Cambridge City Council
Strategy and Resources Scrutiny Committee, Monday 12 October 2015 at 5.00pm

Cultural Trust Project - Review of Implementation

Approved Scrutiny 1 paper

Strategy and Resources Scrutiny Committee approved this item on Monday 12 October 2015. Below is the council's own wording, with the papers it was decided on.

Item15/78/SR

Resolved

Decision The report detailed the post implementation review of the Cultural Trust project. Decisions of the Leader i. Approved that the Transformation Programme Office report to the Members Working Group with findings from its Post Implementation Review. ii. Approved that the Transformation Programme Office implement lessons learnt from the Post Implementation Review to current and future projects. iii. Approved that future reports on Cambridge Live were made to the Executive Councillor for Communities; and the Community Services Scrutiny Committee iv. That the Members Working Group shared information with members of Strategy and Resources Scrutiny Committee. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Transformation Programme Manager. The Committee made the following comments in response to the report: i. Commented that it was good news that a process had been put in place for lessons to be learnt from past experience and that progress reports would in future be delivered to the Community Services Scrutiny Committee. ii. Questioned whether the information that the Members Working Group discussed could be shared with the rest of the Committee members. The following additional recommendation was proposed 2 (d) The Members Working Group shared information with members of Strategy and Resources Scrutiny Committee. On a show of hands the additional recommendation was agreed unanimously. The Committee unanimously resolved to endorse the recommendations. The Leader approved the recommendation. Conflicts of Interest Declared by the Leader (and any Dispensations Granted): Not applicable.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Background

3.1Overview

Report Page No: 1 On 1 April 2015, Council staff working at the Cambridge Corn Exchange, Cambridge Folk Festival and other city events transferred to a new charity set up by the Council called Cambridge Live..

The project was successfully delivered on time and budget. Some monies (125k) where given to Cambridge Live in advance of go live as it had no budget or income but this is being schooled in on payback basis

3.2Post Implementation Review The Councils Transformation Programme Office is carrying out a Post Implementation Review on this project to review the project in terms of benefit realisation, lessons learnt/applied and were the objects set out for this project met.

Extensive work is being carried out to engage with key stakeholders involved in the Cambridge Live project to capture the information set out above. The lessons learnt/applied in terms of delivering a project of this kind are deemed to be a valuable output of this report. Areas that are being discussed include capacity and capability requirements/assessments, governance/decision making, and project management compliance.

It is recommended the Post Implementation Review be shared with the Members Working Group set up to advise this project and the lessons learnt/applied used by Transformation Programme Office to influence current and future projects

3.3Working Members Group A Working Members Group was in place during the design and delivery of the Cambridge Live project. It is recommended to reconvene this group to discuss the Post Implementation Review and to seek approval to closing this project.

It is proposed to have the Project Sponsor (Liz Bisset – Director Customer & Community Services), Project Manager (Debbie Kaye – Head of Communities, Arts & Recreation) ,Transformation Programme Manager (Brian O’Sullivan) and Working Members Group in attendance at this meeting, with attendance by other officers as appropriate.

A nomination will be sought from the Leader of the Opposition to replace former Councillor Andy Blackhurst.

3.4Future Reporting

As Cambridge Live is now operational it is deemed that all future reports should go to Community Services Scrutiny for decision by the Executive

Report Page No: 2 Councillor for Communities as this role has responsibility for the delivery of Community, Arts & Recreation.

A report on the Cambridge Live project in year 1 will go to the Executive Councillor for Communities and will go to Community Scrutiny committee on 14th Jan if approval is given. This will include an overview of all topics including a review of the city event programme.

Cambridge Live will be holding its AGM on 30th September and it is open to the public

4. Implications

None (a) Financial Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cultural Trust Project: Review of ImplementationReport 82 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 11 attended
RR
Councillor Richard RobertsonChair, present
AS
Councillor Ann SinnottVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy, Transformation, Finance and ResourcesCommittee Member, present
RC
Councillor Rod CantrillCommittee Member, apologies, sent representative
JH
Councillor John HipkinCommittee Member, present
VH
Councillor Valerie HoltCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
CS
Councillor Catherine SmartReserve, present as substitute

On this subject at Cambridge

Search all
  1. Cultural Trust Project - Review of ImplementationThis decision
  2. Arrangements to establish The Cultural Trust (The Leader)Agreed
  3. Arrangements to Establishment The Cultural TrustApproved

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies