Community Infrastructure Levy Preliminary Draft Charging Schedule

Approved Scrutiny 3 papers

Environment Scrutiny Committee approved this item on Tuesday 12 March 2013. Below is the council's own wording, with the papers it was decided on.

Item13/27/ENV

Resolved

The purpose of the report was to update members on the work that was being undertaken to prepare a Community Infrastructure Levy (CIL) for Cambridge and seek approval that a Preliminary Draft Charging Schedule is published for public consultation in March. Decision of Executive Councillor for Planning and Climate Change The Executive Councillor resolved to: i. Endorse the Cambridge CIL Viability Assessment (Appendix 2 of the Officer’s report) as background evidence to support the proposed Preliminary Draft Charging Schedule; and, ii. Approve the publication of the Cambridge Preliminary Draft Charging Schedule (attached as Appendix 1 of the Officer’s report) for a six-week consultation period between 18 March 2013 and 29 April 2013. Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: Not applicable. Scrutiny Considerations: The committee received a report and an associated presentation from the Senior Planning Policy Officer regarding the Draft Charging Schedule for the Community Infrastructure Levy. Councillor Herbert stated that his group would respond formally to the consultation. The Chair introduced consultants, Richard Dixon and Rob Searle of Dixon-Searle LLP who were present to answer questions regarding the presentation and the report. In response to questions from the committee the following points were clarified. i. Variable charging rates for large or small retail units and across different wards within the City would add to a degree of complication to the process and would raise the admin costs. ii. Keeping the process simple, and directing the CIL charges to the most relevant development types, was suggested as the best course of action for the initial period to avoid unintended consequences. iii. Setting residential rates at too high a level could have an impact on viability of development and so the proposed rates were pitched at the mid-range. iv. There would need to be a robust evidence base to support any move to variable business CIL rates. v. In response to questions, the consultants offered to provide information from authorities that had already introduced CIL for comparison purposes. vi. Concerns were raised that some developments had a greater impact on the local community than others. The consultants confirmed that S106 agreements could still be used on a site-specific basis in mitigation. vii. The impact of an inflexible, flat rate on the delivery of affordable housing was questioned. The consultants stated that providing affordable housing had a greater impact on scheme viability than CIL. The level of affordable housing required would need to be set to reflect this. viii. The charitable status, and associated mandatory exemption, of Universities from CIL was raised as a concern which could result in an imbalance in the provision of student accommodation. ix. It was confirmed that there would be a transition period from S106 to CIL and modelling work was on-going to establish the impact on receipts received. x. The governance of CIL funds was discussed, and the governance arrangements used by Huntingdonshire District Council were held up as an example. The Head of Planning pointed out that governance was an area on which work was underway. This would be the subject of a report to members at a later date. xi. The zero rate applied to hotels was justified as many hotel sites were currently developed on marginal viability. xii. Fringe sites and cross boundary developments would need to be kept under consideration in relation to the emerging Local Plan growth requirements. The Committee resolved by 4 votes to 0 to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Executive summary

1.1The purpose of this report is to update members on the work that is being undertaken to prepare a Community Infrastructure Levy (CIL) for Cambridge and seek approval that a Preliminary Draft Charging Schedule is published for public consultation in March.

1.2A copy of the Draft CIL Viability Assessment and a copy of the Draft Preliminary Draft Charging Schedule are attached as Appendices to this report.

Recommendations

2.1The Executive Councillor is recommended to:

• Endorse the Cambridge CIL Viability Assessment (attached as Appendix 2 to this report) as background evidence to support the proposed Preliminary Draft Charging Schedule; and,

• Approve the publication of the Cambridge Preliminary Draft Charging Schedule (attached as Appendix 1 to this report) for a six-week consultation period between 18 March 2013 and 29 April 2013, subject to any amendments Members may wish to make.

Background

3.1The Community Infrastructure Levy (CIL) is a charge that local authorities can levy on all new development in their area to fund infrastructure improvements related to new development. The 2008 Planning Act established powers to create a CIL in England and Report Page No: 1 Wales. This came into force on 6 April 2010 through the Community Infrastructure Levy Regulations 2010 [now amended by the CIL (Amendment) Regulations 2011, the CIL (Amendment) Regulations 2012 and the CIL (Amendment) Regulations 2013]. The Planning Act 2008 provides a broad definition of infrastructure projects which can be funded by the levy, including transport, flood defences, schools, hospitals and other health and social care facilities. This definition is not exhaustive.

3.2The Council committed to taking a CIL forward in parallel with its Local Plan Review at Development Plan Scrutiny Sub-Committee on 22-03- 2011. A Project Plan for the CIL was agreed at Development Plan Scrutiny Sub Committee on 17-07-2012.

3.3The CIL is intended to supplement (not replace) other funding streams. A number of contributions will still be acquired through S.106 Planning Obligations. These include affordable housing requirements and site specific infrastructure necessary to make a development acceptable in planning terms.

3.4The government considers that the CIL is a more transparent and simpler method of collecting funds for infrastructure to support development than the current system of planning obligations (S.106). As such, regulations restrict the use of Section 106 planning obligations post 2014 to encourage local planning authorities to introduce a CIL. The restrictions mean that post April 2014 (or adoption of a CIL charging schedule, whichever is sooner) tariff based approaches to S.106, such as that operated by the Council, will become inoperable. Regulations state that post 2014 a local planning authority may only enter into five planning obligations to secure funding for the same item of infrastructure. This seriously limits the ability of a Council to raise funds from S.106 post April 2014.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Preliminary Draft Charging Schedule Consultat… /27/ENVAppendix 1 893 KB Download
PDF
CIL Viability Assessment FINAL DRAFT 26.02.2013 /27/ENVAppendix 2 10 MB Download
PDF
Community Infrastructure Levy Preliminary Draft Charging ScheduleReport 101 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
RJ
Councillor Richard JohnsonCommittee Member, present
GM
Councillor Gail Marchant-Daisley Labour Spokes for Planning and Climate ChangeCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
AR
Councillor Andrea ReinerCommittee Member, apologies, sent representative
SB
Councillor Simon BrierleyCommittee Member, present
LH
Councillor Lewis HerbertCommittee Member, present
D
DepositPublic, expected

On this subject at Cambridge

Search all
  1. Community Infrastructure Levy Preliminary Draft Charging ScheduleThis decision
  2. Withdrawal of Community Infrastructure Levy Draft Charging ScheduleApproved
  3. S106 Funding And Interim Arrangements Ahead Of The Local Introduction Of The Community Infrastructure LevyAgreed
  4. Cambridge Community Infrastructure Levy (CIL) – Draft Charging ScheduleApproved
  5. Proposed Response to South Cambridgeshire Local Plan (Proposed Submission Consultation and Community Infrastructure Levy - Preliminary Draft Charging Schedule Consultation)Agreed
  6. Cambridge Local Plan - Towards 2031 – Airport Safety, Higher and Further Education, Tourism, Open Space and Community Facilities, Transport and InfrastructureAgreed

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies