Resolved (unanimously): i. To agree amendments to the Counterparty list, which highlighted changes in Capita’s (Council’s Treasury Adviser) credit criteria, within Appendix B of the officer’s report. These are summarised below:- - Name ‘smaller’ building societies with an asset value greater than £5billion; and; - Show the limits for ‘smaller’ building societies meeting these criteria. ii. To add equity investment in the Local Capital Finance Company, the legal entity of the UK Municipal Bonds Agency, to non-specified investments within the Council’s investment strategy. iii. To agree changes to the estimated Prudential & Treasury Indicators for 2014/15 to 2017/18, inclusive, as set out in Appendix G of the officer’s report. iv. To approve a capital investment of up to £50,000 in the equity share capital of the Local Capital Finance Company; and; v. To delegate the final decision on investment to the Head of Finance in consultation with the Executive Councillor for Finance and Resources. vi. To include additional capital expenditure of £220,000, funded by borrowing, to the capital plan, for the additional capital cost of the Clay Farm Community Centre.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
This project was considered by the Customer and Community Services Committee in January 2012 and the Executive Councillor approved that the project should proceed. The project has reached the stage where tenders have been received to build the new Community Centre. Due to build cost inflation the budget for the project has increased significantly although the increased contribution required from the Council is more marginal. This is because of the partnership nature of the project and because funding for the project comes from a number of sources, much of which is building cost index linked. Nevertheless, as the project has reached a key point and in view of the budget variation it was felt appropriate for the Committee to scrutinise the project again at this stage.
Recommendations
The Executive Councillor is recommended to approve the revised budget for the project of £10,950,000.
Report Page No: 1 3. Background
The City Council is leading the partnership project to provide the new multi- use Community Centre at the heart of Clay Farm. The Community Centre will sit on City Council land and therefore the City Council is the lead partner. Other partners include the local General Practice backed by the NHS; the County Council; and bpha (Affordable Housing provider). A representative from Trumpington Residents Association is part of the partnership Project Group.
Situated at centre of the Southern Fringe Growth site, the Clay Farm Community Centre will be a high profile building that reflects the Council’s objectives to promote high quality and sustainable development. By the time the Centre is built in Spring 2016 about 40% (2000) of the new homes on the Southern Fringe will be occupied.
The following facilities were required to be provided in the new Clay Farm Community Centre from the outset of the project.
• a community centre: comprising a multi-use hall with sprung floor, suitable for performance and exhibition, and flexible meeting rooms • a community café large enough to be viable • a youth wing with games area, band & DJ room, and space for craft activities. • a public library with internet access and areas for lending and reading materials • a health centre with consultation rooms for eight general practitioners, flexible spaces for primary care support services, waiting areas, and a minor surgery suite • residential accommodation – up to 20 affordable flats • touchdown facilities and accommodation for police and social services and other providers • car parking for essential staff and emergency vehicles with external areas for community use
The Design Code for this part of the Southern Fringe development calls for a building of between three and five storeys in this location. In order to achieve the height and stature required the concept for the building is for the community facilities to occupy the ground and first floors; the Health Centre to occupy the second floor; with the Affordable Housing units on floors three and four.
The following approvals have been agreed to-date;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.