Joint Development Control Committee - Cambridge Fringes approved this item on Wednesday 23 January 2013. Below is the council's own wording, with the papers it was decided on.
Resolved (by 8 votes to 2) to accept the officer recommendation to approve, subject to conditions as set out in committee report and in the Amendment sheet (also listed below), without condition 12. Condition 7: Addition of ‘Plan SC137-ALL-008-L-SPC-0-100-021’ . Condition 11: Amendment of date and version number of Earthworks Statement: ‘P02 dated 18.12.2012’ replaced by ‘P03 dated 18. 01.2013’.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Joint Development Control Committee - Cambridge Fringes
Appendices
Ref Title Page A Government and Regional Guidance and Advice 30 B Local Plan Policies 31 C Supplementary Planning Documents and Material Considerations D Internal Consultations and Cambridgeshire County Council 31 Response E Other External Consultations and Representations 36 F Neighbour & Other Representations 37 G Outline condition status 39 H Design Code Compliance 40 I Plan Pack: 1. Masterplan 2. Southern Fringe Composite Plan 3. Aerial Perspective of the proposal 4. Wingate Way: Extract from Masterplan 5. Wingate Way: Boundary Treatment adjacent to no 35 6. Wider site access plan 7. Tenure distribution plan
2 0.0 INTRODUCTION
0.1This is a Reserved Matters application for 274 dwellings at the northern end of the Clay Farm site (Long Road Plantations parcels 1A, 3 & 4). The applicant is Skanska, who are currently developing parcels 19 & 20 at the southern end of the site.
0.2In August 2010 outline approval was granted for the Clay Farm development of up to 2,300 homes, a local centre, schools and open space. The outline permission approved 6 parameter plans with which all reserved matter applications must comply. These covered land use, access, density, building heights, landscaping and urban design principles. A full application for the construction of the spine road through the Clay Farm site from Long Road to the Addenbrooke’s Road (AR) roundabout, site wide drainage infrastructure and works to the Long Road plantations was approved at the same time. The spine road is now completed and the associated trees planted.
0.3Reserved matters approval was granted for 306 dwellings for Royal Showground Parcels 10,11,12b and 12c (Countryside Properties) in July 2011, for 128 dwellings for Royal Showground Parcels 19 and 20 (Skanska Residential) in October 2011 and for 102 dwellings for parcel 16 and part 17 (Bovis Homes) in September 2012. The first of these are under construction, with show homes and marketing suites open and first occupations are expected this winter. Construction is likely to start on the Bovis site before the end of the year. An application is currently being considered for 229 dwellings on Long Road Parcels 1B, 2 & 5 (Countryside Properties). A plan showing the location of these applications is included in Appendix I.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Development Control Committee - Cambridge Fringes at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.