Environmental Improvement Capital Programme Review
AgreedScrutiny1 paper
Community Services Scrutiny Committee agreed this item on Thursday 16 October 2014. Below is the council's own wording, with the papers it was decided on.
Decision The report provided a review of the Environmental Improvement Capital Programme’s performance over its four year extension period, 2011/12-2014/15. The review included a breakdown of the various local improvement schemes, including local highway projects, delivered through the programme to date; and the pipeline of schemes remaining to be delivered by March 2016. With the current programme budget ending March 2016, the report outlines the need to consider an extension of the programme for a further agreed period, as part of the corporate budget setting process. Decision of Executive Councillor for City Centre and Public Places The Executive Councillor resolved: i. to note the Environmental Improvement Capital Programme schemes delivered over the period 2011-2014; ii. to note the Environmental Improvement Capital Programme schemes scheduled to be delivered over the period 2014 -2016; iii. to consider making provision, as part of the corporate budget setting process, for an extension of the Environmental Improvement Capital Programme; and iv. to consider making provision, as part of the corporate budget setting process, of a new dedicated budget to support the match funding of local highway schemes under Cambridgeshire County Council’s Local Highway Improvement Programme. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Street and Open Spaces regarding the environmental improvement capital programme review . The Committee resolved unanimously to endorse the recommendation. The Executive Councillor approved the recommendation.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1This report provides a review of the Environmental Improvement Capital Programme’s performance over its four year extension period, 2011/12-2014/15. The review includes a breakdown of the various local improvement schemes, including local highway projects, delivered through the programme to date; and the pipeline of schemes remaining to be delivered by March 2016. With the current programme budget ending March 2016, the report outlines the need to consider an extension of the programme for a further agreed period, as part of the corporate budget setting process.
Recommendations
The Executive Councillor is recommended:
2.1To note the Environmental Improvement Capital Programme schemes delivered over the period 2011-2014
2.2To note the Environmental Improvement Capital Programme schemes scheduled to be delivered over the period 2014 -2016
2.3To consider making provision, as part of the corporate budget setting process, for an extension of the Environmental Improvement Capital Programme
Report Page No: 1 2.4 To consider making provision, as part of the corporate budget setting process, of a new dedicated budget to support the match funding of local highway schemes under Cambridgeshire County Council’s Local Highway Improvement Programme
Background
3.1The Council’s Environmental Improvement Capital Programme (EIP) was established in 2005/6, as an initial five year programme, to provide each of the four Area Committees with a delegated annual capital budget for local public realm improvements. Following a review in 2011, the initial five year programme was extended for a further four years, ending 31 March 2015. The programme is funded by and forms part of the Council’s Capital Programme.
3.3The Council provided an annual budget of £523,000 per annum over the initial five year programme period, to be apportioned between each of the four Area Committees, based on their respective population sizes. This annual budget provision was reduced to £200,000 per annum for the extended four year programme period, 2011/12-2014/15. By the end of the initial five year period, the programme budget had a balance of £600,000, which was carried forward and included in the extended programme budget.
3.4Under the devolved management system, each Area Committee determines which schemes to fund using the adopted eligibility criteria detailed in appendix A. Schemes are submitted for Area Committee consideration from a range of sources including local groups and organisations, Councillors and officers. Once an Area Committee approves a scheme for programme funding, staff in the Council’s Streets and Open Spaces service are tasked to lead its development and delivery, including any associated feasibility, business planning, stakeholder consultation and legal consent work.
3.5Under the initial five year programme, the Council’s staff costs associated with providing this project management service was met by taking a 20% top slice of the annual programme budget. In 2011/12, with the reduction in annual programme budget from £532,000 to £200,000 per annum, the ‘top slicing’ facility for staff costs was removed. The Streets and Open Spaces project management service now receives a General Fund budget allocation of £82,000, which covers the costs of 2 full-time equivalent (FTE) project officers.
Report Page No: 2 3.6 In addition to the EIP, the Streets and Open Spaces project management service also manages the delivery of the following other elements of the Council’s Capital Programme:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.