Procurement of the Council’s Electricity and Gas Supplies

Agreed Scrutiny 2 papers

Strategy and Resources Scrutiny Committee agreed this item on Monday 12 October 2015. Below is the council's own wording, with the papers it was decided on.

Item15/79/SR

Resolved

Decision The report outlined the different options available to the Council to procure the Council’s energy supplies from 2016. Decisions of the Executive Councillor for Finance and Resources i. Agreed Option 5 for the City Council to enter into a “call-off” contract for the purchase of energy supplies under the terms of the Eastern Procurement Purchasing Organisation (ESPO) energy framework and delegate the final choice of tariff to the Director of Customer & Community Services, in consultation with the Executive Councillor and Head of Finance, with priority given to use of Green Energy Tariffs subject to costs being broadly comparable with alternative sources. ii. Agreed a contract period for the provision of electricity for four years with an option to review or change tariff each October, subject to prevailing market conditions and advice from ESPO at the time. iii. Agreed a contract period for the provision of gas for three years with an option to review or change tariff each October, subject to prevailing market conditions and advice from ESPO at the time. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Head of Estates and Facilities. The Committee noted the revised recommendation sheet that had been circulated in advance of the meeting (which related to item ii and iii above). The Committee made the following comment in response to the report: i. Questioned what the difference in cost was between green and non-green energy. In response to the Members’ question the Head of Estates and Facilities said the following: i. The difference in cost between green and non-green energy on current usage was approximately £2000. The Committee unanimously resolved to endorse the revised recommendations. The Executive Councillor approved the recommendation. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted): Not applicable.
Word for word from the decision Cambridge published for this meeting. Source: democracy.cambridge.gov.uk

Follow this further

Built from Cambridge's papers

What the report saysPro

Report to Strategy and Resources Scrutiny Committee

Cambridge City Council Item

To: Councillor George Owers : Executive Councillor for Finance and Resources Report by: Trevor Burdon : Head of Estates & Facilities Relevant scrutiny Strategy & Resources 12/10/2015 committee: Wards affected: Abbey Arbury Castle Cherry Hinton Coleridge East Chesterton King's Hedges Market Newnham Petersfield Queen Edith's Romsey Trumpington West Chesterton

RE-PROCUREMENT OF THE COUNCIL'S ELECTRICITY AND GAS SUPPLIES EFFECTIVE FROM 2016 Key Decision

1. Executive summary 1.1 There is a requirement to re-procure the Council’s energy supply contracts in 2016 (gas from 1st April and electricity from 1st October). This report outlines the different options available to the Council.

1.2Energy markets are increasingly complex and Central Government guidance recommends that, wherever possible, all public sector organisations take advantage of energy supply framework contracts. These are designed to procure large volume single supply contracts at more favourable rates than would be possible if partner organisations such as the City Council procured independently.

1.3The appropriate consortium framework for Local Authority use in this instance is Eastern Shires Purchasing Organisation (ESPO) and it is this organisation that is recommended for use by the City Council in this report.

2. Recommendations The Executive Councillor is recommended to approve:

i) Option 5 for the City Council to enter into a “call-off” contract for the purchase of energy supplies under the terms of the Eastern Procurement Purchasing Organisation (ESPO) energy framework. The final choice of tariffs to be delegated to the Director of Customer & Community Services, in consultation with the Executive Councillor and Head of Finance, with priority given to use of Green Energy

Report Page No: 1 Tariffs subject to costs being broadly comparable with alternative sources.

ii) an initial contract period for the provision of ELECTRICITY of two years with options to extend for two further periods of one year each subject to prevailing market conditions and advice from ESPO at the time;

iii) an initial contract period for the provision of GAS of two years with an option to extend for one further period of one year subject to prevailing market conditions and advice from ESPO at the time.

3. Background 3.1 Cambridge City Council spending on gas and electricity in 2014/15 was approximately £1,260,000. The current gas contract expires on 31st March 2016 and is worth approximately £260,000 per annum. The current electricity contracts expire on 30th September 2016 and are worth approximately £1,000,000 per annum in total.

3.2The energy supply market is both volatile and complex and requires specialist expertise to obtain best value. The Council, therefore, currently employs an independent energy consultancy, Utilitywise PLC, to procure its energy supply contracts and to provide some support with account management.

3.3There are various options open to the Council in order to procure replacements for these contracts when they expire. These are summarised below:

i. Option 1 – Do nothing. When the current contracts expire all sites would automatically transfer onto emergency rate tariffs but these are not competitive and would therefore be very expensive. This option would therefore not offer value for money.

ii. Option 2 – Direct procurement. The Council could procure its energy supplies directly without the involvement of any third party specialist consultant advice. The markets and tariff options are complex, however, and this would involve a lot of internal officer time to draft tender documentation and manage an OJEU compliant procurement process which would be necessary due to the value of contract involved. There is no guarantee that this option would deliver any significant benefits and, due to a lack of specialist expertise in the market, it is unlikely that the outcome may would be the best available. Accordingly this is not the preferred option.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Procurement of the Council’s Electricity and Gas SuppliesReport 83 KB DownloadRead as text
PDF
SR 12 Oct 2015 CCC Energy procurement: Amendment /79/SRReport 47 KB Download

At this meeting

Whole meeting

Who was there

11 of 11 attended
RR
Councillor Richard RobertsonChair, present
AS
Councillor Ann SinnottVice-Chair, present
DB
Councillor Dave BaigentCommittee Member, present
JB
Councillor Jeremy BensteadCommittee Member, present
TB
Councillor Tim Bick Lib Dem Spokes for Strategy, Transformation, Finance and ResourcesCommittee Member, present
RC
Councillor Rod CantrillCommittee Member, apologies, sent representative
JH
Councillor John HipkinCommittee Member, present
VH
Councillor Valerie HoltCommittee Member, present
PS
Councillor Peter SarrisCommittee Member, present
MS
Councillor Martin SmartCommittee Member, present
CS
Councillor Catherine SmartReserve, present as substitute

On this subject at Cambridge

Search all
  1. Procurement of the Council’s Electricity and Gas SuppliesThis decision
  2. Procurement of Contract for Electricity Supply 2024-28Approved

More from Cambridge Strategy and Resources Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2025 Cambridge City Council Performance Management FrameworkDecision This proposal sets out the new approach the Council will use to manage its performance. It will be a part of... Approved Open
31 Mar 2025 Combined Authority UpdateDecision This was a regular report to the Strategy & Resources Scrutiny Committee providing an update on the activiti... Noted Open
31 Mar 2025 Cambridge Delivery Company: Update ReportDecision The report updated Members of Strategy and Resources Committee on the recent developments with Central Gover... Noted Open
31 Mar 2025 CIP Loan FacilityDecision The council has acted in the past as the development debt provider to fund the development of regeneration a... Agreed Open
31 Mar 2025 Cambridge Leisure Development ProposalDecision of Executive Councillor for Finance and Resources Approved the Officer’s recommendations. Reason for the Dec... Approved Open