Environment Scrutiny Committee, Tuesday 11 March 2014 at 5.00pm

Queen Anne Terrace Car Park Holding Repairs

Approved Scrutiny 2 papers

Environment Scrutiny Committee approved this item on Tuesday 11 March 2014. Below is the council's own wording, with the papers it was decided on.

Item14/35/Env

Resolved

Decision To carry out a five-year programme of essential structural repairs to the car park structure, repairs to the car parks impact barriers, drainage repairs and refurbishment of the lift, including associated specialist technical and tendering support and supervision. Decision of Executive Councillor for Planning and Climate Change Financial recommendation The Executive Councillor is asked to approve the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan. · The total cost of the project is estimated to be £580,000 over five years, funded from Repairs and Renewals · There are no on-going revenue implications arising from the project. Procurement recommendations The Executive Councillor is asked to approve the carrying out and completion of the procurement of essential structural repairs to the car park structure, repairs to the car parks impact barriers, drainage repairs and including associated specialist technical and project management support to specify and supervise the repair works over the next five years to the value of £580,000. Subject to: · The permission of the Director of Business Transformation being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. · The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Specialist Services. In response to Members’ questions the Head of Specialist Services said the following: i. The report covered expected maintenance costs for the Queen Anne Terrace Car Park over a five year period. Options could be reviewed after this period, such as further maintenance or redevelopment of the site. ii. Most repair work would be undertaken at the start of the five year period, work outside of this period was unlikely to be justified at present. Annual inspections would be undertaken to monitor the state of the car park. A cost / benefit analysis would need to be undertaken for work outside of the planned five year period. iii. Various proposals for mixed site use had been made over time, such as roofing the top deck so it could be used by a diving club. These were not mentioned in the Officer’s report as no proposals had been made recently. However, short and medium term maintenance was required to safeguard the car park for a further five years. iv. Usage of the Queen Anne Terrace Car Park has grown consistently over the past five years. The car park is well used at most times, and very busy at weekends. The Committee resolved by 4 votes to 0 to endorse the recommendation. The Executive Councillor for Environmental and Waste Services undertook to inform the Executive Councillor for Planning and Climate Change of the Scrutiny Committee decision. Post Meeting Note 19 March 2014 Decision of Executive Councillor for Planning and Climate Change 19 March 2014 Financial recommendation Approved the commencement of this scheme, which is already included in the Council’s Capital & Revenue Project Plan. · The total cost of the project is estimated to be £580,000 over five years, funded from Repairs and Renewals. · There are no on-going revenue implications arising from the project. Procurement recommendations Approved the carrying out and completion of the procurement of essential structural repairs to the car park structure, repairs to the car parks impact barriers, drainage repairs and including associated specialist technical and project management support to specify and supervise the repair works over the next five years to the value of £580,000. Subject to: · The permission of the Director of Business Transformation being sought prior to proceeding if the quotation or tender sum exceeds the estimated contract. · The permission from the Executive Councillor being sought before proceeding if the value exceeds the estimated contract by more than 15%. Scrutiny Considerations The Executive Councillor approved the recommendations in accordance with the Officer recommendations and the committee vote. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Cambridge City Council Equality Impact Assessment Completing an Equality Impact Assessment will help you to think about what impact your strategy, policy, plan, project, contract or major change to your service may have on people that live in, work in or visit Cambridge, as well as on City Council staff.

The template is easy to use. You do not need to have specialist equalities knowledge to complete it. It asks you to make judgements based on evidence and experience. There are guidance notes on the intranet to help you. You can also get advice from David Kidston, Strategy and Partnerships Manager on 01223 457043 or email [email protected] or from any member of the Joint Equalities Group.

1. Title of strategy, policy, plan, project, contract or major change to your service:

Programme of holding repairs to Queen Anne Multi Storey car park

Page 1 2. What is the objective or purpose of your strategy, policy, plan, project, contract or major change to your service?

The Council is currently considering options for the future of Queen Anne Terrace multi- storey car park, which is now over 40 years old. Essential structural and safety repairs including a lift refurbishment will be required over the next five years in order to ensure its safe operation, provide a safe environment to the public and officers of the Council, and protect future income streams whilst consideration is taken for its long term future

The priority works in the project will focus on carrying out essential structural repairs to the concrete and steel structure, to lay a new protective membrane of the roof, to replace or strengthen vehicle impact barriers throughout the car park, and address drainage problems. Refurbishing the lift will also be an early element of the programme of works. Annual inspections will review the precise programme for subsequent years.

The project will improve the safety of the current parking facilities and extend the useful life of the car park, thereby protecting potential future revenue streams to the Council from car parking.

It will contribute to ensuring that all customers have an entirely satisfactory experience of using the Council’s services.

The refurbishment of the lift will help us maintain the Park Mark award, which is a police run safer parking scheme aimed at reducing crime and fear of crime in parking facilities. This refurbishment will however mean that the lift will be out of action for 1 or 2 weeks.

Parking services will liaise closely with the contractor to carefully plan the works to ensure that as much public parking remains available as possible and that works are not being carried out at potentially busy periods, so reducing the impact to the public and local businesses.

In the event of parking level closures or limited spaces we have capacity at the nearby Grand Arcade, Park Street, Grafton East/west car parks to accommodate additional vehicles.

3. Who will be affected by this strategy, policy, plan, project, contract or major change to your service? (Please tick those that apply)

Residents Visitors Staff

A specific client group or groups (please state): General Public Staff

Page 2 4. What type of strategy, policy, plan, project, contract or major change to your service is this? (Please tick)

New Revised Existing

5. Responsible directorate and service

Directorate: Environment

Service: Parking Services (Specialist Services)

6. Are other departments or partners involved in delivering this strategy, policy, plan, project, contract or major change to your service?

No Yes (please give details):

Advice and contract design by Legal Services. Advice from Procurment dept. The sevices of an external consultant who will be a structural surveyor will be employed to advise us on which essential repairs are required, to write the contractor specification and monitor the works.

Page 3 7. Potential impact

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
QATii EqIA: QAT car park Essential repairs 2014 /35/EnvReport 142 KB DownloadRead as text
PDF
Queen Anne Terrace Car Park Holding RepairsReport 197 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
SK
Councillor Simon KightleyChair, present
PS
Councillor Paul SaundersVice-Chair, apologies
KB
Councillor Kevin Blencowe Labour Spokes for Planning and Climate ChangeCommittee Member, present
SB
Councillor Simon BrierleyCommittee Member, present as substitute
NG
Councillor Nigel GawthropeCommittee Member, present
CO
Councillor Carina O'Reilly Labour Spokes for Public PlacesCommittee Member, present
SR
Councillor Sian ReidCommittee Member, present
PR
Councillor Peter Roberts Labour Spokes for Environmental and Waste ServicesCommittee Member, present
PT
Councillor Philip TuckerCommittee Member, present

On this subject at Cambridge

Search all
  1. Queen Anne Terrace Car Park Holding RepairsThis decision
  2. Grand Arcade and Queen Anne Terrace Car Parks Sprinkler System ReplacementApproved
  3. Replacement of Car Parking Equipment at Queen Anne Terrace, Grafton East and Grafton West Multi-Storey Car ParksApproved
  4. Topographical Surveys for Grafton East, Queen Anne Terrace and Grand Arcade Multi Storey Car ParksRefused

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies