Decision of the Executive Councillor for Housing: i. Noted the content of the Officer’s report. Scrutiny Considerations. This item was requested for pre-scrutiny. The Committee received a report from the Head of Estate and Facilities. The report referred to the new Heat Network (Metering and Billing) Regulations 2014 and the impact on Cambridge City Council’s housing stock. Investigations had identified that the Council owned six properties affected by these regulations and these had all been reported to the National Measurement Office as required by the new legislation. Technical and financial feasibility testing had been carried out on four of these sites and no further work was currently required. Two remaining sites at Ditchburn Place and School Court were due for substantial refurbishments in the next 12-24 months and heating systems at both would be revised as necessary to comply with the legislation. In response to questions from the Committee, the Head of Estate and Facilities stated the following: i. The Council currently had a two year contract for the provision of energy supplies. Corporately the Council obtained a really good energy provision deal because of the amount of energy that was used. In large residential complexes some people used a lot of energy and others used less, without a separate meter it was difficult to determine an individual’s usage. The Committee: Resolved unanimously to approve the recommendation. The Executive Councillor for Housing approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted). No conflicts were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
This paper has been prepared, as requested at the Housing Scrutiny Committee meeting held on 10 March 2015 in order to further inform members about the impact of the new Heat Network (Metering and Billing) Regulations 2014 on Cambridge City Council’s housing stock.
Investigations have identified that the Council owns six properties affected by these regulations and these have all been reported to the National Measurement Office as required by the new legislation.
Technical and financial feasibility testing has been carried out on four of these sites and no further work is currently required. Two remaining sites at Ditchburn Place and School Court, are due for substantial refurbishments in the next 12-24 months and heating systems at both will therefore be revised as necessary to comply with the legislation as part of that work.
Recommendations
The Executive Councillor and Scrutiny Committee members are asked to note the content of this report.
Background
The Heat Network (Metering and Billing) Regulations 2014 came into force on the 18th December 2014. The new regulations transfer into law certain Report Page No: 1 articles from the EU Energy Efficiency Directive 2012 and have been established to contribute towards the achievement of the EU 2020 20% reduction target on energy efficiency.
The legislation is designed to ensure better control of communal energy systems wherever practical. The Government states that the regulations will: Give individual consumers control over the cost of heating and cooling set minimum requirements surrounding the billing of consumers; and improve consistency and efficiency, alongside promoting the roll out and better management of heating and cooling networks.
In practical terms this means that existing communal energy systems have to be checked and, subject to pre-prescribed technical feasibility and cost effectiveness calculations, then individual metering may have to be installed. In terms of any future work, either when a new connection to an existing network is made, or when an existing building undergoes major renovation, then individual metering will also be required as part of the work.
There are three deadlines associated with the new regulations:
31st December 2014 – Accurate billing information (where technically possible and economically justified) requirements come into force. 30th April 2015 – Heat Suppliers (in this case Cambridge City Council as landlord) required to notify the relevant Government’s National Measurement Office of any sites with communal energy supplies where the regulations might apply. CCC have complied with this requirement 31st December 2016 – Deadline for completion of technical and financial feasibility tests and installation of viable sub-metering where required.
The following properties within the CCC housing stock benefit from communal energy systems and are therefore affected by the new regulations. Details of all sites have already been reported to the National Measurement Office (who is the scheme administrator and enforcing body):
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.