Project Appraisal for Improvements to St. Augustine's Church

Approved Committee 1 paper

West Central Area Committee approved this item on Thursday 6 March 2014. Below is the council's own wording, with the papers it was decided on.

Item14/21/WCAC

Resolved

Resolved (unanimously) subject to relevant planning approval and completion of the Council’s Capital Grant Agreement, to approve the capital grant of up to £100,000 to St. Augustine’s Church towards the cost of improvements to the community facilities.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to West Central Area Committee

Recommendations

Financial recommendations -

a) Subject to relevant planning approval and completion of the Council’s Capital Grant Agreement, members are asked to approve a capital grant of up to £100,000 to St. Augustine’s Church in Castle Ward. This project is already included in the Council’s Capital Plan.

b) There are no revenue or maintenance implications for the Council.

1 Summary 1.1 The project The project involves a capital grant of up to £100,000 to St. Augustine’s Church towards the cost of improvements to their community facilities. The building is shown at Appendix B and will form an extension to the front and side of the existing community facility.

Provisional funding for the capital grant was agreed by the West/Central Area Committee on 14 November 2013. This was part of the prioritisation round of S106 developer contribution projects.

1 The project appraisal has been considered by the Council’s Asset Management Group.

Note: these are provisional dates Target Dates: provided by St. Augustine’s Start of Procurement April 2014 Award of Contract May 2014 Start of project delivery July 2014 Completion of project Dec 2014

1.2The Cost Total Project Cost £100,000

Capital Cost Funded from:

Funding: Amount: Details:

Reserves £

Repairs & Renewals £ From West/Central Developer £100,000 committee’s developer Contributions contributions programme Climate Change Fund Other

Revenue Cost

Year 1 0

Ongoing 0

1.3The Procurement The works will be procured and project managed by St Augustine’s Church.

2 2 Capital Project Appraisal & Procurement Report

2.1What is the project? This project is to award a capital grant of up to £100,000 to St Augustine’s Church towards improvements to their community facilities. The improvements comprise:

• An upgrade to the main kitchen and provision of improved storage at the front of the hall. • Remodelling of the entrance and front of the building, including new accessible toilet facilities. • A side extension to the main hall to provide additional meeting / event space.

Funding has already been secured by St.Augustines for additional works at the rear of the building which includes refurbishment of the existing toilet block and improvements to a small kitchenette. This work is under construction.

The works will be phased so that they can proceed with the improvements to the front of the hall, should the grant be approved. The side extension will follow on when additional funding is secured. It is estimated that all the works will cost around £300,000. The church has reserves of £25,000 and is actively fund raising to secure the remaining money.

The building is used extensively by a range of community groups on a regular basis, and is also a venue for concerts, talks and other events, including children’s parties and receptions. The current building has served the needs of the community for over 100 years. The improvements will increase the quality and range of facilities on offer, and make better use of the space that is available, in order to make the building accessible to all. The church are looking forward to welcoming residents from the new community at Darwin Green.

2.2The major issues for stakeholders & other departments

This project will significantly improve the range of community facilities at St. Augustine’s Hall and will help to ensure the

3 longer term viability of the hall through increased use and opportunities for income generation.

2.3Summarise key risks associated with the project

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Project Appraisal for Improvements to St. Augustine's ChurchReport 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 12 attended
SK
Councillor Simon KightleyChair, present
PT
Councillor Philip TuckerVice-Chair, present
AR
Councillor Andrea ReinerCommittee Member, present
TB
Councillor Tim BickCommittee Member, present
RC
Councillor Rod CantrillCommittee Member, present
JH
Councillor John HipkinCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
CR
Councillor Colin RosenstielCommittee Member, present
JS
Councillor Julie SmithCommittee Member, present
EC
Councillor Edward Cearns Cambridgeshire County Councillor for MarketCommittee Member, present
JH
Councillor John Hipkin Cambridgeshire County Councillor for CastleCommittee Member, present
LN
Councillor Lucy Nethsingha Cambridgeshire County Councillor for NewnhamCommittee Member, apologies

On this subject at Cambridge

Search all
  1. Project Appraisal for Improvements to St. Augustine's ChurchThis decision
  2. Project Appraisal - ARU/Howes Place Sports GroundApproved
  3. Project appraisal: East Barnwell Community Hub – Centre RedevelopmentApproved
  4. Revised project appraisal for the BMX track at Brown's FieldApproved
  5. Project Appraisal for Improvements to Community Facilities at St. Marks ChurchApproved
  6. Project Appraisal - Ross Street Community Centre ImprovementsAgreed

More from Cambridge West Central Area Committee

All decisions
MeetingDecisionOutcome
14 Sep 2023 Environmental Report - WCACAgreed that the needle pick up across the wards seemed high but compared to the data over 24 months the number of nee... Agreed Open
15 Jun 2023 Policing and Safer Neighbourhoods WCACAgreed to speak with Inspector McNeill on how to improve the message of successes and if a briefing note could be cir... Agreed Open
16 Mar 2023 Open ForumAgreed with the points raised as experienced the same issues. ii. Had recently spoken with the traffic warden who wer... Agreed Open
5 Mar 2020 WCAC Area Committee Grants 2020-21Resolved- To approve the recommendations in paragraph 2 of the officer report. Approved Open
5 Mar 2020 Environmental Improvement ProgrammeResolved- To approve the recommendations in paragraph 2 of the officer report. Approved Open