Joint Development Control Committee - Cambridge Fringes decided this item on Wednesday 17 June 2015. Below is the council's own wording, with the papers it was decided on.
Resolved (by 13 votes to 0 with 2 abstentions) to grant the application for planning permission in accordance with the officer recommendation, for the reasons set out in the officer report, and subject to the amended conditions recommended by the officers.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
Report to Joint Development Control Committee - Cambridge Fringes
Appendices
Ref Title A Plan Pack 1. SITE DESCRIPTION/AREA CONTEXT
1.1The site is approximately triangular in shape, measures 0.83 hectares and lies on the southern edge of Trumpington village immediately to the east of the Glebe Farm development, known for marketing purposes as Novo. That development is nearing completion and will comprise 287 dwellings and incorporate open space, allotment provision and associated landscaping.
1.2Along the northern edge runs a track which provides access to Glebe Farmhouse from Exeter Close and Shelford Road beyond. To the east is a recent development of 13 townhouses (Trumpington Place) and to the south is the Addenbrookes Access Road (AAR).
1.3The site is broadly flat and devoid of planting with the exception of a mature hedgerow running along the northern boundary track and some of the buffer planting along the AAR. The site was formerly in agricultural use but in recent months the site has been used as a materials store in connection with the adjacent Glebe Farm residential development.
1.4This extension to the main Glebe Farm site did not come forward at the same time as the main Glebe Farm development as it is currently under different ownership (Cambridgeshire County Council) and at that time the County Council were considering developing the site as a Household Waste Recycling Centre. The situation has changed in recent years and the site is now proposed for residential development by Countryside Properties, the master developers for the rest of Glebe Farm and Clay Farm.
1.5The application is being brought to the Joint Development Control Committee (JDCC) in accordance with the Scheme of Delegation because of the number of third party objections raised.
2. THE PROPOSAL
2.1The application has been submitted as a detailed proposal (full application) as was the case for the main Glebe Farm development, but this is for a much smaller scheme on land not previously subject to an application for residential development. As this is an application for full planning permission, a separate S106 agreement will be required to make the scheme acceptable in planning terms if permission is granted and this is currently being progressed in parallel.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Joint Development Control Committee - Cambridge Fringes at Cambridge and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.