Housing Scrutiny Committee, Tuesday 30 September 2014 at 5.30pm

Repairs Improvement Plan - Performance Update

Approved Scrutiny 1 paper

Housing Scrutiny Committee approved this item on Tuesday 30 September 2014. Below is the council's own wording, with the papers it was decided on.

Item14/26/HSC

Resolved

Decision The decision to implement a 2 year improvement plan for the responsive repairs and voids service was approved at the meeting of Housing Management Board on 28 Sept 2010. The Executive Councillor subsequently agreed to extend the period by a further 1 year to enable further investigation into the procurement of alternative IT solutions and to implement the most appropriate option. A report detailing the success of the improvement plan was discussed at the meeting of Housing Management Board in October 2013, at which the decision was made to retain the delivery of the service by the in-house team, providing the high service standards achieved during the period of the improvement plan were maintained. A further report was requested in October 2013 to demonstrate the impact and improvements on service delivery once mobile working has been established for a period of months. The tables included below make a comparison between service delivery before and after implementation of mobile working and the new integrated Orchard software. Decision of Executive Councillor for Housing i. Agreed that a review report be presented to the June cycle each year which monitors annual performance and provides certainty that the decision to retain the service in house is still valid. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Operations Manager. The Committee made the following comments in response to the report: i. Commented that it was good to see improvements were being made and the service was going well. ii. Asked if the data for residents satisfaction had been circulated and how this compared with the recent star survey iii. Queried if the introduction of South View Solutions (SVS) mobile working affected the number of post or pre inspections which were carried out. iv. Requested an explanation as to why the ‘appointments made’ had significantly increased. v. Questioned what the target figure was referenced in the report. In response to Committees comments Officers and the Director of Community and Customer Services stated the following: i. Data on satisfaction for repairs has been obtained but it did not differentiate between planned and responsive repairs. ii. Further work was required to determine if the data was linked to the planned maintenance programme or the responsive repairs programme. Once the work had been completed the results would be shared. iii. Mobile working did not directly affect the post or pre inspections. iv. Before the consolidation of mobile working there had been several categories which had now merged into the ‘Appointments Made’. All jobs were now appointed. v. The target was 98%. The Committee: Resolved (unanimously ) to approve the recommendation. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Housing Scrutiny Committee

Executive summary

The decision to implement a 2 year improvement plan for the responsive repairs and voids service was approved at the meeting of Housing Management Board on 28 Sept 2010. The Executive Councillor subsequently agreed to extend the period by a further 1 year to enable further investigation into the procurement of alternative IT solutions and to implement the most appropriate option. A report detailing the success of the improvement plan was discussed at the meeting of Housing Management Board in October 2013, at which the decision was made to retain the delivery of the service by the in-house team, providing the high service standards achieved during the period of the improvement plan were maintained.

A further report was requested in October 2013 to demonstrate the impact and improvements on service delivery once mobile working has been established for a period of months. The tables included below make a comparison between service delivery before and after implementation of mobile working and the new integrated Orchard software.

Recommendations

The Executive Councillor is recommended:

1 2.1 To agree that a review report is presented to the June cycle each year which monitors annual performance and provides certainty that the decision to retain the service in house is still valid.

Background

3.2.1 The key performance indicators set out below monitor service delivery and identify the level of improvement achieved since the successful launch of mobile working and Direct Works software on 6th January 2014.

Responsive Repairs Service Delivery Improved? Apr – July Apr – July 2013/2014 2014/15

Emergency jobs completed in target 99% 99%

Urgent jobs completed in target 5 97% 98%

Routine jobs completed within target 98% 99% All jobs completed within target 98% 99.% Appointments made 55% 78%

Appointments Kept Data 99% unavailable at present Number of late afternoon 98 176 appointments made Resident satisfaction with the Data completed repair (score out of 10) 9.9 unavailable at present Percentage of jobs where the target date is extended 4.86 2.86%

Average cost of responsive repair 109.72 93.47

Appointments Kept. Currently we are unable to update this information in Direct Works. This issue should be resolved as part of the next SVS upgrade.

2 Resident Satisfaction Currently this data is not downloading from the hand held devices to Orchard. This issue should be resolved as part of the next SVS upgrade. However performance data would suggest that as we are meeting our priority deadlines, customer satisfaction should be high. This is supported by the fact that the level of customer complaints has not increased

Further benefits of the implementation of SVS mobile working and the implementation of Orchard Direct Works software are the reduction of the paper job tickets by 90%, real-time status information recording progress of the work, removal of duplication of data and processes resulting in more accurate management information.

4. Implications

Financial Implications Ongoing costs associated with mobile working and the Orchard Direct Works software are included within current budget allocations.

Staffing Implications

The introduction of mobile working and a single software package has reduced the manual tasks previously carried out and facilitated a reduction in the level of staffing within the Finance team based at Mill Road, which was identified during the support services review.

Equal Opportunities Implications

The impact assessment did not identify any major issues that cannot be resolved through training etc.

Environmental Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Repairs Improvement Plan: Performance UpdateReport 83 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
MT
Councillor Mike Todd-JonesChair, present
NA
Councillor Nicholas AveryCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, apologies, sent representative
AB
Councillor Andy Blackhurst Lib Dem Spokes for HousingCommittee Member, present
MH
Councillor Marie-Louise Holland Independent/Conservative Spokesperson for HousingCommittee Member, present
RR
Councillor Richard RobertsonCommittee Member, present
NG
Councillor Nigel GawthropeReserve, present as substitute
DB
Diane Best Leaseholder RepresentativeCo-Optee, expected
KH
Kay Harris Tenant RepresentativeCo-Optee, expected
JM
John Marais Tenant RepresentativeCo-Optee, expected
DM
Diana Minns Tenant RepresentativeCo-Optee, expected

All 14 on the meeting page

On this subject at Cambridge

Search all
  1. Repairs Improvement Plan - Performance UpdateThis decision
  2. Repairs Improvement Plan - Performance UpdateRefused
  3. Outcome of the Repairs Improvement PlanApproved
  4. Repairs and Maintenance Improvement Plan - Progress to date and permission to procure associated IT solutionsAgreed
  5. Repairs and Maintenance Improvement Plan - Authority to Procure and Progress to DateNoted
  6. Housing Repairs Improvement planRefused

More from Cambridge Housing Scrutiny Committee

All decisions
MeetingDecisionOutcome
11 Mar 2025 Public QuestionsAgreed that a formal legal letter had been sent to residents; it was necessary as part of the legal process. The Exec... Agreed Open
11 Mar 2025 Structural repairs and associated works at Bermuda Terrace flats – 2025Decision The Council owns six blocks of flats at Bermuda Terrace, Histon Road. A programme of structural repairs and ... Approved Open
11 Mar 2025 Pledge to Support the Resettlement of RefugeesDecision In 2020 the Council made a pledge to resettle 200 refugees over 5 years. A major part of the resettlement pr... Agreed Open
11 Mar 2025 Housing Adaptations, Repairs and Renewal PolicyDecision The draft policy contained within Appendix A of the Officer’s report aims to replace the existing Cambridges... Approved Open
11 Mar 2025 City Centre Regeneration SitesDecision The purpose of the report is to provide an update on city centre sites: Stanton House, East Road and Hanover... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies