Joint Development Control Committee - Cambridge Fringes approved this item on Wednesday 20 November 2013. Below is the council's own wording, with the papers it was decided on.
Resolved (unanimously) to grant the application for full planning permission (Major) in accordance with the officer recommendation, for the reasons set out in the officer report, and the inclusion of the following additional condition (9) and informative; Notwithstanding the detail of the Park and Ride junction on plan numbers NWC1-AEC-LA-MW-XXX-DRG-LD-3102 PO2, NWC1-AEC-LA-MW-XXX-DRG-LD-3201 PO2 and NWC1-AEC-LA-MW-XXX-DRG-LD-3501 PO2 prior to development commencing a scheme for the layout of the pedestrian/cyclists crossing shall be submitted to and approved in writing by the local planning authority. Development shall be carried out in accordance with the approved details. Reason: To ensure that a pedestrian and cycle island that can cope with the capacity is included for the safety of future users of the junction. (NWCAAP (2009) policy NW17 & 18). INFORMATIVE: 1) In discharging condition 9 the applicants are asked to show whether a single stage pedestrian/cyclist crossing can be provided without detriment to the efficient operation of the Park and Ride site. 2) If a two stage cross is required, then the applicants should show if the central island can be enhanced to accommodate extra capacity for waiting cyclists or pedestrians.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Joint Development Control Committee - Cambridge Fringes
JOINT DEVELOPMENT CONTROL COMMITTEE (CAMBRIDGE FRINGE SITES)
Report by: Head of Planning Services
Date: 20th November 2013
Application 13/1258/FUL Agenda Item Number Date Received 27 August 2013 Officer Sophie Pain Target Date 26 November 2013 Parishes/Wards Castle
Site Madingley Road West Access Junction, Land Between Huntingdon Road, Madingley Road, and the M11, North West Cambridge, Cambridge, Cambridgeshire
Proposal Highway embankment construction; gabion retaining wall construction; drainage and land drain construction; installation of fencing; carriageway and footway reconstruction; installation of buried infrastructure, including traffic signal ducting and associated landscaping.
Applicant University of Cambridge
Recommendation Approve with conditions
Application Type Full Application (Major) Departure: No
The above applications have been reported to the Planning Committee for determination by Members in accordance with the Scheme of Delegation for the Joint Development Control Committee for the Cambridge Fringes. 0.0 INTRODUCTION
0.1The Joint Development Control Committee (JDCC) resolved to grant approval of the outline planning applications (11/1114/OUT and S/1886/11) on 8th August 2012 subject to the completion of the S106 agreement, which was signed on 22nd February 2013.
0.2The approval for the wider site is for a mixed-use development to the north- west of Cambridge, known as the ‘Land Between Huntingdon Road, Madingley Road and the M11’ or the ‘University site’. The scheme comprises up to 3,000 dwellings (of which 1,500 are to be affordable key worker units), 2,000 student bed spaces, 100,000sqm of employment floorspace (of which at least 60,000sqm will be academic employment space), a primary school, open space, recreational facilities, and a local centre which includes retail and community facilities, a hotel, police office, health facilities, senior living accommodation and an energy centre.
0.3The permitted outline application included works to widen Madingley Road and to construct the Madingley Road West Junction as set out within the description of development. The extent of these approved works include;
• Junction improvements works at the High Cross/Madingley Road junction to alter it from a three arm priority junction to a four arm signal controlled junction including pedestrian and cycle crossings, to provide access to the proposed development; • Installation of a toucan crossing across Madingley Road • Diversion and/or replacement and/or protection of existing utilities affected by the proposed highway works • Construction of sections of unsegregated footway/cycleway and provision of sections of on-carriageway cycleway on the northern side of Madingley Road; • Installation of a retaining wall along Madingley Road • Provision of a new pumped foul water rising main, including chamber connection, and new telecommuniciaitons, electricity and gas infrastructure and the associated connection to existing utility infrastructure situated along Madingley Road; • Related landscaping, accommodation works, street furniture, drainage, telemetry and utilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Development Control Committee - Cambridge Fringes at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.