Upgrade of Corn Exchange Building Management System (BMS) Heating Controls in the Front Plant Room

Approved Scrutiny 1 paper

Community Services Scrutiny Committee approved this item on Thursday 17 January 2013. Below is the council's own wording, with the papers it was decided on.

Item13/14/CS

Resolved

To consider the upgrade of Corn Exchange Building Management System (BMS) Heating Controls in the Front Plant Room Decision of the Executive Councillor for Arts, Sport and Public Places: The Executive Councillor resolved to Financial recommendations i. Recommend this scheme which is on the Capital plan (C3227) for approval by Council, subject to resources being available to fund the capital and revenue costs. ii. Approve the total cost of the project is £20,000, funded from Corn Exchange Repairs and Renewals fund iii. Note that there are no on-going revenue implications arising from the project . Procurement recommendations i. Approve the carrying out and completion of the procurement of a heating control system for the Corn Exchange foyer area. Subject to the permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the As per the officer report Any alternative options considered and rejected: N/A Scrutiny Considerations: N/A – Not requested for pre-scrutiny The Executive Councillor approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensation granted): N/A
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Community Services Scrutiny Committee

Page 1 of 7

Cambridge City Council

Executive Councillor for Arts, Sport and Public To: Places Report by: Steve Bagnall Scrutiny committee: COMMUNITY SERVICES Jan 2013 Wards affected: None

Project Appraisal and Scrutiny Committee Recommendation Project Name: Corn Exchange - improvements to heating management system

Recommendation/s Financial recommendations – • The Executive Councillor is asked to recommend this scheme which is on the Capital plan (C3227) for approval by Council, subject to resources being available to fund the capital and revenue costs. • The total cost of the project is £20,000, funded from Corn Exchange Repairs and Renewals fund • There are no ongoing revenue implications arising from the project. Procurement recommendations: The Executive Councillor is asked to approve the carrying out and completion of the procurement of a heating control system for the Corn Exchange foyer area. • Subject to:

- The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Page 2 of 7

1 Summary 1.1 The project

Purchase and installation of heating control system to include control panel , valves, dampers and sensors.

Target Dates: Start of procurement February 2013 Award of Contract April 2013 Start of project delivery May 2013 Completion of project May 2013

1.2Anticipated Cost Total Project Cost £ 20,000

Cost Funded from:

Funding: Amount: Details:

Reserves £ Corn Exchange Buildings Repairs & Renewals £20,000 R&R fund 27708 Developer £ Contributions Other £

Ongoing Revenue Cost

Year 1 £

Ongoing £ Page 3 of 7

1.3Procurement process Three written quotations will be obtained in response to an appropriate specification.

2 Project Appraisal & Procurement Report

2.1Project Background The existing equipment is old and not fit for purpose, there is a lack of control over the heating system which results in it either being off when it is needed on or on when not needed. This either results in a cold building or an over heated building which wastes energy at some expense. There is also no control over the adjustment of the level of heating so the achieving a comfortable heating level for visitors is very difficult. The new management system will be more energy efficient.

2.2Aims & objectives The aim of the project is to install a heating control system that provides a good level of comfort for visitors and is more energy efficient to operate.

2.3Major issues for stakeholders & other departments None

2.4Summarise key risks associated with the project Not undertaking this work risks ongoing complaints from customers and clients. The inefficiency of the current system also risks considerable energy wastage.

2.5Financial implications a. Appraisal prepared on the following price base: 2012/13 b. Specific grant funding conditions are: None c. Other comments: None Page 4 of 7

2.6Capital & Revenue costs

(a) Capital £ Comments Building contractor / works 5000 Purchase of vehicles, plant & equipment 15000

Professional / Consultants fees

IT Hardware/Software

Other capital expenditure

Total Capital Cost 0

(b) Revenue £ Comments Maintenance R&R Contribution Developer Contributions See Appendix B

Total Revenue Cost 0

2.7VAT implications This work will be subject to VAT at the standard rate.

2.8Environmental Implications Climate Change impact +M

This project will improve the energy efficiency of the Corn Exchange foyer heating system.

2.9Other implications None Page 5 of 7

2.10Staff required to deliver the project This project will largely be delivered via external contractors. Some planning input will be provided by the Corn Exchange technical team. The procurement exercise will be run by the Corn Exchange technical team.

2.11Dependency on other work or projects None

2.12Background Papers None

2.13Inspection of papers

Author’s Name Steve Bagnall

Author’s phone No. 01223 - 457553

Author’s e-mail: [email protected]

Date prepared: 28th November 2012 Page 6 of 7

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Upgrade of Corn Exchange Building Management System (BMS) Heating Controls in the Front Plant RoomReport 181 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 14 attended
SK
Councillor Susannah KerrChair, present
SK
Councillor Simon KightleyVice-Chair, present
AB
Councillor Andy BlackhurstCommittee Member, present
SB
Councillor Sarah BrownCommittee Member, present
SB
Councillor Sue BirtlesCommittee Member, apologies, sent representative
KB
Councillor Kevin Blencowe Labour Spokes for HousingCommittee Member, present
ZM
Councillor Zoe Moghadas Labour Spokes for Arts, Sport and Public PlacesCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Community Development and HealthCommittee Member, present
DB
Diane Best HMB - Tenant and Leaseholder RepresentativeCo-Optee, present
KH
Kay Harris HMB - Tenant and Leaseholder RepresentativeCo-Optee, present
JM
John Marais HMB - Tenant and Leaseholder RepresentativeCo-Optee, apologies, sent representative
TD
Tom Dutton Primary Care Trust RepresentativeCo-Optee, expected

All 14 on the meeting page

More from Cambridge Community Services Scrutiny Committee

All decisions
MeetingDecisionOutcome
15 Mar 2018 Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a... Refused Open
15 Mar 2018 Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover... Approved Open
15 Mar 2018 Annual Update on the Work of our Strategic Partnerships - Communities PortfolioDecision The Officer’s report provides an update on the work of the Health and Wellbeing Board and Children’s Trust a... Agreed Open
18 Jan 2018 Policy for Use of Events on Parks and Open SpaceDecision The hosting of events on city parks and open spaces had become increasingly popular with both local and nati... Approved Open
18 Jan 2018 S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies