Community Services Scrutiny Committee approved this item on Tuesday 25 June 2013. Below is the council's own wording, with the papers it was decided on.
Decision The report provided a review of the programme and specifically seeks approval of a revised three year rolling programme that includes sites to be investigated 2013/14 to 2015/16 . The report set this request for approval to the revised three year programme in the context of the delivery of Affordable Housing through the planning system, and the new Council housing programme. Decision of Executive Councillor for Housing The Executive Councillor resolved to: (i) Approve revisions to the 3 Year Rolling Programme 2013/14 to 2015/16 in the context of the wider . Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Strategic Housing. The Committee resolved (by 4 votes to 0) to endorse the recommendations. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1. Scheme – Jane’s Court (formerly known as Seymour Court)
2. Stage
Stage Date (estimate in italics) 3 Year Programme Community Serv. Scrutiny Com. - Exec Cllr Approval Development Agreement Signed Pre-application First Meeting Planning Application Planning Approval Nov 2010 Development Agreement – Unconditional Start on Site March 2012 Practical Completion October 2013
Comments: This scheme was originally part of the Sheltered Housing Programme.
3. Resident Engagement
First 3 Year Programme Letter N/A 3 Year Programme Up-date Letter (if applicable) N/A Residents Meeting Prior to Exec Cllr Approval N/A Pre-application Neighbourhood Meeting N/A
Comments (including progress with residents re-housing): Tenants were re-housed under the Sheltered Housing Programme. There were no leaseholders.
4. Scheme Mix History
Mix Formerly HCA Bid Exec Cllr Current Approval Bedsits 50 0 0 0 1 bed flat 0 2 2 2 2 bed flat 0 19 19 18 Total 50 21 21 20
Comments: Two flats are to fully wheelchair accessible standards. The new scheme will also deliver fourteen market sale properties, alongside the Affordable Housing.
5. Scheme Cost History
£ HCA Bid Exec Cllr Current Approval Construction - - - Home Loss - - - Project Agent - - - Internal Fee - - - Total 400,000 400,000 400,000
Comments: The scheme was sufficiently advanced when the HCA bid was made for the grant bid and allocation to cover the net construction cost of the Affordable Housing. The cost of relocating tenants is not shown in the above.
Stage Date (estimate in italics) 3 Year Programme Nov 2008 Community Serv. Scrutiny Com. - Exec Cllr 28/06/2012 Approval Development Agreement Signed 25/01/2013 Pre-application First Meeting 28/08/2012 Planning Application 20/12/2012 Planning Approval 03/03/2013 Development Agreement – Unconditional June 2013 Start on Site Sept 2013 Practical Completion Sept 2014 Comments: The detailed scheme design is now being worked up by the architects. Final scheme costs are being prepared ready for validation. Planning conditions are being addressed to enable the Development agreement to move to the unconditional stage.
3. Resident Engagement
First 3 Year Programme Letter 13/11/2008 3 Year Programme Up-date Letter (if applicable) 05/10/2011 Residents Meeting Prior to Exec Cllr Approval None Pre-application Neighbourhood Meeting 20/09/2012
Comments (including progress with residents re-housing): All tenants have been re-housed. One leasehold property has been repurchased through negotiation and a second is in the Council’s ownership through a Compulsory Purchase Order. Negotiations with the remaining two leaseholders has broken down and approval is being sought to apply for Compulsory Purchase Orders.
4. Scheme Mix History
Mix Existing HCA Bid Exec Cllr Current Approval 1 bed flat 16 1 2 1 2 bed flat 0 3 2 3 2 bed house 0 2 2 2 3 bed house 0 3 5 5 4 bed house 0 1 1 1 Total 16 10 12 12
Comments: There are currently 16 one bedroom rented flats, with 4 one bedroom leasehold flats. The new scheme will also deliver eight market sale properties, alongside the twelve Affordable Housing.
5. Scheme Cost History
£ HCA Bid Exec Cllr Current Approval Construction - 772,734 690,373 Home Loss - 565,712 565,712 Project Agent - 30,160 17,650 Internal Fee - - 26,148 Total 982,936 1,368,606 1,299,883
Comments: The HCA bid included assumptions about the cost construction and of compensating leaseholders but no other cost.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.