Upgrade of Corn Exchange Building Management System (BMS) Heating Controls in the Front Plant Room
ApprovedScrutiny1 paper
Community Services Scrutiny Committee approved this item on Thursday 17 January 2013. Below is the council's own wording, with the papers it was decided on.
To consider the upgrade of Corn Exchange Building Management System (BMS) Heating Controls in the Front Plant Room Decision of the Executive Councillor for Arts, Sport and Public Places: The Executive Councillor resolved to Financial recommendations i. Recommend this scheme which is on the Capital plan (C3227) for approval by Council, subject to resources being available to fund the capital and revenue costs. ii. Approve the total cost of the project is £20,000, funded from Corn Exchange Repairs and Renewals fund iii. Note that there are no on-going revenue implications arising from the project . Procurement recommendations i. Approve the carrying out and completion of the procurement of a heating control system for the Corn Exchange foyer area. Subject to the permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the As per the officer report Any alternative options considered and rejected: N/A Scrutiny Considerations: N/A – Not requested for pre-scrutiny The Executive Councillor approved the recommendations. Conflicts of interest declared by the Executive Councillor (and any dispensation granted): N/A
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Executive Councillor for Arts, Sport and Public To: Places Report by: Steve Bagnall Scrutiny committee: COMMUNITY SERVICES Jan 2013 Wards affected: None
Project Appraisal and Scrutiny Committee Recommendation Project Name: Corn Exchange - improvements to heating management system
Recommendation/s Financial recommendations – • The Executive Councillor is asked to recommend this scheme which is on the Capital plan (C3227) for approval by Council, subject to resources being available to fund the capital and revenue costs. • The total cost of the project is £20,000, funded from Corn Exchange Repairs and Renewals fund • There are no ongoing revenue implications arising from the project. Procurement recommendations: The Executive Councillor is asked to approve the carrying out and completion of the procurement of a heating control system for the Corn Exchange foyer area. • Subject to:
- The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Page 2 of 7
1 Summary 1.1 The project
Purchase and installation of heating control system to include control panel , valves, dampers and sensors.
Target Dates: Start of procurement February 2013 Award of Contract April 2013 Start of project delivery May 2013 Completion of project May 2013
1.2Anticipated Cost Total Project Cost £ 20,000
Cost Funded from:
Funding: Amount: Details:
Reserves £ Corn Exchange Buildings Repairs & Renewals £20,000 R&R fund 27708 Developer £ Contributions Other £
Ongoing Revenue Cost
Year 1 £
Ongoing £ Page 3 of 7
1.3Procurement process Three written quotations will be obtained in response to an appropriate specification.
2 Project Appraisal & Procurement Report
2.1Project Background The existing equipment is old and not fit for purpose, there is a lack of control over the heating system which results in it either being off when it is needed on or on when not needed. This either results in a cold building or an over heated building which wastes energy at some expense. There is also no control over the adjustment of the level of heating so the achieving a comfortable heating level for visitors is very difficult. The new management system will be more energy efficient.
2.2Aims & objectives The aim of the project is to install a heating control system that provides a good level of comfort for visitors and is more energy efficient to operate.
2.3Major issues for stakeholders & other departments None
2.4Summarise key risks associated with the project Not undertaking this work risks ongoing complaints from customers and clients. The inefficiency of the current system also risks considerable energy wastage.
2.5Financial implications a. Appraisal prepared on the following price base: 2012/13 b. Specific grant funding conditions are: None c. Other comments: None Page 4 of 7
2.6Capital & Revenue costs
(a) Capital £ Comments Building contractor / works 5000 Purchase of vehicles, plant & equipment 15000
Professional / Consultants fees
IT Hardware/Software
Other capital expenditure
Total Capital Cost 0
(b) Revenue £ Comments Maintenance R&R Contribution Developer Contributions See Appendix B
Total Revenue Cost 0
2.7VAT implications This work will be subject to VAT at the standard rate.
This project will improve the energy efficiency of the Corn Exchange foyer heating system.
2.9Other implications None Page 5 of 7
2.10Staff required to deliver the project This project will largely be delivered via external contractors. Some planning input will be provided by the Corn Exchange technical team. The procurement exercise will be run by the Corn Exchange technical team.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.