Review of Capital Plan Processes and Procedures

Approved Committee 2 papers

Council approved this item on Thursday 23 July 2015. Below is the council's own wording, with the papers it was decided on.

Item15/98/CNLc

Resolved

Resolved (by 26 votes to 0) to: i. Approve a Capital Feasibility Fund of £35,600 in 2015/16, funded from a ‘top-sliced’ 5% of net capital funding available, with delegated authority for allocation of these funds given to the CPB in conjunction with the s151 officer. ii. Approve placing all current projects on the General Fund capital plan that do not produce a full business case by 30 November 2015 on to the PUD list, i.e. remove approved funding and require these projects to come forward for funding once a full business case has been approved .
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Council

Executive summary

Mid-year Financial Review (MFR) 2014 and Budget Setting Report (BSR) 2015 highlights the need to improve existing capital plan processes.

This report builds on Phase 1 of the review of the capital plan which examined existing projects in order to release internal funding (e.g. Direct Revenue Funding (DRF), R&R, capital receipts etc.). It also identified projects that were not ready for delivery, no longer required, or were not true capital projects. Projects not ready for delivery were placed on a new Projects Under Development (PUD) list and will be brought forward for prioritisation against available funding when a business case and delivery plan has been developed.

Phase 2 of the review proposes detailed changes to the process whereby new projects come forward and existing projects move from the PUD list for approval and inclusion on the General Fund capital plan.

Recommendations

The Executive Councillor is recommended:

- to approve the establishment of a Capital Programme Board (CPB) officer group, to be convened by the Head of Finance (HoF) with delegated Report Page No: 1 authority to approve project appraisals (full business case) for capital projects up to £300k, subject to changes to the Council’s existing delegations (see Appendix A)

- to approve the changes identified in Appendices B and C for ‘other’ capital approval processes

- to recommend Council to approve a Capital Feasibility Fund of £35,600 in 2015/16, funded from a ‘top-sliced’ 5% of net capital funding available, with delegated authority for allocation of these funds given to the CPB in conjunction with the s151 officer.

- to approve the appointment of a capital accountant/programme manager, funded from existing resources, to implement the proposed changes detailed in this report.

- to recommend Council to approve placing all current projects on the General Fund capital plan that do not produce a full business case by 30 November 2015 on to the PUD list, i.e. remove approved funding and require these projects to come forward for funding once a full business case has been approved.

Background

3.1As part of the MFR 2014 the HoF proposed a review of the capital plan to address its size and complexity. A number of concerns were identified, including the:

• Capacity to deliver projects to time, cost and quality; • Dependency on revenue funding; and • Inclusion of items, such as unallocated funds, projects at an early stage of development, and items more properly treated as small enhancements or maintenance spend.

3.2There was a further commitment in the BSR 2015 to develop the work started within Phase 1 of the review, which examined existing projects in the General Fund capital plan and moved certain projects onto a Projects Under Development (PUD) list, where they could be brought forward for funding once properly developed.

Method

3.3As part of Phase 2 of the review, two officer groups were set up to consider the current process. The first was a technical group, with input from accountancy, internal audit and procurement and the second, key stakeholders, including the Head of Finance. A number Report Page No: 2 of similar issues appeared across both groups and these helped shape the new process.

3.4A number of variations to the main capital approval processes were recognised, such as s106 devolved decision making, the Housing capital plan and capital programmes such as the Environmental Improvements Programme (EIP).

Further discussion with officers involved in the other capital approval processes is summarised with recommendations in Appendices B and C.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CapitalPlanProcessCommitteereportwithAppendicesSRJuly2015 /98/CNLcReport 545 KB DownloadRead as text
PDF
Review of Capital Plan Processes and ProceduresReport 53 KB Download

At this meeting

Whole meeting

Who was there

39 of 42 attended
MA
Councillor Margery AbbottCommittee Member, present
MA
Councillor Mark AshtonCommittee Member, present
YA
Councillor Ysanne AustinCommittee Member, present
NA
Councillor Nicholas AveryCommittee Member, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
TB
Councillor Tim BickCommittee Member, present
GB
Councillor Gerri BirdCommittee Member, present
KB
Councillor Kevin BlencoweCommittee Member, present
RC
Councillor Rod CantrillCommittee Member, present
RD
Councillor Robert DrydenCommittee Member, present
NG
Councillor Nigel GawthropeCommittee Member, present

All 42 on the meeting page

On this subject at Cambridge

Search all
  1. Review of Capital Plan Processes and ProceduresThis decision
  2. Review of Capital Plan Processes and ProceduresApproved
  3. Joint Capital Cycleways Programme ReviewNoted
  4. Environmental Improvement Capital Programme ReviewAgreed
  5. Environmental Improvement Programme Capital Programme ReviewNoted
  6. Cycleways Joint Capital Programme ReviewRefused

More from Cambridge Council

All decisions
MeetingDecisionOutcome
16 Jul 2026 Local Government ReviewFollowing a vote, 12 members voted to note the report, 16 voted against noting the report and 8 abstained. It was con... Noted Open
16 Jul 2026 Councillor Hauk:Improving Accountability and Transparency on Unadopted Residential DevelopmentsRESOLVED to adopt the following motion: Council notes: That many residents move into new developments expecting to be... Approved Open
16 Jul 2026 Councillor Toye Scott: Rights of the River Cam 2026RESOLVED to adopt the following motion: 1 Declaration of the Rights of the River Cam This council declares that the R... Approved Open
16 Jul 2026 Councillor Ashton: Darwin Nurseries and Farm ShopResolved (unanimous) to approve the Darwin Nurseries and Farm Shop Motion. Approved Open
16 Jul 2026 Councillor Baigent: Planning ArrangementsRESOLVED to adopt the following motion: This Council commits to keep building more council homes to the highest quali... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies