Housing Scrutiny Committee, Tuesday 30 September 2014 at 5.30pm

Council Housing at Homerton College Redevelopment

Approved Scrutiny 2 papers

Housing Scrutiny Committee approved this item on Tuesday 30 September 2014. Below is the council's own wording, with the papers it was decided on.

Item14/30/HSC

Resolved

Decision of Executive Councillor for Housing The Executive Councillor for Housing resolved to: i. Approved in principle for the Council to deliver social housing on the Homerton College scheme - noting that a final scheme will be brought back to Committee for scrutiny and approval. ii. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Strategic Housing. The Committee made the following comments in response to the report: i. Congratulated the Head of Strategic Housing and his team. ii. Queried if and how many properties would be tailored for disabled users, such as wheel chair access. iii. Stated it would be helpful for the Government to remove the constraints, particularly on the amount that the Council could borrow in order to move forward. iv. Acknowledged that it was a good news story for the Council but expressed disappointment that the properties did not have to be built to code level five. v. Asked if it was too late to negotiate with the developer to build to code level five. vi. Noted the news release as being slightly misleading as the Housing Scrutiny Committee had not formally agreed the report and planning permission had not yet been granted by the Planning Committee. vii. Asked if the percentage of affordable housing would change. In response to Committees comments Officers, the Director of Community and Customer Services stated the following: i. Noted the comments regarding the press release. ii. As the scheme is well on the way to a detailed planning application the Council has very limited influence on the detail. iii. Very pleased that the Council that are part of the project. iv. With future projects it is hoped that the Council work in partnership from the start and would be able to influence such factors as building to code level five. v. The 40% affordable housing should not change as it would be a breach of planning policy. The Committee: Resolved (unanimously) to endorse the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

The Homerton College scheme is the first to be brought forward in the next phase of the Council’s own Social Housing Programme and is notable too to be the first opportunity to work on a site not owned by the Council.

The report describes the funding background to the next phase of the Social Housing Programme and explains that the factor that is driving our decision making on which schemes to prioritise is the need to spend Right to Buy receipts within a given time limit.

Recommendations

The Executive Councillor is recommended:

Approve in principle for the Council to deliver social housing on the Homerton College scheme - noting that a final scheme will be brought back to Committee for scrutiny and approval.

Report Page No: 1 3. Background

A report to the Housing Scrutiny Committee in July 2014 reiterated that as the main provider of housing in Cambridge, the reasons why the Council has its own new build housing programme are as follows;

1. Provide additional social housing to meet the shortfall in Cambridge and to replace the loss of social housing through the Right to Buy.

2. Replace some of the Council’s existing social housing that no longer meets current day standards and is becoming less popular with residents.

3. Build new house types that will better meet the overall mix of Affordable Housing needed in the future.

4. Improve the energy efficiency of the Council’s housing.

The report described that twenty eight new Council homes have now been completed since 2010 and that we are well into the delivery of 125 more homes funded in part by Homes and Communities Grant. Approval has also been given to commit to the delivery of a further 104 new Council homes on the Quad scheme on the Southern Fringe and a planning permission has been submitted by our developer partner, Hill.

Officers have subsequently been turning attention to the next phase of new Council homes. Having established the Council back into the ‘business’ of building new homes over the last five years officers are beginning to develop a more systematic and comprehensive approach to identifying opportunities for new schemes and matching funding streams and timescales to these opportunities. Although this is still ‘work in progress’, officers are beginning to categorise new schemes opportunities in terms of land ownership as follows;

a. Housing Revenue Account (HRA) land with existing housing b. HRA garage and small in-fill sites c. General Fund sites d. Sites owned by other public sector bodies e. Sites in private ownership

As an indication of scale, sites have been identified that could deliver around 300 new social housing units for the Council over the next four years.

Report Page No: 2 The Homerton College scheme is the first to be brought forward in the next phase of the Council’s own Social Housing Programme and is notable too to be the first opportunity to work on a site not owned by the Council.

The site is owned by Homerton College and is earmarked in the current Local Plan for residential development. Homerton College has selected Hill as their developer partner and Hill in turn has agreed with Homerton College for the Council to provide the social housing.

An outline planning approval is in place for the scheme and Hill are working up a detailed planning application. The whole scheme will mainly consist of flats and the likely schedule of accommodation of the social housing comprising 39 units will be as follows (this is still in development):

One block comprising Rented Apartments -

For Rent;

8 no 1 bedroom 2 person - 50 sq m 17 no 2 bedroom 3 person - 70 sq m 2 no 3 bedroom 5 person - 85 sq m

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Housing at Homerton College RedevelopmentReport 85 KB DownloadRead as text
PDF
Homerton panel presentation September 2014: low res /30/HSCReport 5.8 MB Download

At this meeting

Whole meeting

Who was there

8 of 14 attended
MT
Councillor Mike Todd-JonesChair, present
NA
Councillor Nicholas AveryCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, apologies, sent representative
AB
Councillor Andy Blackhurst Lib Dem Spokes for HousingCommittee Member, present
MH
Councillor Marie-Louise Holland Independent/Conservative Spokesperson for HousingCommittee Member, present
RR
Councillor Richard RobertsonCommittee Member, present
NG
Councillor Nigel GawthropeReserve, present as substitute
DB
Diane Best Leaseholder RepresentativeCo-Optee, expected
KH
Kay Harris Tenant RepresentativeCo-Optee, expected
JM
John Marais Tenant RepresentativeCo-Optee, expected
DM
Diana Minns Tenant RepresentativeCo-Optee, expected

All 14 on the meeting page

On this subject at Cambridge

Search all
  1. Council Housing at Homerton College RedevelopmentThis decision
  2. Council Housing at Homerton CollegeAgreed

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies