Decision of the Executive Councillor for Housing: i. Approved the revisions to the Three Year Rolling Programme 2015/16 to 2017/18 in the context of the wider social housing programme. Scrutiny Considerations The Committee received a report from the Head of Strategic Housing. The report provided a review of the Three Year Rolling programme and specifically sought approval of a revised Three Year Rolling programme which included sites to be investigated in 2015/16 to 2017/18. The report set the context for the approval to the revised three year programme in the context of: - The delivery of social housing through the planning system - The new Council social housing programme. In response to questions from the Committee, the Head of Strategic Housing stated the following: i. Not every large rear garden was able to be developed. ii. Each development would be considered on a case by case basis but a check would be required to make sure the processes being followed were reasonable. The Committee: Resolved unanimously to approve the recommendation. The Executive Councillor for Housing approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted). No conflicts were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
In July 2014, the Executive Councillor for Housing approved a three year rolling programme of housing sites in the Council’s ownership for consideration for development, redevelopment or disposal.
This report provides a review of the programme and specifically seeks approval of a revised Three Year Rolling programme that includes sites to be investigated in 2015/16 to 2017/18.
The report sets this request for approval to the revised three year programme in the context of;
the delivery of social housing through the planning system the new Council social housing programme
Recommendations
The Executive Councillor is recommended:
To approve revisions to the Three Year Rolling Programme 2015/16 to 2017/18 in the context of the wider social housing programme.
Background
Over the last twenty years most new social housing has been delivered by Registered Providers (RPs) working with house-builders and developers through the planning system. Following a relaxation on some financial constraints through ‘self-financing’ the Council has taken the opportunity to provide some balance to this through the implementation of its own new Council House building programme. Report Page No: 1 As the main provider of housing in Cambridge, the reasons why the Council has its own programme are as follows;
Provide additional social housing to meet the shortfall in Cambridge and to replace the loss of housing through the Right to Buy.
Replace some of the Council’s existing housing that no longer meets current day standards and is becoming less popular with residents.
Build new house types that will better meet the overall mix of social housing needed in the future.
Improve the energy efficiency of the Council’s housing.
The following table summarises the number of Council and Registered Provider housing completed since 2006.07 and the number estimated to be completed in 2015.16.
The following tables shows the Council schemes completed in 2014.15 and those due to complete in 2015.16.
2014.15 Units Latimer Close 12 Stanesfield Road 4 Anstey Way Drying Area 1 Total 17
Report Page No: 2 2015.16 Units Campkin Road 20 Colville Road 25 Barnwell Road 12 Aylesborough Close 20 Water Lane 14 Wadloes Road 9 Atkins Close 12 Hawkins Road 9 Ekin Road 6 Fulbourn Road 8 Total 135
A further 161 units have been approved to be provided by the Council on the Quad and Homerton schemes and the next phase of garage and infill site developments.
The new housing provided by Registered Providers in 2014.15 is largely made up of schemes on the Southern fringe growth sites and CB1. The estimates for 2015.16 again relate mainly to the Southern fringe schemes.
Three Year Rolling Programme
The Three Year Rolling Programme is made up of Council sites brought forward each year for consideration for development, redevelopment or disposal. The annual review keeps members appraised of progress with sites and offers the opportunity to introduce new sites for investigation.
Appendix 1 provides an update of the schemes within the Three Year Rolling Programme that are already under investigation.
Appendix 2 is the revised Three Year Rolling Programme that is requested to be approved.
Once sites have been investigated and if they are considered feasible and viable proposed schemes are brought to Committee to gain scheme specific approval to commence the development.
(a) Financial Implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.