CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Environment Scrutiny Committee, Tuesday 11 June 2013 at 5.00pm

Jesus Green Drainage

Approved Scrutiny 1 paper

Environment Scrutiny Committee approved this item on Tuesday 11 June 2013. Below is the council's own wording, with the papers it was decided on.

Item13/14/ESC

Resolved

To approve the undertaking of a feasibility study and potential physical improvements to the drainage capacity of an area of 16000m2 of Jesus Green, to alleviate problems with seasonal standing surface water. Decision of Executive Councillor for Public Places : The Executive Councillor resolved to: Financial recommendations i. The Executive Councillor, in consultation with the Chair and Spokes is asked to approve the feasibility study and commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR034C - 38226). · The total cost of the project is £ 105,000 funded from developer contributions · The on-going revenue costs of the project are £ 1,500 per annum over a 30 year period, funded from Streets and Open Spaces Repairs and Renewals fund. Procurement recommendations : ii. The Executive Councillor approved the commencement of the project and procurement, including the award of contract, of contractors for the drainage improvements for Jesus Green Subject to: · The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract value. · The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the As set out in the Officer’s report. Any Alternative Options Considered and Rejected: Not applicable. Scrutiny Considerations: The Committee received a report from the Project Delivery and Environment Manager regarding Improvements. Councillor Kightley proposed an amendment to the financial recommendations as follow (additional wording in bold and underlined): · The Executive Councillor, in consultation with the Chair and Spokes is asked to approve the feasibility study and commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR034C - 38226). Members agreed the amendment. In response to questions from members, the Officer confirmed the following: i. The proposed works would not stop flooding but would ensure the ground drained quicker. ii. Arboricultural Officers would be consulted but no impact on the trees was anticipated. iii. There would be a visual impact on the area for some months. However long term visual amenity would be unaffected. iv. Discussions were on-going with the Environment Agency. v. Members welcomed the prospect of using the area as a sports facility for longer periods of the year than currently possible. The Committee resolved unanimously to endorse the amended recommendations. The Executive Councillor approved the recommendation. Conflicts of interest declared by the Executive Councillor (and any dispensations granted) Not applicable .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Cambridge City Council

To: Executive Councillor for Public Places Report by: DIRECTOR OF ENVIRONMENT Scrutiny committee: ENVIRONMENT Wards affected: MARKET

Project Appraisal and Scrutiny Committee Recommendation

Project Name: Jesus Green Drainage To: Executive Councillor for Public Places Report by: DIRECTOR OF ENVIRONMENT Scrutiny committee: ENVIRONMENT Wards affected: MARKET

Project Appraisal and Scrutiny Committee Recommendation

Project Name: Jesus Green Drainage Recommendation/s Financial recommendations –

• The Executive Councillor is asked to approve the feasibility and commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan (PR034C - 38226). • The total cost of the project is £ 105,000 funded from developer contributions • The on-going revenue costs of the project are £ 1,500 per annum over a 30 year period, funded from Streets and Open Spaces Repairs and Renewals fund.

Procurement recommendations: • The Executive Councillor is asked to approve the commencement of the project and procurement, including the award of contract, of contractors for the drainage improvements for Jesus Green • Subject to: - The permission of the Director of Resources being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract value.

- The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Project Name: Jesus Green Drainage improvements

1 Summary 1.1 The project

To undertake a feasibility study and potential physical improvements to the drainage capacity of an area of 16000m2 of Jesus Green, to alleviate problems with seasonal standing surface water.

The Project is seasonally/weather dependent and the below dates for delivery and completion of project should be treated as provisional.

Target Dates: Start of procurement July 2013 Award of Contract August 2013 Start of project delivery October 2013 March 2014 * Completion of project March 2015 ** Project output complete for Date that project output is March 2014, assuming expected to become operational favourable weather and flooding (if not same as above) conditions * Main contract phase is seasonally dependent ** End of retention period

1.2Anticipated Cost Total Project Cost £ 105,000 Cost Funded from:

Funding: Amount: Details:

Reserves £ 0.00

Repairs & Renewals £ 0.00 Developer £ 105,000 Paragraph 2.5 in report Contributions Climate Change £ 0.00 Fund Other £ 0.00

1.3Procurement process The procurement route will be an Invitation to tender (ITT) process from a minimum of four contractors specialising in drainage. Based on the feasibility work, a Quotation for a design and build Tender will be assessed by a skilled officer panel, and scored in accordance with a clear evaluation scheme detailed in the ITT.

2 Project Appraisal & Procurement Report

2.1Project Background

The drainage of Jesus Green is identified as a strategic priority for the use of city-wide developer contributions funding for the delivery of short to medium term projects by the Executive Councillor for Arts, Sport and Public Places in January 2013, having been put forward by the West/Central Area Workshop in September 2012.

To alleviate problems of standing surface water (caused mostly by rainfall and a potentially high Groundwater level) on selected areas of Jesus Green, a drainage solution will be investigated to take excess water from the surface of the Common in areas of high use. Part of this process will be the appointment of a geo-technical engineer to produce a report on site conditions and potential drainage options. This feasibility study will enable Officers to appoint a specialist design and build contractor to implement the most suitable scheme. A variety of different solutions may be required to find the most suitable means of alleviating the problems caused by standing surface water.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Jesus Green DrainageReport 362 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 10 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, present
KB
Councillor Kevin Blencowe Labour Spokes for Planning and Climate ChangeCommittee Member, present
GM
Councillor Gail Marchant-DaisleyCommittee Member, present
GO
Councillor George Owers Labour Spokes for Environmental and Waste ServicesCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Public PlacesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
DT
Councillor Damien TunnacliffeCommittee Member, apologies, sent representative
SB
Councillor Simon BrierleyCommittee Member, present
LH
Councillor Lewis HerbertReserve

On this subject at Cambridge

Search all
  1. Jesus Green DrainageThis decision
  2. Councillor Bick: Winter Opening of Jesus Green LidoDecided
  3. 20/0034/FUL - Jesus Green Moorings, Thompsons LaneRefused
  4. 20/0034/FUL - Jesus Green Moorings, Thompsons LaneDeferred
  5. Jesus Green Lido ImprovementsApproved
  6. 16/0001/FUL - Lock House, Jesus GreenRefused

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies