CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Environment Scrutiny Committee, Tuesday 11 June 2013 at 5.00pm

Upgrade and Hosting of the Cemetery and Crematorium Administration System

Approved Scrutiny 1 paper

Environment Scrutiny Committee approved this item on Tuesday 11 June 2013. Below is the council's own wording, with the papers it was decided on.

Item13/10/ESC

Resolved

To upgrade the existing Cemetery and Crematorium Administration System and transfer that system to a hosted arrangement with Gower Consultants. Decision of Executive Councillor for Public Places : The Executive Councillor resolved to: Financial recommendations – i. Recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. • The total cost of the project over 4 years is £23,400, funded from Bereavement Services IT Renewal & Replacement Fund • The ongoing revenue costs of the project are £6,505 ( excl inflation), funded from existing revenue accounts Procurement recommendations : ii. Approved the carrying out and completion of the procurement of: iii. The transfer of the Epilog Burials and Cremation and Administration System to a hosted service with Gower Consultants. iv. The upgrade of the current system to the latest stable release as part of that process. Subject to: • The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. • The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: It was possible to upgrade and retain the system in-house. However, it would be necessary to not only replace the existing server but also purchase additional equipment to run the database and web-facing services, increasing both the capital and revenue costs of the system. Scrutiny Considerations: No Applicable as pre-scrutiny was not requested. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Cambridge City Council

Executive Councillor for Environmental and Waste To: Services Report by: Tracy Lawrence, Bereavement Services Manager Scrutiny committee: Environment 11 June 2013 Wards affected: All

Project Appraisal and Scrutiny Committee Recommendation Project Name: Upgrade and hosting of the Cemetery and Crematorium Administration System

Recommendations Financial recommendations – • The Executive Councillor is asked to recommend this scheme (which is not included in the Council’s Capital & Revenue Project Plan) for approval by Council, subject to resources being available to fund the capital and revenue costs. • The total cost of the project over 4 years is £23,400, funded from Bereavement Services IT Renewal & Replacement Fund • The ongoing revenue costs of the project are £6,505 (excl inflation), funded from existing revenue accounts Procurement recommendations:

• The Executive Councillor is asked to approve the carrying out and completion of the procurement of: • The transfer of the Epilog Burials and Cremation and Administration System to a hosted service with Gower Consultants. • The upgrade of the current system to the latest stable release as part of that process. Subject to: • The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract.

• The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%.

Project Name: Upgrade and hosting of the Cemetery and Crematorium Administration System

1 Summary 1.1 The project

Upgrade the existing Cemetery and Crematorium Administration System and transfer that system to a hosted arrangement with Gower Consultants.

Target Dates: Start of procurement Not applicable (exempted) Award of Contract Not applicable (exempted) Start of project delivery November 2013 Completion of project March 2014 Date that project output is expected to become operational (if not same as above) 1.2 Anticipated Cost Total Project Cost £ 23,400 Cost Funded from:

Funding: Amount: Details:

Reserves £ Bereavement Services IT R Repairs & Renewals £23,400 & R Fund Climate Change £ Fund Other £

1.3Procurement process Gower Consultants are the leading supplier from only two in this specialist market. A waiver will be sought to exclude the competitive tendering process in these circumstances.

Detailed costing have been obtained for the work required.

2 Project Appraisal & Procurement Report

2.1Project Background The Epilog Burials and Cremation Administration System has been in use with the Council since 1997. Other than minor patches the current version is the original installation and is about to become unsupported. It is stored on a server running an unsupported operating system. The latest version supports a number of new features that will benefit the Council and its customers, including online and teletone bookings as well as automatic invoice generation through Oracle.

It is possible to upgrade and retain the system in-house. However, it would be necessary to not only replace the existing server but also purchase additional equipment to run the database and web- facing services, increasing both the capital and revenue costs of the system. An alternative solution, is for Gower Consultants to host the system on our behalf. This has a number of merits:

• Capital Costs are reduced as the Council does not need to buy new and replacement servers and may actually be in a position to dispose of some obsolete ones. Current hardware replacement costs are estimated at £56,363 (lowest cost virtual server approach).

• Under this arrangement the overall revenue costs payable to Gower increase as there is a hosting “charge”. However the revenue costs attributable to server support internally (based on the required servers) are consequently reduced.

• The system will benefit from 24/7 support directly by those who supply the system, particularly where the online booking option is in use.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Upgrade and Hosting of the Cemetery and Crematorium Administration SystemReport 52 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
KB
Councillor Kevin Blencowe Labour Spokes for Planning and Climate ChangeCommittee Member, present
GM
Councillor Gail Marchant-DaisleyCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Public PlacesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, apologies, sent representative
SB
Councillor Simon BrierleyCommittee Member, present
LH
Councillor Lewis HerbertReserve

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies