Environmental Improvement Programme

Approved Committee 5 papers

East Area Committee approved this item on Thursday 19 June 2014. Below is the council's own wording, with the papers it was decided on.

Item14/39/EAC

Resolved

RESOLVED To allocate funding of £10,890 for the annual provision and maintenance of 66 hanging baskets along Mill Rd. To fund the following projects as detailed in the Officer’s report: E1 Oyster Row road narrowing - £23,500 E2 Riverside/Stourbridge Common parking scheme - £12,500 E7 Cherry Hinton Road / Perne Road road signs - £6,000 E18 Tenison Road noticeboard - £1,750 E19 Glisson Road Tree (bollard option ) - £2,000 E6 Silverwood Close £ 500 These approvals lead to an over allocation of £725, which was agreed to be resolved by targeting savings across the Oyster Row Road Narrowing and Riverside/ Stourbidge Common Parking Scheme project budgets.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to East Area Committee

Executive summary

 This report requests that the Committee determine which of the proposed new EIP schemes are allocated funding as part of the 2014/15 Environmental Improvement Programme, from those listed in Appendix A of this report.

Recommendations

The East Area Committee is recommended:

2.1To allocate funding of £10,890 for the annual provision and maintenance of 66 hanging baskets along Mill Rd. 2.2 To allocate the remaining £45,310 to the list of proposed projects in Appendix A of this report. 2.3 To approve those projects for implementation, subject to positive consultation where required and final approval by Ward Councillors. 2.4 To note the progress of existing schemes listed in Appendix C of this report.

Background

3.1Initial feasibility work has been carried out on all of the schemes that have been suggested for the 2014/15 Environmental Improvement Programme (EIP).

3.2The table in Appendix A lists all of the schemes that could be feasibly delivered as part of this year’s EIP Programme, should they be allocated funding by East Area Committee.

Report Page No: 1 3.3 The East Area Committee has an annual budget of £56,200 to allocate to schemes from its Environmental Improvement Programme Budget.

3.4Any scheme that involved the public highway was submitted to Cambridgeshire County Council, with authority for the public highway, to apply for funding from its Local Highways Improvement (LHI) Programme, of which £112,000 is allocated to the city for 2014/15.

3.5The table in Appendix A highlights those schemes that have secured funding from this budget.

3.6Schemes numbers E4 and E6 have secured funding totalling £14,500. A further £10,000 has been allocated to completing verge protection work in Birdwood Road; which is an existing approved EIP project.

3.7The LHI funding is subject to a minimum 10% third party contribution, proposed to be funded by East Area Committee’s Environmental Improvement Programme.

3.8If the funding is not allocated, then the County Council funding will be withdrawn and reallocated to other LHI projects further down the prioritised list of schemes.

3.9Further details of each proposed EIP scheme can be found in Appendix B of this report.

3.10Appendix A lists a number of schemes aimed at improving damage to verges caused by vehicular parking and access to off-street parking facilities. A significant number of areas across Cambridge are suffering similar problems, many of which are subject to bids for improvements from this and previous EIP rounds. Consequently, it is considered prudent to undertake a review into how best to address this difficulty; balancing the strategic interest with local need.

3.11Some of the schemes that have been suggested for this year’s programme have not been included in Appendix A, as they either; require further assessment of their feasibility, are not deliverable or will be implemented by others. Table 1.0 below provides a summary of these schemes.

Report Page No: 2 Scheme Position

Stone Street parking A Traffic Regulation Order to restrict parking in Stone Street, restrictions in order to facilitate access, is already included on the list of such projects approved by East Area Committee. Detailed development work is required given the difficulty in reaching local agreement over parking controls in the area previously.

Davy Road / Corrie Road East Area Committee previously allocated £8,000 of EIP parking restrictions funding to a project that covered these issues. This will be delivered by the County Council, which is delivering a project to co-ordinate parking management across the south of the city (South Area Parking Review)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Feasible EIP Schemes /39/EACAppendix A 212 KB Download
PDF
Details of Proposed Schemes /39/EACAppendix B 2.7 MB Download
PDF
PROGRESS OF EXISTING SCHEMES /39/EACAppendix C 26 KB Download
PDF
EIP ELIGIBILITY CRITERIA /39/EACAppendix D 13 KB Download
PDF
Environmental Improvement ProgrammeReport 25 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 16 attended
KB
Councillor Kevin BlencoweChair, present
GO
Councillor George OwersVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
CH
Councillor Caroline HartCommittee Member, present
LH
Councillor Lewis HerbertCommittee Member, present
RJ
Councillor Richard JohnsonCommittee Member, present
ZM
Councillor Zoe MoghadasCommittee Member, present
PR
Councillor Peter RobertsCommittee Member, present
RR
Councillor Richard RobertsonCommittee Member, apologies
AS
Councillor Ann SinnottCommittee Member, present
CS
Councillor Catherine SmartCommittee Member, present

All 16 on the meeting page

On this subject at Cambridge

Search all
  1. Environmental Improvement ProgrammeThis decision
  2. Review of the Environmental Improvement ProgrammeAgreed
  3. Environmental Improvement ProgrammeApproved
  4. Environmental Improvement ProgrammeAgreed
  5. Environmental Improvement ProgrammeAgreed
  6. Environmental Improvement Programme 2017-18Noted

More from Cambridge East Area Committee

All decisions
MeetingDecisionOutcome
24 Jun 2021 Open ForumAgreed it was vital that residents understood the documentation and would be happy to arrange assistance when looking... Agreed Open
3 Dec 2020 Policing and Safer NeighbourhoodsRESOLVED unanimously to write to the Acting Police and Crime Commissioner highlighting the Committee’s concern regard... Decided Open
17 Sep 2020 Election of Chair and Vice Chair - EACResolved unanimously that Councillor Barnett be Chair for the ensuing year. Councillor Barnett assumed the chair from... Decided Open
17 Sep 2020 Policing and Safer NeighbourhoodsResolved unanimously to approve the following as local areas of concern: i. Anti-social driving ii. Cycle theft iii. ... Approved Open
17 Sep 2020 Outside Body Appointment: Cambridge Airport Consultative CommitteeResolved that Councillor Davey be the representative for the Cambridge Airport Consultative Committee for the ensuing... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies