Resolved (nem con): i. To n ote the project programme, and previous approvals from Environment Scrutiny Committee, and to note the proposed consultation area, consultation method, and content for Phase 3. ii. To provide the comments and recommendations (as above) to the Executive Councillor for Planning, Policy and Transport (Councillor Kevin Blencowe) on the proposed consultation arrangements. Particularly with regard to which roads/sections of roads are specifically identified within Question 3 of the consultation document.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
This report sets out the overall programme for the proposed City-Wide Cambridge 20mph Project. It requests feedback and input to the consultation plans for Phase 3 of the project (the South & West/Central Area).
Recommendations
The West/Central Area Committee is recommended;
2.1to note the project programme, and previous approvals from Environment Scrutiny Committee, and to note the proposed consultation area, consultation method, and content for Phase 3;
2.2to provide comments and recommendations to the Executive Councillor for Planning, Policy and Transport (Councillor Kevin Blencowe) on the proposed consultation arrangements. Particularly with regard to which roads/sections of roads are specifically identified within Question 3 of the consultation document.
Background
3.1In July 2011, a motion to Council was agreed that requested the then Executive Councillor for Planning and Climate Change to evaluate existing 20mph schemes in Cambridge and where appropriate, consult on the expansion of schemes. Support and commitment from Cambridgeshire County Council was secured, and the project scope and resourcing were investigated, which culminated in a budget bid for ‘the Cambridge City 20mph Zones Project’. A capital bid for £400,000 to cover works was agreed in
Report Page 1 February 2012, along with a revenue Priority Policy Fund bid for £59,800 to cover staffing. This initial budget bid was subsequently increased to £600,000 in February 2014, following more detailed development of the project.
3.2Both funding bids stipulate that the project should have a citywide approach. As such the project considers all appropriate roads within the Cambridge City boundary where it is appropriate/feasible to introduce a 20mph limit. Works are subject to agreement with the Highway Authority (Cambridgeshire County Council).
3.3Due to the size of the project, it was divided into four separate phases, reflecting existing area committee boundaries. It is intended that the final two phases, South and West/Central Area, be progressed concurrently and brought to the relevant area committee’s to make a recommendation to the Executive Councillor for Planning, Policy & Transport.
3.4The main aims of the project are to;
provide conditions that are conducive to an increase in the take up of active travel modes such as walking and cycling, and to encourage a modal shift towards these modes reduce the severity of road traffic collisions that occur on the city’s road network reduce noise and air pollution levels, and generally provide a better environment for residents and users of the city.
3.4The project was initially taken to Environment Scrutiny Committee on 15 January 2013, at which approval was provided for the project:
Phasing Programme (see Appendix A) Governance/Decision making process as set out below Board terms of reference (see Appendix B) Engagement/Consultation to commence for Phase 1
Approval was also provided for the following items: Automatic Traffic Counts (ATCs) for project baseline data collection Project wide Engagement/Consultation Activities
Report Page 2 3.6 Subsequently both Phase 1 and 2 were taken to public consultation and met with a positive response, with Phase 1 now implemented and Phase 2 due to complete its legal traffic order stage shortly.
3.7The project returned to Environment Scrutiny Committee on 8 July 2014, at which approval was provided for: Commencement of the statutory legal process for Phase 2 and Victoria Road, and implementation, subject to any objections determined by Cambridgeshire County Council’s Highways & Infrastructure Committee and the Cambridge Joint Area Committee. Commencement of the public consultation and pre-consultation ATCs for Phase 3.
4.0Governance/Decision Making
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Policing and Safer Neighbourhoods WCACAgreed to speak with Inspector McNeill on how to improve the message of successes and if a briefing note could be cir...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.