CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Environment Scrutiny Committee, Tuesday 12 March 2013 at 5.00pm

Cambridge City Centre Cycle Parking Project

Agreed Scrutiny 6 papers

Environment Scrutiny Committee agreed this item on Tuesday 12 March 2013. Below is the council's own wording, with the papers it was decided on.

Item13/25/ENV

Resolved

This report seeks to agree the project proposal, programme and scope for the . It further seeks approval to commence consultation on the on-street cycle parking proposals included within a Preliminary Design Report. Decision of Executive Councillor for Planning and Climate Change : The Executive Councillor resolved: i. To approve initiation of the project, the scope and the programme in accordance with the project documentation referenced in this report, with implementation subject to further scrutiny through approval of project appraisals. Specific approval is sought for the project, which includes the following: • Project Proposal Report ( Appendix A ) of the Officer’s report. • Project Programme ( Appendix B ) of the Officer’s report. ii. To approve commencement of the design and consultation of the on-street parking proposals detailed in the Preliminary Design Report ( Appendix C ) of the Officer’s report. Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: Not applicable. Scrutiny Considerations: The Committee received a report from the Project Delivery and Environment Manager regarding the Cambridge City Centre Cycle Parking Project. The committee made the following comments in response to the report. i. It was acknowledged that there was insufficient funding for a third underground cycle park. ii. The visual impact of high-density cycle parking in the historic core would need careful consideration. iii. It was suggested that the Colleges could be asked if they have land capacity for cycle parking areas. iv. The Equality Impact Assessment should be amended to reflect the positive aspects of encouraging people cycle. It should also highlight navigational aspect of cycle ranks so that they do not create obstacles for other pavement users. v. It was agreed that the East Road area to be added as an area in need of more cycle parking. The Committee resolved unanimously to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

This report seeks to agree the project proposal, programme and scope for the Cambridge City Centre Cycle Parking Project.

It further seeks approval to commence consultation on the on-street cycle parking proposals included within a Preliminary Design Report.

Recommendations

The Executive Councillor is recommended:

2.1To approve initiation of the project, the scope and the programme in accordance with the project documentation referenced in this report, with implementation subject to further scrutiny through approval of project appraisals.

Specific approval is sought for the project, which includes the following:

• Project Proposal Report (Appendix A) • Project Programme (Appendix B)

2.2To approve commencement of the design and consultation of the on-street parking proposals detailed in the Preliminary Design Report (Appendix C).

Report Page No: 1 3. Background

3.1A capital bid of £500,000 for this project was approved at Council in October 2012, which proposes to provide up to 1,000 additional cycle parking spaces in the heart of the city centre.

3.2The city centre has ever growing pressures over its use, which is set to increase as the city expands, particularly around its fringes due to the significant growth agenda.

3.3The City Council’s vision of a city where getting around is primarily by public transport, bike and on foot is a key driver for this project.

3.4The demand for secure cycle parking in the city centre is clear for all to see and this project aims to significantly increase capacity in the heart of the city centre where the demand is at it highest.

3.5With that in mind, the project has two key aims, the first being to provide localised on-street cycle parking throughout the city centre where space allows and the demand for cycle parking is high.

3.6Table 1.0 overleaf shows the potential locations that have currently been identified for additional on-street cycle parking provision and includes the number of additional spaces that could be created.

3.7Some of these proposals involve a reduction in on-street metered parking bays, disabled parking and green space.

3.8These factors will need to be investigated in more detail prior to public consultation, particularly with Cambridgeshire County Council, which is responsible for on-street parking.

3.9Estimated cost of Table 1.0 is within the £500,000 budget.

Report Page No: 2 TOTAL ESTIMATED ON-STREET ADDITIONAL NUMBER OF NEW LOCATION CYCLE PARKING CYCLE STANDS SPACES Bene't Street 10 20 Christ's Pieces 34 67* Free School Lane 18 36 Guildhall Street 26 52 Jesus Lane 13 26 King's Parade 16 32 Lion Yard / Petty Cury 7 13* Market Square 21 42 Park Terrace 11 22 Peas Hill 32 64 Quayside 30 60 Regent Terrace 25 50 Sidney Street 24 48 St John's Street 18 36 Sussex Street 7 14 Tennis Court Road 8 16 Trinity Street 7 14 Trumpington Street 79 158 TOTAL 356 710 * 1 single-sided stand due to restrictive space Total new cycle stands 356 generating 710 additional cycle parking spaces (two spaces would be defunct due to restrictive space). Table 1: Proposed On-street Cycle Parking Provisions

3.10The second key aim of the project is to investigate the provision of a third dedicated undercover secure cycle parking facility within the heart of the city centre.

3.11Various locations have been identified and their feasibility for providing secured off-street cycle parking facilities is currently being investigated. These include the following locations:

• Lion Yard courtyard; • Market Square underground toilets; • Guildhall basement; • Grand Arcade Car Park.

3.12A further report on the detailed feasibility of these sites will be reported back to this Committee, once the preferred location has been finalised.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cambridge City Centre Cycle Parking ProjectReport 65 KB DownloadRead as text
PDF
[A] CCC Cycle Parking Project Proposal FINAL /25/ENVReport 1.9 MB Download
PDF
[B] CCC Cycle Parking Project Programme FINAL /25/ENVReport 159 KB Download
PDF
[C] CCC Cycle Parking Project Prelim Design FINAL /25/ENVReport 10 MB Download
PDF
[D] Equality Impact Assessment FINAL /25/ENVReport 59 KB Download
PDF
[E] Environmental Impact Assessment FINAL /25/ENVReport 40 KB Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
RJ
Councillor Richard JohnsonCommittee Member, present
GM
Councillor Gail Marchant-Daisley Labour Spokes for Planning and Climate ChangeCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
AR
Councillor Andrea ReinerCommittee Member, apologies, sent representative
SB
Councillor Simon BrierleyCommittee Member, present
LH
Councillor Lewis HerbertCommittee Member, present
D
DepositPublic, expected

On this subject at Cambridge

Search all
  1. Cambridge City Centre Cycle Parking ProjectThis decision
  2. Cambridge City Council Report MRF Update Dec 2025Noted
  3. Procurement at Cambridge City CouncilNoted
  4. Civic Affairs Committee - Cambridge City Council ConstitutionApproved
  5. Cambridge City Council Performance Management FrameworkApproved
  6. Proposals for revised governance arrangements and updated Cambridge City Council ConstitutionApproved

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies