CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Cambridge City Council
Council, Thursday 6 November 2014 at 6.00pm

Mid Year Financial Review (MFR) October 2014 (Executive Councillor for Finance and Resources)

Agreed Committee 3 papers

Council agreed this item on Thursday 6 November 2014. Below is the council's own wording, with the papers it was decided on.

Item14/53/CNLb

Resolved

Resolved (unanimously): General Fund Revenue i. To agree the budget strategy, process and timetable for the 2015/16 budget cycle as outlined in Section 1 [pages 5 to 6 refer] and Appendix A of the MFR document. Resolved (by 27 votes to 0): ii. To agree incorporation of the budget savings and pressures identified in Section 4 [pages 15 to 17 refer]. This provided an indication of the net savings requirements, by year for the next 5 years, and revised General Fund revenue, funding and reserves projections as shown in Section 5 [page 18 refers] of the MFR document. Resolved (unanimously): Capital To agree: iii. inclusion of a new scheme in the Capital Plan relating to the replacement of an air cooling system, at a cost of £166,950 (£70,000 from existing repairs and renewals funding, the remainder from available capital funding), subject to a detailed project appraisal. iv. other changes to the Capital Plan, predominantly re-phasing as set out in Section 6 [pages 19 to 22 refer] of the MFR document. Note the proposal for a focused review of the processes and procedures underlying capital planning and delivery in advance of setting the 2015/16 budget in February 2015, with a view to delivering improved, fit for purpose processes and a sustainable capital plan, as set out in Section 6 [page 22 of MFR document refers] Reserves v. changes to General Fund Reserve levels, with the Prudent Minimum Balance being set at £4.40m and the target level at £5.28m as detailed in Section 7 [pages 23 to 24 of the MFR document refer].
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Council

Executive summary

1.1This report presents and recommends the budget strategy for the 2015/16 budget cycle and specific implications, as outlined in the Mid- year Financial Review (MFR) October 2014 document, which is attached and to be agreed.

1.2This report also recommends the approval of one new capital item and changes to phasing and funding proposals of the Council’s Capital Plan which will be included in the updated version published separately on the Council’s web site.

1.3At this stage in the 2015/16 budget process the range of assumptions on which the Budget-Setting Report (BSR) published in February 2014 was based need to be reviewed, in light of the latest information available, to determine whether any aspects of the strategy need to be revised. This then provides the basis for updating the 2014/15 revised and 2015/16 budgets. All references in the recommendations to Appendices, pages and sections relate to the MFR Version 1.

1.4The recommended budget strategy is based on the outcome of the review undertaken together with financial modelling and projections of the Council’s expenditure and resources, in the light of local policies and priorities, national policy and economic context. Service managers have identified financial and budget issues and pressures and this information has been used to inform the MFR.

Report Page No: 1 2. Recommendations

The Executive Councillor is asked to recommend to Council:

General Fund Revenue

2.1To agree the budget strategy, process and timetable for the 2015/16 budget cycle as outlined in Section 1 [pages 6 to 7 refer] and Appendix A of the MFR document.

2.2To agree incorporation of the budget savings and pressures, identified in Section 4 [pages 16 to 18 refer]. This provides an indication of the net savings requirements, by year for the next 5 years, and revised General Fund revenue, funding and reserves projections as shown in Section 5 [page 19 refers] of the MFR document.

Capital

2.3To agree:  inclusion of a new scheme in the Capital Plan relating to the replacement of an air cooling system, at a cost of £166,950 (£70,000 from existing repairs and renewals funding, the remainder from available capital funding), subject to a detailed project appraisal  other changes to the Capital Plan, predominantly re- phasing

as set out in Section 6 [pages 20 to 23 refer] of the MFR document.

Note the proposal for a focused review of the processes and procedures underlying capital planning and delivery in advance of setting the 2015/16 budget in February 2015, with a view to delivering improved, fit for purpose processes and a sustainable capital plan, as set out in Section 6 [page 23 refers]

Reserves

2.4To agree changes to General Fund Reserve levels, with the Prudent Minimum Balance being set at £4.40m and the target level at £5.28m as detailed in Section 7 [pages 24 to 25 refer].

Report Page No: 2 3. Background

Mid-year Financial Review

3.1The purpose of this report is to outline the overall financial position of the Council and to consider the prospects for the 2015/16 budget process within the context of projections over the medium-term. The detailed analysis undertaken to fulfil this is presented in the Mid-year Financial Review (MFR) October 2014 document appended to this report.

3.2The document considers the General Fund revenue position and the Council’s overall Capital Plan.

3.3Revenue forecasts are presented for the 5-year projection period through to the year 2019/20, demonstrating the sustainability of the Council’s financial planning with reference to the level of reserves held throughout this period. Underpinning this is a full 25-year financial model, and associated risk analysis.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
MFR: Sept S&R Report /53/CNLbReport 105 KB DownloadRead as text
PDF
MFR Doc: Council /53/CNLbReport 526 KB Download
PDF
Mid Year Financial Review (MFR) October 2014 (Executive Councillor for Finance and Resources)Report 48 KB Download

At this meeting

Whole meeting

Who was there

40 of 42 attended
CC
Cadet Corporal A. MocherlaPublic, expected
GP
Councillor George PippasVice-Chair, present
MA
Councillor Margery AbbottCommittee Member, present
MA
Councillor Mark AshtonCommittee Member, present
YA
Councillor Ysanne AustinCommittee Member, present
NA
Councillor Nicholas AveryCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
TB
Councillor Tim BickCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
AB
Councillor Andy BlackhurstCommittee Member, present
KB
Councillor Kevin BlencoweCommittee Member, present

All 42 on the meeting page

On this subject at Cambridge

Search all
  1. Mid Year Financial Review (MFR) October 2014 (Executive Councillor for Finance and Resources)This decision
  2. Housing Revenue Account (HRA) Mid-Year Financial Review (Executive Councillor for Housing)Approved
  3. General Fund (GF) Mid-Year Financial Review (MFR) (Executive Councillor for Finance and Resources)Agreed
  4. General Fund: Mid Year Financial Review - October 2015Approved
  5. Housing Revenue Account Mid-Year Financial ReviewApproved
  6. Housing Revenue Account (HRA) Mid-Year Financial Review (Executive Councillor for Housing)Approved

More from Cambridge Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Local Government ReviewFollowing a vote, 12 members voted to note the report, 16 voted against noting the report and 8 abstained. It was con... Noted Open
16 Jul 2026 Councillor Hauk:Improving Accountability and Transparency on Unadopted Residential DevelopmentsRESOLVED to adopt the following motion: Council notes: That many residents move into new developments expecting to be... Approved Open
16 Jul 2026 Councillor Toye Scott: Rights of the River Cam 2026RESOLVED to adopt the following motion: 1 Declaration of the Rights of the River Cam This council declares that the R... Approved Open
16 Jul 2026 Councillor Ashton: Darwin Nurseries and Farm ShopResolved (unanimous) to approve the Darwin Nurseries and Farm Shop Motion. Approved Open
16 Jul 2026 Councillor Baigent: Planning ArrangementsRESOLVED to adopt the following motion: This Council commits to keep building more council homes to the highest quali... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies