Community Services Scrutiny Committee noted this item on Thursday 14 January 2016. Below is the council's own wording, with the papers it was decided on.
Decision The Officer’s report provided: i. An update on the work of the review to date and outline proposals for the next steps of the information gathering exercise. ii. Headline findings from the audit of city-wide community facilities. Decision of Executive Councillor for Communities i. Noted the headline findings of the city-wide community facilities audit. ii. Agreed the next steps as identified in section 3.6 of the Officer’s report. Reason for the Decision As set out in the Officer’s report. Any Alternative Options Considered and Rejected Not applicable. Scrutiny Considerations The Committee received a report from the Community Funding and Development Manager. In response to Members’ questions the Community Funding and Development Manager said the following: i. There had been 68 returns to the audit, 50 facilities were run by charity organisations and another 2 by voluntary groups. ii. 22 churches had responded to state they provided community facilities. They were required to register as charities as a result of a change to the law. iii. Officers could provide headline details of responses currently. They would identify further detail to report back to area committees in future. iv. Officers were drawing up stakeholder engagement plans. Details would be made available through community centres and the council website. The Committee unanimously resolved to endorse the recommendations. The Executive Councillor approved the recommendations. Conflicts of Interest Declared by the Executive Councillor (and any Dispensations Granted) No conflicts of interest were declared by the Executive Councillor.
Word for word from the decision Cambridge published for this meeting.Source: democracy.cambridge.gov.uk
1.1To provide an update on the work of the review to date and outline proposals for the next steps of the information gathering exercise.
1.2To provide headline findings from the audit of city-wide community facilities.
Recommendations
The Executive Councillor is recommended to:
2.1Note the headline findings of the city-wide community facilities audit.
2.2Agree the next steps identified in section 3.6 of this report.
Background
3.1In October 2015 this committee considered a report on the strategic review of community provision and the Executive Councillor for Communities agreed the approach to the review to include: An evidenced-based, strategic assessment of community provision to achieve agreed outcomes The scope of the work to include City Council run centres, community development resource and support for communities, other community facilities, major growth sites, County Council Report Page No: 1 libraries and the Council’s Digital Transformation and Customer Access strategies The establishment of a project team with engagement from other stakeholders A work programme considering current provision, need, opportunity, and future focus containing the following components: - An audit of facility provision which will also support the requirements for the interim arrangements for s106 and Community Infrastructure Levy (CIL) requirements - An analysis with partners of community and population requirements - Anti-poverty and Digital Transformation Strategy support requirements - Opportunity for collaboration with Property Services and other stakeholder such as the Library Service
3.2The outcomes for this review are: Stronger communities (e.g: inclusive, connected, resilient, vibrant, good places to live) Council resources are targeted to known need Savings – with a focus on reducing net cost by opportunity for further efficiency and generating increased income with the possibility of redirecting resources
3.3A project team has been established including representatives from Communities, Arts and Recreation, Internal Audit, Corporate Strategy, Customer Services, and others will be involved to cover areas of expertise as required.
3.4City-wide community facilities audit
The initial audit has been started and the methodology for this work was as follows:
Definition of community facilities For the purpose of the survey we used the following: Community facilities are buildings that are available for use by the wider local community, and/or for hire by local groups for a range of community/social activities and meetings, for at least some of their opening hours each week.
List of facilities A list was compiled using data from existing databases, planning and other research material. 149 venues where emailed the survey (including our own centres and 35 schools that had rooms Report Page No: 2 for hire or wider community activities taking place). Venues without an email address or an invalid email address were sent the survey by post and an additional 28 schools had the form posted for them to verify community access to their premises.
Survey design To maximise the use of the information the survey was compiled in three sections to cover current use, current capacity and future development. Survey Monkey was used to enable efficient reporting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Hobson’s Brook Corridor 10 Year VisionDecision Hobson’s Brook Corridor is an important green infrastructure corridor extending between the natural spring a...
Allocation of Sharing Prosperity FundDecision The Council has an Anti-Poverty Strategy, which sets out a range of ongoing and new actions to address pover...
S106 Public Art and Public Realm IssuesDecision One of the ways in which the Council has mitigated the impact of development in Cambridge is through public ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.