision of houses in partnership with an established developer and a group of ‘self-builders’ with outright ownership of the houses and collective ownership of the communal areas/public realm. The information available from the initial marketing of a co-housing scheme is considered inconclusive as to the viability of such a scheme. A decision is needed on whether to proceed with the community co-housing approach or re-market the site on the open market. Decision of Executive Councillor for Customer Services and Resources : Approved that the Council dispose of Site K1 by one of the following options: i. Continue with the community co-housing approach if sufficient interest allowing for a 6-month marketing period and that the risks in paragraph 1.3 of Appendix A of the Officer’s report can be mitigated, failing which the site will be disposed of as in ii below. ii. Re-market the site on the open market to achieve a quality scheme reflecting the Council’s desire for good sustainability, good design, high values and integration with the wider Orchard Park Community. Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: Not applicable. Scrutiny Considerations: The Committee received a report from the Asset Development Project Manager regarding the Options for site K1 Orchard Park. Adam Broadway, the Managing Director of Instinctively Green, was also present to answer questions. Members discussed deliverability of the scheme. It was suggested that the initial low take up was not uncommon and that current expressions of interest would generate further interest. It was believed that the project was both innovative and deliverable. Members expressed the hope that the scheme would generate high quality designs. The Committee resolved unanimously to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Executive summary

1.1Site K1 was approved for disposal in November 2004. The Council entered into a development agreement with neighbouring landowners as part of the wider Arbury Camp development. It was allocated for 37 market houses with affordable housing provided on adjoining parts of the site.

1.2A sale was agreed at £4.3m in 2007 but with the market decline, the prospective purchaser withdrew. Further marketing generated very low offers and it was decided to investigate other disposal options to achieve a comparable value and more timely development.

1.3The Strategy & Resources Scrutiny Committee on 29th March 2010 approved investigation for a community co-housing scheme. This is the provision of houses in partnership with an established developer and a group of ‘self-builders’ with outright ownership of the houses and collective ownership of the communal areas/public realm.

1.4Cambridge Architectural Research Limited was appointed to investigate the demand and interest into a community co- housing initiative on the site. After extensive marketing, 7 households have expressed strong interest in the scheme. A further 13 are interested but have unresolved questions. Altogether, 62 people expressed interest.

1.5The information available from the initial marketing of a co- housing scheme is considered inconclusive as to the viability of such a scheme. A decision is needed on whether to proceed with the community co-housing approach or re-market the site on the open market.

Recommendations

The Executive Councillor is recommended:

To approve that the Council dispose of Site K1 by one of the following options:

2.1Continue with the community co-housing approach if sufficient interest allowing for a 6-month marketing period and that the risks in paragraph 1.3 of Appendix A can be mitigated, failing which the site will be disposed of as in 2.2 below

OR

2.2Re-market the site on the open market to achieve a quality scheme reflecting the Council’s desire for good sustainability, good design, high values and integration with the wider Orchard Park Community.

Background

3.1Site K1 is 0.97 hectares (2.4 acres), on the edge of Orchard Park, as shown edged in Appendix B and is within South Cambridgeshire. The Council’s land was brought forward for development through a collaboration agreement with adjoining landowners. This enabled a collective approach to obtaining planning consent, undertaking infrastructure works and servicing the land parcels.

3.2The Council’s land was spilt into 4 sites for housing: K1 for market housing and J1, J2 and K2 for affordable housing (now sold and the developments completed on site). K1 was allocated 37 market housing units in the master-plan. The site had outline planning consent for these units subject to submitting a “reserved matters” application within 3 years.

3.3A sale was agreed at £4.3m in 2007 but this fell through and no reserved matters application was made. The planning consent therefore lapsed in June 2008. Further offers from developers and from Registered Social Landlords were received but these were significantly below the previous sale price.

3.4Consideration was given to whether or not more innovative approaches could be found to bring the site forward for sale and/or development at the earliest opportunity. Local residents were keen that the site be developed as soon as possible rather than left as a vacant building plot.

3.5Options were considered at the Strategy & Resources Scrutiny Committee in March 2010. A decision was made to investigate a community co-housing scheme on the site with a fall back position that if insufficient interest, the Council could revert to the original market disposal approach.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Background Document: Minutes , 29/03/2010 Strategy and Resources Scrutiny Committee /79/SRMinutes 81 KB Download
PDF
Options for Site K1, Orchard ParkReport 190 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SB
Councillor Sarah BrownChair, present
CR
Councillor Colin RosenstielVice-Chair, present
SB
Councillor Sue BirtlesCommittee Member, present
MB
Councillor Max BoyceCommittee Member, present
MA
Councillor Mark AshtonCommittee Member, present
JB
Councillor Jeremy Benstead Labour Spokes for Customer Services and ResourcesCommittee Member, present
LH
Councillor Lewis Herbert Labour Spokes for Strategy and Climate ChangeCommittee Member, present
PT
Councillor Philip TuckerCommittee Member, apologies, sent representative
AP
Councillor Adam PogonowskiReserve
AB
Councillor Andy BlackhurstCommittee Member, present

On this subject at Cambridge

Search all
  1. Options for Site K1, Orchard ParkThis decision
  2. Cambridge Local Plan - Towards 2031 Issues and Options 2 (Site Options Consultation)Agreed

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open