Grand Arcade and Queen Anne Terrace Car Parks Sprinkler System Replacement

Approved Scrutiny 1 paper

Environment Scrutiny Committee approved this item on Tuesday 17 January 2017. Below is the council's own wording, with the papers it was decided on.

Item17/8/Env

Resolved

Decision The Executive Councillor was asked to approve a project to procure and award a contract, subject to budget approval, to replace the sprinkler systems located in the underground levels of the Grand Arcade annex and the basement of the Queen Anne Terrace car park. Decision of Executive Councillor for Planning Policy and Transport Approved carrying out the procurement and contract award for a project to replace the sprinkler systems in the underground parking levels at the Grand Arcade and Queen Anne Terrace car parks. Funding for these works as part of an overall capital bid of £1.4 million. So as to meet these and other proposed works at the multi storey car parks in 2017/18. · Subject to: If the quotation or tender sum exceeds the estimated contract value by more than 10% then the permission of the Executive Councillor and Strategic Director will be sought prior to proceeding. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Commercial Operations Manager . The Commercial Operations Manager said the following in response to Members’ questions: i. The sprinkler system needed to be replaced now for the car park to continue to be fully operational. If work was not undertaken the basement would have to be closed due to fire risk. ii. There were frequent intermittent instances when different parts of the sprinkler system were inoperative. This increased costs, so investment funding was needed to protect the Council’s reputation and income stream. iii. Car park usage would be reviewed after 2019 for maintenance planning reasons. iv. The proposed replacement system would be ‘dry’, the old one was water based and so more affected by cold weather ( freezing ). A key contract requirement was to have a more freeze/thaw resistant system than the present one. The Committee endorsed the recommendation by 3 votes to 0. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Environment Scrutiny Committee

Recommendations

The Executive Councillor is recommended:

2.1To approve the carrying out the procurement and contract award for a project to replace the sprinkler systems in the underground parking levels at the Grand Arcade and Queen Anne Terrace car parks. Funding for these works is as part of an overall capital bid of £1.4 million. This is so as to meet these and other proposed works at the multi storey car parks in 2017/18.

2.2Subject to: If the quotation or tender sum exceeds the estimated contract value by more than 10% then the permission of the Executive Councillor and Strategic Director will be sought prior to proceeding.

Report Page No: 1 3. Background

The current sprinkler systems installed in the car parks are 30-40 years old respectively. It is known that sprinkler systems have significant problems with corrosion after 12 years and the expected end of life is usually 25 years.

Given the systems are between 5yrs and 15yrs past their lifespan they are at risk of a complete failure or being deemed unsafe. If this was to occur then it is very likely that health and safety would be compromised and the underground parking levels would have to be closed. This would result in a reduction in income and reputational damage to the council.

4. Implications

(a) Financial Implications These works are to be funded as part of an overall capital bid of £1.4 million. This is so as to meet these and other proposed works at the multi storey car parks in 2017/18. The financial implications are set out in the separate parking services appendix 1.

Advice has been given by a sprinkler specialist; however, at this time we do not know accurate costs until quotes have been received from suppliers and as part of the procurement exercise.

Costs relating to repair and replacement of parts have been increasing and we have seen incidences of flooding due to corroded pipes bursting. Failure of the existing sprinkler systems would necessitate closures of parking decks with associated potential loss of income

A repair programme is financially unviable and replacement has been recommended by a sprinkler specialist company. A new sprinkler system would result in significantly reduced costs against ongoing repairs and maintenance.

There are no adverse VAT implications for undertaking the works at either the Grand Arcade Car Park or Queen Anne Terrace Car Park.

(b) Staffing Implications Parking services staffs to manage the project and ensure the car parks remain safe and operational during on-site works

Report Page No: 2 Procurement will be handled through a corporate contract and therefore the existing contractor will obtain quotes and arrange the works contractor. The Council’s contract manager will oversee this process.

(c) Equality and Poverty Implications An equality impact assessment has been completed.

The replacement of the sprinkler system will ensure all groups have adequate fire management whilst using the car parks and therefore no adverse implications have been identified

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Grand Arcade and Queen Anne Terrace Car Parks Sprinkler System ReplacementReport 127 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 8 attended
CP
Councillor Charlotte PerryChair, apologies
NG
Councillor Nigel GawthropeVice-Chair, apologies, sent representative
MS
Councillor Mike SargeantCo-Chair, present
DA
Councillor Donald AdeyCommittee Member, present as substitute
TB
Councillor Tim Bick Lib Dem Spokes for Planning Policy & TransportCommittee Member, present
MG
Councillor Markus Gehring Lib Dem Spokes for Environmental Services and City CentreCommittee Member, apologies, sent representative
DR
Councillor Dan RatcliffeCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present as substitute

On this subject at Cambridge

Search all
  1. Grand Arcade and Queen Anne Terrace Car Parks Sprinkler System ReplacementThis decision
  2. Grand Arcade Deck Coating and Drainage Repairs/ReplacementApproved
  3. Topographical Surveys for Grafton East, Queen Anne Terrace and Grand Arcade Multi Storey Car ParksRefused
  4. Capital Project to Relocate/Amalgamate Car Park Control Room and Shopmobility Office at Grand Arcade Car ParkApproved
  5. Replacement of Car Park Management System at Grand Arcade Car ParkRefused

More from Cambridge Environment Scrutiny Committee

All decisions
MeetingDecisionOutcome
13 Mar 2018 Air Quality Action PlanDecision of Executive Councillor for Environmental Services and City Centre. i. Approved the Cambridge 2018 – 23, as ... Approved Open
13 Mar 2018 Shared Waste 2018/19 Business PlanDecision of Executive Councillor for Waste Services and City Centre. i. Approved the 2018/19 Shared Waste business Pl... Approved Open
13 Mar 2018 Greater Cambridge Planning Service - 2018/19 Business PlanDecision of Executive Councillor for Planning Policy & Transport i. Approved the 2018/19 Greater Cambridge Planning S... Approved Open
16 Jan 2018 Shopmobility Services ReviewDecision of Executive Councillor for Planning Policy & Transport i. Approved the Introduction of annual membership fe... Approved Open
16 Jan 2018 PP&T Portfolio Revenue and Capital Budget Proposals for 2018/19 to 2022/23Decision of Executive Councillor for Planning Policy and Transport Review of Charges: i . Approved the proposed charg... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies